Resolved
RESOLVED that the contents of the report be noted.
Portchester Crematorium Joint Committee noted this item on Monday 14 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contents of the report be noted.
REPORT TO: PORTCHESTER CREMATORIUM JOINT COMMITTEE
ON: 14 DECEMBER 2015
REPORT OF: THE ENGINEER AND SURVEYOR
SUBJECT: BUILDING WORKS REPORT
2014/5/6 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1502/3 South Chapel – refurbishment Works part 205,000 205,000 Nil Works commenced and progressing completed satisfactorily. Anticipated completion December 2015 1504 Internal redecoration – rolling Works 20,000 20,000 Minus Works combined with 2015/16 programme programme completed. 12,290 to enable economies of scale. Works completed to the waiting rooms and the North Chapel foyer. Expenditure to date £7710, subject to confirmation.
1505 Steam cleaning paving – Works 6,000 1,000 Minus Works deferred until 2015/16 programme rolling programme completed. 5,000 to enable economies of scale. Minor area of works undertaken adjacent to North Chapel.
1508 Water feature Works 3,000 3,000 Nil Expenditure to date subject to completed. confirmation. There is a need to re-evaluate the working of the water feature and this will be the subject of a future report of the Joint Committee. 1509 Works to Mess Room Assessing 2,600 2,600 Nil Feasibility and costing exercise of works to requirements incorporate safety railing being undertaken.
TCG – 26.11.15 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1510 Crematory/Committal areas Assessing 9,000 9,000 Nil Investigation of new flooring to the requirements crematory to be progressed.
1511 Mercury abatement project – Complete 9,500 19,036 Plus 9,536 Acoustic grills installed and working sound attenuation satisfactorily. Final cost subject to confirmation. Increase largely due to unforeseen installation issues.
1601 Redecoration of North Chapel 10,000 See item1504. Budget now included in and Foyer item 1504
1602 External Redecoration – Order placed 5,000 1,000 Minus Works identified to the external North rolling programme 4,000 Cloister including remediation of leak
1603 Steam Cleaning Paving – 3,000 See item1505. Budget now included in rolling programme item 1505
1607 Internal Redecoration – rolling 5,000 See item1504. Budget now included in programme item 1504
1608 External Paving and Walls Assessing 0 1500 Plus 1,500 Area of defective paving and wall identified requirements for remedial work. Quotation to be obtained
Note
Items previous reported as completed are not shown
TCG – 26.11.15 2016/7 Ref Item Description Status Budget Anticipated Variation Commentary £ Cost £ £ 1701 Roofing Programme - Survey, Feasibility 50,000 50,000 Nil clearance and initial repairs
1702 External Redecoration Feasibility 60,000 60,000 Nil
1703 Paving Works cleaning and Feasibility 40,000 40,000 Nil repointing
1704 Staff Room Refurbishment Feasibility 2,500 2,500 Nil
1705 Internal Redecoration – Feasibility 3,000 3,000 Nil Charge & Cremation Room
1706 Internal Redecoration – South Feasibility 1,500 1,500 Nil Cloister Toilets
1707 Water Feature Review Feasibility 4,000 4,000 Nil
1708 Review compliance with Feasibility 4,000 4,000 Nil Disability Discrimination Act and provide new accessible door to the office 1709 Retendering of Building Feasibility 4,000 4,000 Nil Surveying Consultancy Total (for 169,000 169,000 Nil 2016/7)
Terry Garvey Engineer and Surveyor
TCG – 26.11.15
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Engineer and Surveyor's Report: Planned Maintenance and Building Works Progress ReportReport | 98 KB | DownloadRead as text |
Follow Portchester Crematorium Joint Committee at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Dec 2021 | Minutes of the Meeting held on 20 September 2021RESOLVED that the minutes of the meeting held on the 20 September 2021 be signed as a correct record. | Decided | Open |
| 13 Dec 2021 | Finance Strategy and Budget for 2022/23RESOLVED (1) that the Finance Strategy 2022/23, attached as Appendix A to the report, be approved; (2) that the Finan... | Approved | Open |
| 13 Dec 2021 | Revenue Budget Report - 2022/23RESOLVED (a) That the capital works programme as detailed in Appendix D to the report be approved; (b) That the Joint... | Approved | Open |
| 13 Dec 2021 | Manager and Registrar’s ReportRESOLVED that the report be received and noted. | Noted | Open |
| 13 Dec 2021 | Building Repairs and Renewal ProgrammeRESOLVED that the contents of the report be noted and approved. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.