Agreed that - (1) a Compulsory Purchase Order resolution is made (in the event that it is required) for properties within North Prospect, defined as - (a) Woodhey Road (1 – 83 (odds) and 2 – 56 (evens)); (b) Ham Drive (26 and 28); (c) Laurel Road (28 – 48 (evens)); (d) North Prospect Road (157 – 195 (odds) and 170 – 202 (evens)); (e) Foliot Road (46 – 84 (evens)); (f) North Prospect Primary School and Children’s Centre site; (g) Electricity Sub-station, Cookworthy Road; as set out in decisions (2) and (3) below - (2) the Council make a Compulsory Purchase Order pursuant to Section 17 of the Housing Act 1985, in respect of the areas outlined in red on the plan submitted; (3) t he Cabinet specifically notes the considerations that arise under the Human Rights Act (1998) in respect of the proposed Compulsory Purchase Order, and has had full regard to the rights of those that would be affected by the Compulsory Purchase Order but, for the reasons set out in the report, determines nevertheless to authorise the Compulsory Purchase Order procedure.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
This report seeks approval to make Compulsory Purchase Orders (CPO), in the future, if necessary, as part of the first phase of the North Prospect Regeneration project. It relates to those parts of the estate which are to be demolished, to ensure that the land ownership is unified and to enable clear title to be provided to Plymouth Community Homes. The circumstances in which we would be making a Compulsory Purchase Order would include the failure to buy a freehold or leasehold property by agreement, or the need to deal with covenants or secure other interests in the land. This action will only be taken where all other negotiated approaches fail. This request relates to the first sites identified in the Master Plan which includes demolition and rebuilding as the method of achieving regeneration and decent homes. These properties are within the estates transferred to Plymouth Community Homes as part of the Housing Stock Transfer on 20 November 2009. These are defined on the maps at annex 1 and particularly properties in:
a. Woodhey Road (1 – 83[odds] & 2 – 56[evens]) b. Ham Drive (26 & 28) c. Laurel Road (28 – 48[Evens]) d. North Prospect Road (157 – 195[Odds] & 170 – 202[Evens]) e. Foliot Road (46 – 84[Evens]) f. North Prospect Primary School and Children’s Centre site g. Electricity Sub-station, Cookworthy Road Corporate Plan 2010-2013 as amended by the four new priorities for the City and Council:
North Prospect Regeneration contributes to a range of corporate priorities but most importantly supporting Council and city priorities; Delivering Growth and Reducing Inequality. Within the housing transfer Plymouth Community Homes are committed to develop a master plan and work towards a solution to deliver decent homes across its housing stock.
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
Provision has been made within the Housing Stock Transfer Agreement for Plymouth Community Homes to meet the costs of acquisition and associated home loss compensation, disturbance and legal costs.
Other Implications: e.g. Section 17 Community Safety, Health and Safety, Risk Management, Equalities Impact Assessment, etc.
Project and risk management form part of the Programme Board arrangements between Plymouth City Council, Plymouth Community Homes, and the Homes and Communities Agency.
Recommendations & Reasons for recommended action: It is recommended that the Cabinet:
make a Compulsory Purchase Order resolution (in the event that they are required) for properties within North Prospect defined as:
h. Woodhey Road (1 – 83[odds] & 2 – 56[evens]) i. Ham Drive (26 & 28) j. Laurel Road (28 – 48[Evens]) k. North Prospect Road (157 – 195[Odds] & 170 – 202[Evens]) l. Foliot Road (46 – 84[Evens]) m. North Prospect Primary School and Children’s Centre site n. Electricity Sub-station, Cookworthy Road
As follows:
Resolved that, the Council make a Compulsory Purchase Order pursuant to S17 of the HA 1985 in respect of the areas outlined in red on the plan submitted
The Cabinet specifically notes the considerations that arise under the Human Rights Act (1998) in respect of the proposed CPO and has had full regard to the rights of those that would be affected by the CPO but, for the reasons set out in this report, determines nevertheless to authorise CPO procedure.
2 Alternative options considered and reasons for recommended action:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.