Portsmouth City Council
Portchester Crematorium Joint Committee, Monday 14 March 2016 at 2.00pm

Engineer and Surveyor's Report - Planned Maintenance and Building Works Progress Report

Noted Committee 1 paper

Portchester Crematorium Joint Committee noted this item on Monday 14 March 2016. Below is the council's own wording, with the papers it was decided on.

Item678

Resolved

RESOLVED that the contents of the report be noted.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Portchester Crematorium Joint Committee

REPORT TO PORTCHESTER CREMATORIUM JOINT COMMITTEE ON 14 MARCH 2016 FROM THE ENGINEER AND SURVEYOR BUILDING WORKS REPORT Repairs & Repairs & Repairs & Repairs & Renewals Renewals Renewals Renewals Fund Budget Expenditure Status Commentary £ £ £ Balance 1.4.2015 200,000 Contribution from Revenue Account 2015/16 80,000 280,000

Proposed applications 2015/16 -1502-3 South Chapel refurbishment 205,000 216,926 In Progress -1508 Water Feature 3,000 4,700 In Progress Feasibility and costing exercise of works to incorporate safety railing undertaken. Order raised -1509 Works to Mess Room 2,600 Complete with Steel Services 20/1/16 and works now complete. -1510 Crematory / Committal areas Crematory / Committal Area – Site visits on the 16th February with manufactures of flooring 9,000 Feasibility material. Issue identified with suitability of materials proposed. Further discussion required. -1601 Internal redecoration – North Chapel and Foyer, WC 15,000 11,827 Complete Complete for 2015/16 Works identified to the external North Cloister -1602 External redecoration – rolling programme 5,000 805 Complete including remediation of leak, completed by T Coleborn -1603 Steam cleaning paving – rolling programme 3,000 543 Complete Complete for 2015/16 -1606 Renewal of white lining 2,000 675 Complete Complete for 2015/16 Quotation to Post budget preparation, Area of defective paving -1608 External Paving and Walls be obtained and wall identified for remedial work. 244,600

Estimated Balance 31.3.2016 35,400 Contribution from Revenue Account 2016/17 80,000 115,400

Continued overleaf Repairs & Repairs & Repairs & Repairs & Renewals Renewals Renewals Renewals Fund Budget Expenditure Status Commentary £ £ £ Proposed applications 2016/17 -1701 Roofing Programme - Survey, clearance and initial Repairs (see Capital Programme) Quotations being obtained for this work. -1702 External redecoration 60,000 -1703 Paving Works cleaning and repointing 40,000 -1704 Staff Room Refurbishment 2,500 -1705 Internal Redecoration – Charge & Cremation Room 3,000 -1706 Internal Redecoration – South Cloister Toilets 1,500 -1707 Water Feature Review 4,000 -1708 Review compliance with Disability Discrimination Act And Provide new accessible door to the office 4,000 115,000 Estimated Balance 31.3.2017 400

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Engineer and Surveyor's Report: Planned Maintenance and Building Works Progress ReportReport 78 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
SB
Councillor Susan BellCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
AS
Councillor Alan ScardCommittee Member, present
DW
Councillor Dennis WrightVice-Chair, in the Chair, present
TB
Councillor Tony BriggsCommittee Member, apologies due to council business
DG
Councillor David GuestCommittee Member, apologies
YW
Councillor Yvonne WeeksStanding Deputy, present as substitute
KE
Councillor Ken EllcomeCommittee Member, apologies
RN
Councillor Rob NewCommittee Member, apologies
LM
Councillor Lee MasonCommittee Member, present
JH
John HaskellClerk, expected

On this subject at Portsmouth

Search all
  1. Engineer and Surveyor's Report - Planned Maintenance and Building Works Progress ReportThis decision
  2. Retirement of Engineer and Surveyor & Deputy Engineer and Surveyor to the Joint Committee (Exempt Item)Noted
  3. Engineer and Surveyor's Report - Planned Maintenance and Building Works Progress ReportNoted
  4. Engineer and Surveyor's Report - Planned Maintenance and Building Works Progress ReportNoted
  5. Engineer and Surveyor's Report - Planned Maintenance and Building Works Progress ReportNoted
  6. Engineer and Surveyor's Report - Planned Maintenance Programme - Progress ReportNoted

More from Portsmouth Portchester Crematorium Joint Committee

All decisions
MeetingDecisionOutcome
13 Dec 2021 Minutes of the Meeting held on 20 September 2021RESOLVED that the minutes of the meeting held on the 20 September 2021 be signed as a correct record. Decided Open
13 Dec 2021 Finance Strategy and Budget for 2022/23RESOLVED (1) that the Finance Strategy 2022/23, attached as Appendix A to the report, be approved; (2) that the Finan... Approved Open
13 Dec 2021 Revenue Budget Report - 2022/23RESOLVED (a) That the capital works programme as detailed in Appendix D to the report be approved; (b) That the Joint... Approved Open
13 Dec 2021 Manager and Registrar’s ReportRESOLVED that the report be received and noted. Noted Open
13 Dec 2021 Building Repairs and Renewal ProgrammeRESOLVED that the contents of the report be noted and approved. Noted Open