Noted the progress made on land assembly to support the development in paragraph 7 of this report and that land assembly continues as approved by Full Council on the 13 October 2021. 2. Noted work done by officers to support the wider City Centre's economic recovery through the multiple workstreams listed below and the role of the new City Centre North development in that programme of work. 3. Noted the progress of all work to complete the planning application and submit it in Spring 2022. 4. Delegated authority to the Director of Regeneration and the S151 officer to deliver meanwhile uses in all PCC owned assets where possible and viable to do so, to further support the economic recovery of the City Centre. 5. Delegated authority to the Director of Regeneration and S151 Officer on the advice of the City Solicitor in consultation with the Leader to investigate funding and delivery options including internal delivery and potential partnering options for the City Centre North Development. 6. Noted that the way retail operates has changed nationally and recognises that while Commercial Road is adapting to modern needs to deliver the stronger retail offer that residents want, it might be possible to help accelerate this. Therefore, to help this transition the Council will work with landlords and retailers to ensure that the city centre becomes the vibrant and engaging high street residents want and that the shopping offer is as strong as possible. 7. Agreed that the Culture & Leisure and Children, Families and Education directorates continue to work with colleagues within the Regeneration directorate to ensure the regeneration of the city centre is culturally led and meets the needs of young people.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report sets out the role the city centre plays, in accommodating the Cities growth needs.
1.2The development of the city centre, has for many years been a Council priority, defined in the current and emerging local plans as an area of housing and economic growth with the areas of City Centre North identified for regeneration and redevelopment.
1.3The report provides an update to the 13th October Council decision and asks members to note progress made on the new masterplan, and planning applications which are due to be submitted to the Local Planning Authority (LPA) in early Spring.
1.4The report seeks Cabinet approval of a series of recommendations to ensure progress from planning to the delivery stages of an extended City Centre Regeneration project also known as City Centre North.
Recommendations
The Cabinet is recommended:
2.1To note the progress made on land assembly to support the development in paragraph 7 of this report and that land assembly continues as approved by Full Council on the 13th October 2021.
2.2To note work done by officers to support the wider City Centre's economic recovery through the multiple workstreams listed below and the role of the new City Centre North development in that programme of work.
2.3To note the progress of all work to complete the planning application and submit it in Spring 2022. 1 www.portsmouth.gov.uk 2.4. To delegate authority to the Director of Regeneration and the S151 officer to deliver meanwhile uses in all PCC owned assets where possible and viable to do so, to further support the economic recovery of the City Centre.
2.5To delegate authority to the Director of Regeneration and S151 Officer on the advice of the City Solicitor in consultation with the Leader to investigate funding and delivery options including internal delivery and potential partnering options for the City Centre North Development.
Background
3.1The regeneration of the city centre has been a long-held ambition of the city council. Previous papers have detailed the development history of the area and approved the teams approach to site assembly with the ability to rely on a Compulsory Purchase Order for the area should it be required as a last resort.
3.2Since then, there have been significant progress, with the RIBA 1 designs approved by the portfolio holders in September 2021 enabling the team to progress with RIBA 2 and remain on track to submit an outline planning submission for the City Centre North project in early Spring 2022.
3.3The City Centre North programme of improvement and regeneration is complex with multiple workstreams, this paper looks to update Cabinet on how these are progressing in parallel, see the benefits map in Appendix A.
3.4This report will highlight the key workstreams involved in the City Centre and provide updates on those that are ongoing.
4. Local Plan
4.1The City Centre makes up a significant proportion of the land allocated to meet identified needs within the City. The Cross-Party Members working group is currently reviewing the emerging Plan looking for opportunities to increase the efficiency of land uses and has considered increasing scale and delivery within the City Centre as part of a sustainable spatial strategy.
4.2The emerging Plan also highlights sites where their current lack of green coverage and proposal for significant redevelopment presents an opportunity to deliver additional greening. The City Centre is one such site and an Urban Greening Factor tool has been developed to assist with achieving betterment in green infrastructure provision through on- site net gains.
4.3The development management team has determined several recent large scale applications supporting growth in the City Centre and is in discussion on a number of other key sites. This
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.