Cabinet, Tuesday 23 June 2026 at 4.00pm

Hampton Vivacity Premier replacement Air Handling Unit (AHU) and Changing room refurbishment

Agreed Executive 1 paper

AI summaryCabinet approves £800,000 air handling unit replacement and changing room refurbishment at Vivacity Premier, with up to £250,000 from reserves for temporary changing facilities during a 12 week closure.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedR G Carter Cambridge Ltd appointed for AHU and changing room work
Money£800,000 capital, up to £250,000 revenueCapital already in programme; revenue from Innovation and LGR reserve
What happens nextWorks complete by April 2027Temporary changing facility hired for 12 weeks
Who it affectsVivacity Premier users and operatorSwimming pool and changing rooms closed for 12 weeks

What was decided

Cabinet approved the direct appointment of R G Carter Cambridge Ltd via the Pagabo Medium Construction Works Framework Lot 2 for AHU replacement and changing room refurbishment at Vivacity Premier, within the existing £800,000 capital allocation. Report P2, 2.10

Cabinet approved up to £250,000 from the Innovation and LGR reserve to fund a temporary changing facility for the 12 week closure. Report P6, 2.6, 7.2

Cabinet delegated authority to the Executive Director of Place and Economy to take all steps needed, including contract variations and extensions, and to agree the temporary changing facility hire. Report P3, P5, P7

Why

The existing air handling system is past its operational life and has caused condensation, mould and short unplanned closures, with a mechanical and electrical survey recommending full replacement. Report P8, 2.1, 2.2, 2.3

Carrying out the changing room refurbishment at the same time as the AHU replacement shares preliminary costs, avoids duplicate effort and requires only one facility closure. Report 2.4, 3.2

The new system will improve functionality, meet new regulations and be more environmentally friendly, supporting the council's priority to manage land and buildings efficiently. Report 5.2, 5.3, P27

What happens next

Construction works are to be concluded by April 2027. Report 4.1

A temporary changing facility will be hired for approximately 12 weeks so the pool can remain in use during the closure. Report 2.6, 2.7, P17

A carbon impact assessment will be carried out before construction works begin, and social value will be assessed as part of the tender quality evaluation. Report 5.4, 7.6

The money

  • £800,000 Capital allocation for AHU replacement and changing room refurbishment, already in the Property Capital Programme Report 2.5
  • up to £250,000 Revenue funding for temporary changing facility hire during the 12 week closure, to be funded from reserves (Innovation and LGR reserve) Report P6, 2.6, 7.2
  • £100,000 Budget allocation for the external multi-disciplinary organisation acting as Principal Designer, Contract Administrator and Cost Management, already in the Property Capital Programme Report 2.9, 7.3

Options considered

  • Rejected: Delay the replacement of the air handling unit. Persistent operational issues and breakdowns have caused unplanned closures, operational losses and reputational risk Report 3.1, 7.5
  • Rejected: Do not carry out the changing room refurbishment at the same time. Doing the work together shares preliminary costs, avoids duplicate effort and needs only one facility closure Report 3.2

Implications

  • Financial: No additional capital funding is required; the £800,000 and £100,000 allocations are already in the Property Capital Programme. An unbudgeted revenue pressure of up to £250,000 will be met from reserves. Report 2.5, 7.2, 7.3
  • Legal: Procurement will follow the Council's Contract Rules; the framework was procured under the Public Contracts Regulations 2015 and the framework rules have been followed for the direct award. Report 2.10, 8.1
  • Climate: The new system is expected to be more environmentally friendly and a carbon impact assessment will be carried out before construction. Report 5.3, 7.6
  • Risk: Failure to replace the AHU would lead to ongoing high maintenance costs, breakdowns, unplanned closures and reputational damage. Report 7.5
  • Other: Social value will be a requirement of the quality assessment in the tender exercise. Report 5.4

Who and where

  • Users of Vivacity Premier Fitness, particularly swimmers, who will use a temporary changing facility for 12 weeks Report 2.6, 2.7, P17
  • The operator of the centre, who has agreed the closure period Report 2.6, P32
  • Council taxpayers, as the works are funded from existing capital and reserves Report 2.5, 7.2

Timeline

  • Jan 2023 to Jan 2027: Pagabo Medium Construction Works Framework Lot 2 period Report 2.10
  • 2026 (planned capital programme): Replacement system scheduled as part of the capital programme Report 2.3
  • April 2025: Mechanical and electrical engineer commissioned to undertake a validation survey of the existing systems Report 2.1
  • 23 June 2026: Cabinet decision to appoint the contractor and approve revenue funding Report P4
  • 12 weeks (temporary changing facility hire period): Temporary changing facility to be hired so the pool can stay in use Report 2.7, P17
  • by April 2027: Works to be concluded Report 4.1

