Agreed that – 1. due to the delay to the expansion of Holy Cross Catholic Primary School, Cabinet vary the proposals of Wave II by the addition of ‘bulge’ years at Montpelier Primary School, St Mary’s CE Infant School and Victoria Road Primary School; an extra class of 30 pupils (additional to the PAN) at each school, allocated to one year group, which move through the schools’ year groups until the pupils’ transition to the secondary phase. 2. Cabinet approve the in-year expansion of Pilgrim Primary and Lipson Vale Primary Schools’ PANs for reception age pupils; and : · approves the public consultation on the statutory proposals to expand the above two schools; and · authorises the Cabinet Member for Children and Young People, in consultation with the Director for People, to consider the outcomes and responses to any statutory notices, published as part of statutory school organisation processes, and in light of them to make a final determination on proposals. 3. Cabinet recommend Council to amend the Capital Programme to include the allocations for Waves III and IV of £2.657 million as set out in Section 6 of this report. 4. Cabinet recommend Council to amend the Capital Programme to include the allocations for condition, of £3 million as set out in Section 8 of this re port.
Word for word from the decision Plymouth published for this meeting.Source: democracy.plymouth.gov.uk
PLYMOUTH CITY COUNCIL Subject: Services for Children and Young People Basic Need Programme Committee: Cabinet Date: 27 March 2012 Cabinet Member: Councillor Samantha Leaves (Children and Young People) CMT Member: Carole Burgoyne (Director for People) Authors: Jayne Gorton (School Organisation, Access and Services to Schools Manager) Gareth Simmons (Programme Director for Learning Environments) Contacts: Tel: 01752 307472 Email: [email protected] Tel: 01752 307161 Email: [email protected] Ref: MC.JEG(CAB)01(01/03/12) Key Decision: Yes Part: One ______________________________________________________________
Executive Summary: In October 2010, March 2011 and in October 2011, Cabinet received reports on the rising numbers in primary schools and the developing need for primary school places in the city. This growth in demand is known as ‘basic need’. This report seeks to update members on the progress of the growth and report on the development of the Wave I and Wave II projects set out in the March and October Cabinet reports. This report also seeks authorisation to vary the proposals of Wave II in the light of development work and the results of public consultation, and continue to develop the projects in a manner that meets the Council’s legal obligations. The report sets out proposals for the development of Wave III and IV projects, to meet the increased number of primary age pupils with effect from September 2013 and September 2014; to seek authorisation to commence consultation with stakeholders on expanding schools for 2013 onwards; and to commence consultation on the statutory proposals for the expansions as appropriate. The report also sets out the balance between the Council’s obligation to meet basic need and to maintain the condition of schools. Consequently, the report seeks Cabinet‘s recommendation to Council to amend the Capital Programme in order to meet these obligations. Waves I and II of the Basic Need programme are both delivering on or under the cost allocated in the Capital programme and are progressing well. Due to concerns, raised during consultation, over access and the amount of available external play space, a delegated decision has been taken by the Cabinet Member for Children and Young People to delay the expansion of Holy Cross Catholic Primary School, formerly in Wave II, outside of the current planned waves. To compensate for this delay, it is proposed that for September 2012: Montpelier Primary, St Mary’s CE Infant School and Victoria Road Primary Schools introduce a ‘bulge’ year; an extra class of 30 pupils (additional to the PAN) allocated to one year group, which moves through the school’s year groups until the pupils’ transition to the secondary phase. There have been two recent announcements regarding the establishment of Free Schools in the city. The Marine Academy Plymouth is developing proposals for a two Forms of Entry (FE) primary school, i.e. PAN 60, and Plymouth College of Art have announced proposals for an all-through (5 to 16) school; the proposal is for 300 primary pupils and 600 secondary pupils. This provision has also been taken into account in the forecasting. Proposals for Waves III and IV include bulge years and expansions. The two schools listed below, would be required to increase their Planned Admission Numbers (PANs) for reception admissions in September 2013 for permanent expansion.
September
Additional Places per Proposed Current PAN
PAN
Year 2013 Name of School Pilgrim (Community) Primary School (Wave III) 30 60 30 Lipson Vale (Community) Primary School (Wave III) 55 60 5
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.