The Cabinet APPROVED: (1) That the business case and purpose for Hold Co be approved, including delegating authority to the Director Regeneration and City Solicitor in consultation with the s.151 officer to create a new subsidiary company to support the delivery of HRA projects with development management and project management services. (2) To note that the need for the creation of a fit-for-purpose Board of Directors for each of the incorporated Ravelin companies based around an understanding of the skillsets required to support the company in both a commercial and local authority environment. (3) That new directors are appointed to Hold Co and Prop Co to ensure the companies can remain quorate and able to trade. And RECOMMENDED TO COUNCIL approval of the following recommendations:- (4) That authority is delegated to the Director of Finance and Section 151 Officer in consultation with the Leader of the Council, upon agreement of the business justification case's for each of the proposed development sites, to:- (i) make changes to the budgetary framework as necessary (ii) To borrow as required for Ravelin Group development purposes, subject to a robust financial appraisal approved by the Director of Finance & S151 Officer that demonstrates the delivery of the best return to Portsmouth City Council and has proper regard to the following: · The relevant capital and revenue costs and income resulting from the investment over the whole life of the development. · The extent to which the investment is expected to deliver a secure ongoing income stream. · The level of expected return on the investment. · The payback period of the capital investment. · The tax status and transactional tax events associated with any land transfers or activity of the companies.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The decision to proceed with setting up the Ravelin Group of companies was taken by the Cabinet on the 9th June 2016, delegating responsibility to officers to carry out all necessary work to enable the companies to trade. This further Cabinet report ("the Report") builds on this previous decision and is focused on enabling Ravelin Group to commence trading.
1.2Ravelin Group Limited ("Hold Co") the Council's holding development company and subsidiary Ravelin Property Limited ("Prop Co") have been established to support the delivery of Portsmouth City Council's corporate priorities and to help secure development in the City.
1.3The Council's five corporate priorities have been set to be inclusive for all of the cities stakeholders. They seek to promote economic growth, inward investment and look to support the creation of balanced communities. These priorities are behind a raft of local plan policy documents and define the Councils vision for the future of Portsmouth. A golden strand that runs within all of these documents is the need for more affordable homes to meet the City's emerging housing need and supporting this will be one of Ravelin's priorities.
1.4This Report sets out the purpose and key objectives for Hold Co and any incorporated subsidiaries (collectively referred to as the "Ravelin Group" within this report) within the appended business case (appendix A). This business case sets out how the Council will benefit from using the Ravelin Group, to deliver the
1 www.portsmouth.gov.uk Council's own developments in line with the first five sites as agreed by Cabinet on 9th October 2018.
1.5The Report asks members to consider the appointment of new directors to ensure that both company boards remain quorate.
1.6The Report sets out how the Council as shareholder is able to exercise control over Hold Co who (via the business case) sets out how Hold Co's board will operate and manage Prop Co (and any future subsidiary companies).
Recommendations
That Cabinet approves the following recommendations:-
2.1That the business case and purpose for Hold Co is approved, including delegating authority to the Director Regeneration and City Solicitor in consultation with the s.151 officer to create a new subsidiary company to support the delivery of HRA projects with development management and project management services.
2.2To note that the need for the creation of a fit-for-purpose Board of Directors for each of the incorporated Ravelin companies based around an understanding of the skillsets required to support the company in both a commercial and local authority environment.
2.3That new directors are appointed to Hold Co and Prop Co to ensure the companies can remain quorate and able to trade.
That Council approves the following recommendations:-
2.4That authority is delegated to the Director of Finance and Section 151 Officer in consultation with the Leader of the Council, upon agreement of the business justification case's for each of the proposed development sites, to:-
2.4.1. make changes to the budgetary framework as necessary, and
2.4.2. To borrow as required for Ravelin Group development purposes, subject to a robust financial appraisal approved by the Director of Finance & S151 Officer that demonstrates the delivery of the best return to Portsmouth City Council and has proper regard to the following:
The relevant capital and revenue costs and income resulting from the investment over the whole life of the development.
The extent to which the investment is expected to deliver a secure ongoing income stream.
2 www.portsmouth.gov.uk The level of expected return on the investment.
The payback period of the capital investment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.