Plain English for the jargon

  • AHU: Air Handling Unit, the system that regulates and circulates air in the building
  • Pagabo Medium Construction Works Framework Lot 2: A framework for projects of £500k to £1,000,000, procured under the Public Contracts Regulations 2015
  • CDM regulations: Construction Design and Management regulations covering health and safety duties on construction projects
  • LGR reserve: Local Government Reorganisation reserve, a council reserve proposed as the funding source here
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Cabinet unanimously agreed to: 1. Approve the direct appointment of R G Carter Cambridge Ltd via the PAGBO Medium Construction Works Framework Lot 2 Projects of £500k - £1,000,000 for the delivery of works relating at Vivacity Premier as outlined in this report within the approved budgetary allowance of £800,000. 2. To approve delegated authority to the Executive Director of Place and Economy (in consultation with the Executive Director of Corporate Services and Director of Legal and Governance to take all such steps necessary to deliver the recommendations above, including any variation(s), or an extension of the contract period that may be required. 3. To approve the use of reserves to fund the revenue implications of up to £250,000 for the purpose of delivering a temporary changing facility for the 12-week closure. 4. Delegate authority to the Executive Director of Place and Economy (in consultation with the Executive Director of Corporate Services) to take all such steps necessary to agree a hire agreement for the purposes of delivering the temporary changing facility, including the contract award, variation, and extension of the contract if required.
Word for word from the decision Peterborough published for this meeting. Source: democracy.peterborough.gov.uk

Follow this further

Built from Peterborough's papers

What the report saysPro

Report to Cabinet

Recommendations

It is recommended that Cabinet:

1. Approve the direct appointment of R G Carter Cambridge Ltd via the PAGBO Medium Construction Works Framework Lot 2 Projects of £500k - £1,000,000 for the delivery of works relating at Vivacity Premier as outlined in this report within the approved budgetary allowance of £800,000.

2. To approve delegated authority to the Executive Director of Place and Economy (in consultation with the Executive Director of Corporate Services and Director of Legal and Governance to take all such steps necessary to deliver the

179 23 June Cabinet

recommendations above, including any variation(s), or an extension of the contract period that may be required.

3. To approve the use of reserves to fund the revenue implications of up to £250,000 for the purpose of delivering a temporary changing facility for the 12-week closure.

4. Delegate authority to the Executive Director of Place and Economy (in consultation with the Executive Director of Corporate Services) to take all such steps necessary to agree a hire agreement for the purposes of delivering the temporary changing facility, including the contract award, variation, and extension of the contract if required.

1. Purpose / Reason for Decision 1.1 The purpose of this report is to seek approval to appoint R G Carter Cambridge Ltd via the Pagabo Framework to deliver the replacement of the air handling unit at Vivacity Premier Fitness, together with associated changing room refurbishment works, and to approve the related revenue funding and delegated authority necessary to implement the project. These decisions are requested to address ongoing operational issues with the existing plant and facilities, safeguard service continuity, and enable the works to be delivered in a coordinated and cost-effective manner during a single planned closure period.

2. Background and key issues

2.1In April 2025 a Mechanical and electrical engineer was commissioned to undertake a validation survey of the existing changing room heating, ventilation and cooling systems following a number of issues raised by the public and the operator.

2.2At the time there was increased levels of condensation occurring within the changing rooms and to the surface finishes, which has in turn led to mould growth occurring to the suspended ceilings. Due to the increased condensation levels and mould the operator closed the centre for a short period of time to enable repairs to be undertaken.

2.3The investigation concluded that the system was past its operational life span and in order to permanently resolve the issues, noted by the operator, a replacement system should be installed. A recommendation was provided to replace the system as part of the planned capital programme scheduled for 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hampton Vivacity Premier replacement Air Handling Unit (AHU) and Changing room refurbishmentReport 196 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
DS
Councillor Dr Shabina Qayyum Leader of the CouncilChair, present
NB
Councillor Neil Boyce Deputy Leader and Cabinet Member for Adult ServicesVice Chair, present
ZA
Councillor Zameer Ali Cabinet Member for Communities and Public SafetyCommittee Member, present
KC
Councillor Katy Cole Cabinet Member for Children and Young PeopleCommittee Member, present
AE
Councillor Angus Ellis Cabinet Member for TransportCommittee Member, present
CH
Councillor Christian Hogg Cabinet Member for Regulatory Services and EnforcementCommittee Member, present
NA
Councillor Numan Ali Iqbal Cabinet Member for Growth and RegenerationCommittee Member, present
MJ
Councillor Mohammed Jamil Cabinet Member for Finance & Corporate GovernanceCommittee Member, present
AS
Councillor Ann Shaheed Cabinet Member for Public Health, Homelessness and PovertyCommittee Member, present
CW
Councillor Chris WigginCommittee Member, present

More from Peterborough Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Peterborough Local Plan Proposed Submission Version - Key/06APR26/01Cabinet unanimously RESOLVED to: 1. Approve the Proposed Submission (‘Publication Draft’) Local Plan as attached at A... Approved Open
25 Aug 2026 Youth Guarantee TrailblazerCabinet unanimously RESOLVED to: 1. Approve acceptance of £600,000 grant funding from the Cambridgeshire and Peterbor... Approved Open
25 Aug 2026 Care and Repair - Cabinet Report for a New Open Framework for the Delivery of Disabled Facilities Grants (DFG), Minor and Major Home Adaptations, and the Provision of Aids and Adaptations under the Care Act 2014Cabinet unanimously RESOLVED to: (1) Approve the award of framework agreements under the new Care and Repair Open Fra... Approved Open
25 Aug 2026 Goods Shed (Fletton Quays) DisposalCabinet unanimously RESOLVED to: 1. Authorise the disposal of the Goods Shed on the terms set out in Exempt Annex 2 o... Agreed Open
25 Aug 2026 Approval to deliver the construction phase of the sports quarter leisure developmentCabinet unanimously RESOLVED to: 1. Approve acceptance and use of the £20,000,000 grant from the Department of Busine... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies