Plymouth City Council
Cabinet, Tuesday 27 March 2012 at 2.00pm

Approve the Strategic Direction of a Replacement Materials Recycling Facility Service or Facility

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 27 March 2012. Below is the council's own wording, with the papers it was decided on.

Item148

Resolved

Agreed to approve the strategic direction and procurement parameters of a MRF service solution utilising either a new or existing facility located within or outside Plymouth being taken forward into a formal procurement for a replacement MRF solution capable of recycling glass.
Word for word from the decision Plymouth published for this meeting. Source: democracy.plymouth.gov.uk

Follow this further

Built from Plymouth's papers

What the report saysPro

Report to Cabinet

PLYMOUTH CITY COUNCIL

Subject: Approve the strategic direction of a replacement Materials Recycling Facility (MRF) service or facility. Committee: Cabinet Date: 27 March 2012 Cabinet Member: Councillor Michael Leaves CMT Member: The Director for Place Author: Barry Ashbee; Waste Project Manager Contact: Tel: 01752 304953 email: [email protected] Ref: CM 01-11/03

Key Decision: Yes Part: Part I

Executive Summary: Plymouth City Council (PCC) Cabinet have endorsed plans to deliver a kerb side glass recycling service across the city by April 2014 through the introduction of glass into the current commingled dry recyclate (green bin) kerbside collection waste stream. The collected recycling material is currently delivered to an existing Materials Recycling Facility (MRF) at Chelson Meadow which is not capable of processing collected commingled recyclates containing glass. This existing MRF, being over 11 years old, is also beyond its economic design life and will require renewal in the near future.

This Strategic MRF Project has been initiated to secure a replacement MRF service and/or facility to safeguard and further uplift recycling performance (previously estimated at approximately 4%) once glass has been introduced into the kerbside commingled collection waste stream as of 2014.

In order to inform the options to be considered and ensure that any procurement is well aligned to both the market place and corporate expectations, an early market sounding exercise was approved and formally undertaken in October 2011 through a soft market test approach. This soft market test responses together with wider operational intelligence subsequently informed which options merited further consideration in the form of a high level options appraisal and comparative cost analysis.

This report summarises the appraisal work undertaken and notes the strategy that a MRF service solution utilising either a new or existing facility located within or outside Plymouth, be taken forward into a formal Competitive Dialogue procurement process. This strategy includes Plymouth City Council exploring, through the procurement, the value for money consideration of using its own capital resources and/or assets if a new MRF is constructed.

Corporate Plan 2012 – 2015: The Strategic MRF Project and the associated recommendations made in this report will directly contribute to the delivery of one of the Council’s medium term outcome measures of improving household waste recycling rates by allowing glass to be collected at the kerbside and sorted along with other recycling materials.

Page 1 of 6 A replacement MRF service and/or facility will enable glass to be collected at the kerbside which will also contribute to the Council’s medium term outcome measure of reducing inequality by allowing residents who are currently unable to access bottle bank sites to be able to recycle their glass thereby provide better access to recycling services.

Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land A summary of the financial costs associated with progressing the procurement phase are set-out in the Part I background report and will be allocated in accordance with the Council’s constitution and scheme of delegation.

It is also intended that existing Council waste infrastructure and land assets are made available to bidders as part of the procurement for consideration in their proposed solutions.

Subsequent to the procurement phase, the definitive resource implications including finance, human, IT and land for awarding the contract and delivering the project will be prepared and presented to Cabinet requesting approval to award the contract.

Other Implications: e.g. Community Safety, Health and Safety, Risk Management and Equality, Diversity and Community Cohesion:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approve the Strategic Direction of a Replacement Materials Recycling Facility Service or FacilityReport 78 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
RB
Councillor Richard BallMember, present
IB
Councillor Ian BowyerMember, present
TF
Councillor Ted FryVice-Chair, present
GJ
Councillor Glenn JordanMember, expected
ML
Councillor Michael LeavesMember, present
SL
Councillor Samantha LeavesMember, present
GM
Councillor Grant MonahanMember, present
VP
Councillor Vivien PengellyChair, present
SR
Councillor Steven RickettsMember, present
KW
Councillor Kevin WigensMember, apologies

More from Plymouth Cabinet

All decisions
MeetingDecisionOutcome
14 Sep 2026 Net Zero Action Plan 2026-29Purpose of report The report seeks the approval of the Net Zero Action Plan (NZAP) 2026 - 2029 prior to publication, ... Approved Open
14 Sep 2026 Proposed Public Spaces Protection Order (PSPO) for Alcohol Restriction, linked to Anti-Social Behaviour (ASB) within the CityPurpose of report The purpose of this report is to seek approval to extend the City-Wide Public Spaces Protection Ord... Approved Open
24 Aug 2026 Civic Centre Phase 1 Contract Award and City College Agreement to LeasePurpose of report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprof... Approved Open
24 Aug 2026 Local Government Association Corporate Peer ChallengePurpose of report The Council commissioned the Local Government Association (LGA) to undertake a Corporate Peer Chall... Decided Open
24 Aug 2026 SEND Sufficiency Strategy and Delivery PlanPurpose of report This report presents the SEND Sufficiency Strategy for Plymouth and seeks approval for the next pha... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies