Resolved
DECISION: T he Cabinet Member noted the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).
Education noted this item on Monday 9 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION: T he Cabinet Member noted the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).
1.1The purpose of this report is to provide an update on the progress of:
Urgent school condition projects Secondary school sufficiency schemes aimed at increasing secondary school place capacity within the city. Special school sufficiency schemes aimed at ensuring that schools can take children with more complex SEND.
1.2The quarterly budget monitoring report (also on this agenda) contains information in relation the financial position of the education capital programme.
2.1It is recommended that the Cabinet Member notes the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).
3. School modernisation (urgent condition) projects
3.1The urgent condition projects have been identified through Asset Management Plan meetings, condition surveys and recommendations by Education officers concerning the needs of specific pupils.
1 3.2 There are 4 "live" condition projects remaining in the 2017-18 programme (as reported at the February 2018 Cabinet Member meeting). All other approved urgent condition projects from 2017-2018 have been completed.
3.3There were 10 urgent condition projects approved in the 2018-19 programme at the start of the financial year, plus a contingency allowance for urgent emerging works (as reported at the March 2018 Cabinet Member meeting).
3.4Three additional urgent condition projects have been commissioned since the last report, funded from the contingency for urgent emerging works.
a) The Harbour School @ Fratton - A full condition survey of this building was undertaken in February 2018. The building is due to be vacated in October 2018, when The Harbour School @ Fratton moves to the new Harbour Vanguard Centre. At that time, there will be a corporate decision on the future use of the building, taking account of the condition survey findings. However, as a result of the condition survey, urgent works were instructed for health and safety reasons. These works related to support for corroded structural beams, and urgent works to prevent loose brickwork falling.
b) Craneswater Albert Annex - A full condition survey of this building was undertaken in February 2018. This building houses pupils with complex SEND requirements. Education and Property colleagues are determining a suitable and appropriate location for these pupils, taking account of the condition survey findings. However, as a result of the condition survey, urgent works were instructed for health and safety reasons. These works related to support for corroded structural beams and installation of standalone battery smoke detectors to all classrooms to meet fire safety requirements.
c) Fernhurst School - An inspection was undertaken in May 2018 following moisture leaking into the building. It was determined that the roof was in a reasonable condition, but the mortar to the inner leaf of the gable was in poor condition and requires urgent remedial works.
3.5In summary, the urgent condition projects currently in progress are:
2017-2018 modernisation programme - 4 projects 2018-2019 modernisation programme - 13 projects
3.6Risks to the progress of the individual projects, as detailed in Appendix A, have been updated. No new risks to the progress of the projects have emerged since the last report.
4. Secondary sufficiency schemes (phase 2)
4.1The Secondary School Place Strategy 2017-2023 outlined the immediate and medium-term pressures on secondary school places. The Strategy and
2 the feasibility studies informed the recommendations to address future sufficiency issues.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Copy of School Modernisation Programme: July 2018: Appendix A 19062018Appendix | 193 KB | Download |
PDF |
School Modernisation Programme 2018-2019Report | 166 KB | DownloadRead as text |
Follow Education at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jan 2020 | Education Portfolio Budget Monitoring Report for the Second Quarter 2019/20DECISION: The Cabinet Member for Education noted the Education Portfolio forecast revenue and capital budget position... | Noted | Open |
| 20 Mar 2019 | Willows Centre for Children - end of statutory consultation to close and reopen the Centre under Solent Academies TrustRecommendations The Cabinet Member: a) Considered the response to the statutory consultation carried out on the propo... | Approved | Open |
| 14 Feb 2019 | Dedicated Schools Grant 2018-19 Quarter Three Budget MonitoringDECISION: The Cabinet Member noted the projected year-end budget position for the Dedicated Schools Grant as at 31 De... | Noted | Open |
| 14 Feb 2019 | Education Portfolio Budget Monitoring Report for the Third Quarter 2018/19DECISION: The Cabinet Member noted the Education Portfolio forecast revenue and capital budget positions, as at the e... | Noted | Open |
| 14 Feb 2019 | School Modernisation Programme for the 3rd Quarter 2018 - 19DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects, the secondar... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.