Resolved
Agreed to r ecommend the Tamar Bridge and Torpoint Ferry Joint Committee’s 2016/17 Revenue Estimates and Capital Programme to Full Council for approval.
Cabinet agreed this item on Tuesday 12 January 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed to r ecommend the Tamar Bridge and Torpoint Ferry Joint Committee’s 2016/17 Revenue Estimates and Capital Programme to Full Council for approval.
The Tamar Bridge and Torpoint Ferry are operated, maintained and improved jointly by Plymouth City Council and Cornwall Council on a ‘user pays’ principle, being funded by toll income using powers derived from the Tamar Bridge Act. The finances of the joint undertaking are effectively ring- fenced by the Act, and it is operated as a self-financing business. In order to deliver its approved Business Plan 2015 – 2019 the undertaking needs authorisation from the parent authorities for revenue and capital expenditure.
The Tamar Bridge and Torpoint Ferry Joint Committee (TBTFJC) Terms of Reference require the Cabinets of the Joint Authorities to recommend TBTFJC’s budgets to their respective Full Councils.
The report presents the 2016/17 Revenue Estimates and Capital Programme report submitted to TBTFJC on 4 December 2015 and draft minutes recording TBTFJC’s endorsement.
The Brilliant Co-operative Council Corporate Plan 2013/14 -2016/17:
The Tamar Bridge & Torpoint Ferry links are key gateways to the City and provide opportunities for investment, jobs and growth particularly in the wider context of Plymouth as the regional economic centre.
Providing a safe well-maintained road network contributes to the economic well-being of the City, supporting the Council’s Growth priority.
Implications for Medium Term Financial Plan and Resource Implications: Including finance, human, IT and land
Revised Jul 2013 Finance – The proposed budgets will be funded from toll income, and based on assumed annual traffic growth of 1% from April 2016 to April 2019 no increases in toll charges are anticipated until 2019. Human – The budgets support the approved Business Plan 2015-2019 and this will be delivered by the existing organisation using its own staff, contractors and consultants, with support from the parent authorities. IT – The IT implications are restricted to incremental improvement of existing systems as part of the Business Plan and associated projects. Land – No land issues arising from this item.
Other Implications: e.g. Child Poverty, Community Safety, Health and Safety and Risk Management:
Risk Management – A risk register and mitigation measures are included within the Tamar Bridge and Torpoint Ferry Business Plan 2015-2019.
It should be noted that Plymouth City Council and Cornwall Council have reviewed the TBTFJC Business Plan, Business Continuity Management System and Risk Management Framework, and are content that the business continuity risks associated with TBTFJC are adequately covered.
Health and Safety – Key Performance Indicators within the Business Plan are designed to drive improvement.
There are no child poverty or community safety implications.
Equality and Diversity Has an Equality Impact Assessment been undertaken? Yes, these are provided within respective TBTFJC reports.
Recommendations and Reasons for recommended action:
That the Cabinet recommends TBTFJC’s 2016/17 Revenue Estimates and Capital Programme to Full Council for approval.
Alternative options considered and rejected:
The Business Plan 2015-2019 is designed to deliver safe, reliable and efficient crossings of the Tamar. The key priorites and delivery actions support the Plan and maintain established service delivery characteristics.The proposed budgets provide the resources to deliver the plan.
Asset maintenance has been designed to optimise service delivery and life cost.
Published work / information:
Tamar Bridge & Torpoint Ferry Joint Committee reports, 4 December 2015
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TAMAR BRIDGE AND TORPOINT FERRY JOINT COMMITTEE CAPITAL AND REVENUE BUDGET 2016/17Report | 74 KB | DownloadRead as text |
Follow Cabinet at Plymouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | Net Zero Action Plan 2026-29Purpose of report The report seeks the approval of the Net Zero Action Plan (NZAP) 2026 - 2029 prior to publication, ... | Approved | Open |
| 14 Sep 2026 | Proposed Public Spaces Protection Order (PSPO) for Alcohol Restriction, linked to Anti-Social Behaviour (ASB) within the CityPurpose of report The purpose of this report is to seek approval to extend the City-Wide Public Spaces Protection Ord... | Approved | Open |
| 24 Aug 2026 | Civic Centre Phase 1 Contract Award and City College Agreement to LeasePurpose of report The purpose of the report is to award the phase 1 contract for the Civic Centre works and to reprof... | Approved | Open |
| 24 Aug 2026 | Local Government Association Corporate Peer ChallengePurpose of report The Council commissioned the Local Government Association (LGA) to undertake a Corporate Peer Chall... | Decided | Open |
| 24 Aug 2026 | SEND Sufficiency Strategy and Delivery PlanPurpose of report This report presents the SEND Sufficiency Strategy for Plymouth and seeks approval for the next pha... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.