Agreed that in the event that a Compulsory Purchase Order is required for properties within Phase 3 of North Prospect defined as – ? 9 Mavisdale ; ? 1,11,12,14,20,22,29,32,33,35,42,44,46,48,52,56,60,62,64,68, Wordsworth Road; ? 3,26,30,38,65 Wordsworth Crescent; a Compulsory Purchase Order is made pursuant to Section 17 of the Housing Act 1985, in respect of the areas outlined in red on the plan submitted (appendix one).
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
Subject: Compulsory Purchase Order Resolution for the Regeneration of Phase 3 North Prospect Committee: Cabinet Date: 7 July 2015 Cabinet Member: Councillor Penberthy CMT Member: Anthony Payne (Director for Place) Author: Paul Barnard Assistant Director of Strategic Planning and Infrastructure Contact details Tel: 01752 304077 email: [email protected] Ref: N/A Key Decision: No
Part: I
Purpose of the report: This report seeks approval to make a Compulsory Purchase Order (CPO) in the future, if necessary, as part of the third phase of the North Prospect regeneration project. This request relates to properties that were within the estate transferred to Plymouth Community Homes (PCH) as part of the Housing Stock Transfer on 20th November 2009.
Approval for CPO is being sought by PCH under provisions laid out in schedule 24 of the Housing Stock Transfer Agreement (see appendix 2), to ensure that landownership within Phase 3 of the development is unified and clear title can be provided to the developer to enable the proposed redevelopment to take place. The circumstances in which the Council would be making a CPO would include the failure to purchase a freehold or leasehold property by agreement with the owner, or the need to deal with covenants or secure other interests in the land. This action would only be taken where all other negotiated approaches fail. A similar resolution to make a CPO was approved by Cabinet for Phases 1 and 2 of the development, most recently on14th August 2012, and in both those cases a CPO was not required as all properties were acquired by PCH through negotiation.
The properties that would fall within the boundaries of the CPO for Phase 3 are located within the following streets and shown on a plan in appendix 1:
a. 9 Mavisdale b. 1,11,12,14,20,22,29,32,33,35,42,44,46,48,52,56,60,62,64,68, Wordsworth Road c. 3,26,30,38,65 Wordsworth Crescent
The Brilliant Co-operative Council Corporate Plan 2013/14 -2016/17:
The regeneration of North Prospect contributes to a number of the Council’s corporate priorities, most specifically Growing Plymouth and Confident Plymouth. This is being achieved by demolishing existing properties that are in poor repair, and refurbishing existing properties where repairs are cost effective and by building a range of new properties for sale and rent. This is likely to improve both the quality of life and the health of the residents living in the improved houses. In addition improved community facilities have been created in the area, with the construction of a ‘community hub’ building known as the Beacon, which provides a new library, early years children’s centre, community café and kitchen, community hall, shops and office space.
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
Provision has been made within the Housing Stock Transfer Agreement for PCH to meet the costs of acquisition and associated home-loss compensation, disturbance and all legal costs associated with purchasing a replacement property or any future CPO action that might be required. Therefore there is no direct cost implication for the Council.
Other Implications: e.g. Child Poverty, Community Safety, Health and Safety and Risk Management:
The regeneration of North Prospect will have the long term effect of reducing rates of child poverty within the neighbourhood by replacing older housing which is expensive to heat with modern, energy efficient property, achieving level 4 of the Code for Sustainable Homes. This will result in more affordable utility bills for residents and also help improve the health of occupants by reducing the occurrence of illnesses linked to cold and damp housing. In addition changing the tenure mix of the neighbourhood by introducing new homes for open market sale and low cost homeownership will help raise levels of aspiration for all residents in this area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.