Resolved
DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).
Education noted this item on Tuesday 11 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).
1.1The purpose of this report is to provide an update on the progress of:
Urgent school condition projects Secondary school sufficiency schemes aimed at increasing secondary school place capacity within the city Special school sufficiency schemes aimed at ensuring that schools can take children with more complex SEND.
1.2The quarterly budget monitoring report (also on this agenda) contains information in relation the financial position of the education capital programme.
2.1It is recommended that the Cabinet Member notes the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).
3. School modernisation (urgent condition) projects
3.1The urgent condition projects have been identified through Asset Management Plan meetings, condition surveys and recommendations by Education officers concerning the needs of specific pupils.
1 3.2 There are 4 "live" condition projects remaining in the 2017-18 programme. These 4 projects are expected to be completed by the next quarterly report. All other approved urgent condition projects from 2017-2018 have been completed.
3.3There were 10 urgent condition projects approved in the 2018-19 programme at the start of the financial year, plus a contingency allowance for urgent emerging works. Three additional urgent condition projects have been reported since the start of the financial year.
3.4Since the last report, one urgent condition project has been commissioned, funded from the contingency for urgent emerging works:
Cottage Grove - boiler replacement. The boiler failed the annual boiler service and due to its age and levels of corrosion could not be repaired. Therefore, a new boiler is being installed prior to the winter.
3.5The condition surveys for The Harbour School @ Fratton and the Craneswater Albert Annex, which were completed, have been removed from the projects in progress dashboard. Discussions are continuing regarding the future of these two buildings.
3.6In summary, the urgent condition projects currently in progress are:
2017-2018 modernisation programme - 4 projects 2018-2019 modernisation programme - 12 projects
3.6Risks to the progress of the individual projects, as detailed in the Progress dashboard at Appendix A, have been updated. No new risks to the progress of the projects have emerged since the last report.
4. Secondary sufficiency schemes (phase 2)
4.1The Secondary School Place Strategy 2017-2023 outlined the immediate and medium-term pressures on secondary school places. The Strategy and the feasibility studies informed the recommendations to address future sufficiency issues. The council has previously approved funding for school expansions.
4.2The progress of individual schemes, as detailed in Appendix A, has been updated.
4.3No risks to the progress of the projects have emerged since the last report.
4.4The Secondary School Place Strategy is being refreshed for 2018-2024, and a Primary Place Strategy 2018-2024 is being developed. These documents will inform future sufficiency schemes for mainstream schools.
2 5. Special school provision sufficiency schemes
5.1The council has previously approved funding for special school provision sufficiency schemes.
5.2The progress of individual projects, as detailed in Appendix A, has been updated. These projects were not targeted at increasing the number of places, but ensuring that the schools can take children with more complex SEND.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: School Modernisation Programme: September 2018Appendix | 194 KB | Download |
PDF |
School Modernisation and Sufficiency ProgrammeReport | 123 KB | DownloadRead as text |
Follow Education at Portsmouth and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jan 2020 | Education Portfolio Budget Monitoring Report for the Second Quarter 2019/20DECISION: The Cabinet Member for Education noted the Education Portfolio forecast revenue and capital budget position... | Noted | Open |
| 20 Mar 2019 | Willows Centre for Children - end of statutory consultation to close and reopen the Centre under Solent Academies TrustRecommendations The Cabinet Member: a) Considered the response to the statutory consultation carried out on the propo... | Approved | Open |
| 14 Feb 2019 | Dedicated Schools Grant 2018-19 Quarter Three Budget MonitoringDECISION: The Cabinet Member noted the projected year-end budget position for the Dedicated Schools Grant as at 31 De... | Noted | Open |
| 14 Feb 2019 | Education Portfolio Budget Monitoring Report for the Third Quarter 2018/19DECISION: The Cabinet Member noted the Education Portfolio forecast revenue and capital budget positions, as at the e... | Noted | Open |
| 14 Feb 2019 | School Modernisation Programme for the 3rd Quarter 2018 - 19DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects, the secondar... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.