MMD Update Review

Approved Executive 1 paper

Cabinet approved this item on Tuesday 26 February 2019. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

The Cabinet adopted Option 2 as their preferred option. 2. The Cabinet agreed that a loan facility of £15m be provided to MMD (subject to decisions 3, 4 and 5 below) for the necessary Capital Investment required to deliver a return of £19.3m over the 5 year period 2019/20 to 2023/24, which was approved in principle by City Council on 12 February 2019. 3. The Council loan is provided at a rate consistent with State Aid rules. 4. Any draw down on the loan facility by MMD is subject to the following: a) The 20 Year Business Plan demonstrates the continuing viability of MMD and that the continued operation of MMD continues to deliver the best financial return compared with all other viable alternatives. b) The Capital Investment is necessary either for the sustainability of existing income streams or for the generation of additional income. c) The proposed Capital Investment itself represents the most favourable return when assessed against the balance of: i ) The financial return on a Net Present Value basis and over the whole life of the asset created versus other potential options for the same outcome. ii) The relative risk of each alternative option. 5. Continued parent company support and the availability of the loan facility is subject to the annual review and approval of a satisfactory 3 Year Business Plan and 20 Year Future Forecast which must demonstrate to the shareholders satisfaction that: i ) The assumptions that underpin the 3 Year Business Plan are robust with a more than reasonable chance of being achievable. ii) That the 3 Year Business Plan is prepared to illustrate the financial effect of reasonable optimistic and reasonable pessimistic scenarios in order that the Shareholder is aware of the reasonable range of risk associated with the "Base Case" Business Plan. iii) Recognising the exposure of the company to cyclical trade factors and adverse weather, that the overall 3 to 5 Year financial results of the Company provide an overall net return to the Shareholder over the period taking into account all returns received by the Shareholder through rents, dues and all other profit elements of services provided by the Shareholder (including the Portsmouth International Port). 6. The Council keeps under review the returns that would reasonably be expected to be achieved from alternative uses of the site, undertaking a formal review at the earlier of every 3 years or failure to achieve the financial performance set out in resolution 5 above. 7. That there be an annual information report to Council setting out the financial position of MMD.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To consider the assessment of the available options for the use of the MMD site, based on a full options appraisal and financial evaluation (including risks) prepared over a 20 year period. Accordingly, to approve a preferred option.

Recommendations

2.1It is recommended that:

1. The Cabinet adopt Option 2 as their preferred option.

2. The Cabinet agree that a loan facility of £15m be provided to MMD (subject to recommendations 3, 4 and 5 below) for the necessary Capital Investment required to deliver a return of £19.3m over the 5 year period 2019/20 to 2023/24, which was approved in principle by City Council on 12 February 2019.

3. The Council loan is provided at a rate consistent with State Aid rules.

4. Any draw down on the loan facility by MMD is subject to the following:

a) The 20 Year Business Plan demonstrates the continuing viability of MMD and that the continued operation of MMD continues to deliver the best financial return compared with all other viable alternatives.

b) The Capital Investment is necessary either for the sustainability of existing income streams or for the generation of additional income.

www.portsmouth.gov.uk c) The proposed Capital Investment itself represents the most favourable return when assessed against the balance of:

i) The financial return on a Net Present Value basis and over the whole life of the asset created versus other potential options for the same outcome.

ii) The relative risk of each alternative option.

5. Continued parent company support and the availability of the loan facility is subject to the annual review and approval of a satisfactory 3 Year Business Plan and 20 Year Future Forecast which must demonstrate to the shareholders satisfaction that:

i) The assumptions that underpin the 3 Year Business Plan are robust with a more than reasonable chance of being achievable.

ii) That the 3 Year Business Plan is prepared to illustrate the financial effect of reasonable optimistic and reasonable pessimistic scenarios in order that the Shareholder is aware of the reasonable range of risk associated with the "Base Case" Business Plan.

iii) Recognising the exposure of the company to cyclical trade factors and adverse weather, that the overall 3 to 5 Year financial results of the Company provide an overall net return to the Shareholder over the period taking into account all returns received by the Shareholder through rents, dues and all other profit elements of services provided by the Shareholder (including the Portsmouth International Port).

6. The Council keeps under review the returns that would reasonably be expected to be achieved from alternative uses of the site, undertaking a formal review at the earlier of every 3 years or failure to achieve the financial performance set out in recommendation 5 above.

3. Context

3.1MMD is currently loss making following the loss of its largest customer but is now progressing through a transition phase, with a new management team and an evolving strategy of diversification. To survive, the company needs to adapt to a changing shipping market which is becoming increasingly containerised on larger vessels as well as diversifying its customer base. To adapt to these changing circumstances, a £15m investment is required over the next 10 years in the site and equipment. Prior to considering such an investment, a comprehensive review of all alternative options for the use of the site has been undertaken to evaluate whether the continued operation of MMD will deliver the best commercial return for the site for the level of risk involved. Additionally, the Council has commissioned an independent

www.portsmouth.gov.uk expert review of MMD's Business Plan to provide confidence that the evaluation of the continued operation of MMD is robustly based.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MMD Update ReviewReport 255 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
GV
Councillor Gerald Vernon-Jackson CBEChair, present
SP
Councillor Steve PittVice-Chair, present
DA
Councillor Dave AshmoreCommittee Member, present
BD
Councillor Ben DowlingCommittee Member, present
SH
Councillor Suzy HortonCommittee Member, present
DS
Councillor Darren SandersCommittee Member, present
JS
Councillor Jeanette SmithCommittee Member, present
LS
Councillor Lynne StaggCommittee Member, present
MW
Councillor Matthew WinningtonCommittee Member, present
RW
Councillor Rob WoodCommittee Member, present

More from Portsmouth Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... Noted Open
22 Sep 2026 Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... Approved Open
21 Jul 2026 Carbon Action PlansNoted the report which is for information and is not subject to call-in. Noted Open
21 Jul 2026 Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... Noted Open
21 Jul 2026 Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies