Resolved
RESOLVED that the contents of the report be noted.
Portchester Crematorium Joint Committee noted this item on Monday 16 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contents of the report be noted.
REPORT TO: PORTCHESTER CREMATORIUM JOINT COMMITTEE
ON: 16 MARCH 2015
REPORT OF: THE ENGINEER AND SURVEYOR
SUBJECT: BUILDING WORKS REPORT – 2014/5
Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1501 South Chapel – Minor Completed 2,900 2,900 Nil This work was completed over the Easter redecoration period as part of the budget for item 1505
1502 South Chapel – refurbishment Design stage 175,000 175,000 Nil See separate report to this meeting
1503 South Chapel – air Design stage 10,000 10,000 Nil Installation to be incorporated into the conditioning South Chapel refurbishment scheme
1504 Internal redecoration – rolling Assessing 5,000 5,000 Nil Works deferred until 2015/16 programme programme requirements to enable economies of scale
1505 Steam cleaning paving – Assessing 3,000 3,000 Nil Works deferred until 2015/16 programme rolling programme requirements to enable economies of scale
1506 Fence and gate works Completed 500 400 100 Minor cost variation due to change in scope of works
TCG 04.03.15 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1507 Waiting room toilet facilities Works being 8,800 8,800 Nil Works deferred until 2015/16 programme specified
1508 Water feature Assessing 3,000 3,000 Nil There is a need to re-evaluate the working requirements of the water feature and this will be the subject of a future report of the Joint Committee. Interim measures introduced to facilitate the features operation
1009 Works to Mess Room Works being 2,600 2,600 Nil Works to incorporate safety railing deferred specified until 2015/16 programme and these will be undertaken in the first quarter of the 2015/16 financial year.
1510 Crematory/Committal areas Assessing 9,000 9,000 Nil Works deferred until 2015/16 programme requirements to enable economies of scale
1511 Mercury abatement project – Implementation 9,500 9,500 Nil Acoustic grills delivered and detailed fixing sound attenuation arrangements being designed.
1512 Legionella risk assessment Completed 300 300 Nil Minor items of work have been report recommended and these will be undertaken in the first quarter of the 2015/16 financial year.
1513 Asbestos register Completed 500 500 Nil No actions requiring immediate attention were identified but a minor item of work will be undertaken in the first quarter of the 2015/16 financial year.
TCG 04.03.15 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1514 Fire risk assessment and Completed 600 600 Nil No comment register
Terry Garvey Engineer and Surveyor
Background List of Documents – Section 100D of the Local Government Act 1972 - None
TCG 04.03.15
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Engineer and Surveyor's Report: Planned Maintenance and Building Works Progress ReportReport | 187 KB | DownloadRead as text |
Follow Portchester Crematorium Joint Committee at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Dec 2021 | Minutes of the Meeting held on 20 September 2021RESOLVED that the minutes of the meeting held on the 20 September 2021 be signed as a correct record. | Decided | Open |
| 13 Dec 2021 | Finance Strategy and Budget for 2022/23RESOLVED (1) that the Finance Strategy 2022/23, attached as Appendix A to the report, be approved; (2) that the Finan... | Approved | Open |
| 13 Dec 2021 | Revenue Budget Report - 2022/23RESOLVED (a) That the capital works programme as detailed in Appendix D to the report be approved; (b) That the Joint... | Approved | Open |
| 13 Dec 2021 | Manager and Registrar’s ReportRESOLVED that the report be received and noted. | Noted | Open |
| 13 Dec 2021 | Building Repairs and Renewal ProgrammeRESOLVED that the contents of the report be noted and approved. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.