AI summaryPortsmouth Cabinet delegates authority to four named officers to sign a Development Management Services Agreement with Morgan Sindall LLP, delivered through Muse/ECF, for the City Centre North regeneration, with spending capped at £729,000.
Written from the decision and the officer reportPDF Pro
OutcomeNotedDelegated authority to enter agreement with Morgan Sindall LLP (Muse/ECF)
MoneyUp to £729,000
What happens nextReport back early 2027On DMSA outcome, final business case and draft Heads of Terms
Who it affectsCity Centre North siteThe Portsmouth regeneration area and neighbouring landowners
What was decided
Cabinet noted progress since the February 2026 report: a preferred procurement option chosen, the DMSA drafted with the preferred partner, and site surveys commissioned. Report 2.1, P3, 3.2
Cabinet delegated authority to the Assistant Director of Property and Investment, Assistant Director of Procurement, the Section 151 Officer and the City Solicitor to conclude and enter into the DMSA with Morgan Sindall LLP and to spend up to the estimated £729,000 from the February Cabinet Report. Report 2.2, P5, P6
The development management services will be procured by direct award through the Pagabo Framework, with delivery via Muse/ECF. Report 3.2, 4.1, 4.3
Why
A direct award under the Pagabo Framework offers a compliant, lawful and speedier route to appoint an industry-leading master developer, allowing the scheme to stay on programme. Report 4.3, 6.5
A master developer partnership gives the Council a market-facing business case, a coherent planning and infrastructure strategy, and a single, long-term view of phasing, placemaking and design. Report 4.2
The DMSA also gives the parties the chance to negotiate Heads of Terms for a future Development Agreement so the project can move into delivery without delay. Report 4.4
What happens next
The four delegated officers will finalise and sign the DMSA with Morgan Sindall LLP (Muse/ECF) and start spending the approved £729,000. Report 2.2, P5, P6
Muse/ECF will prepare a delivery business case covering infrastructure review, landowner engagement, community mapping, demand and market analysis, utility studies, phasing, funding strategy, viability and Heads of Terms for a future Development Agreement. Report 4.5, P19
A further report on the DMSA outcome, the final business case and draft Heads of Terms will come back to Cabinet in early 2027. Report 4.8
The money
£729,000 Estimated spend cap on DMSA activities, set in the February Cabinet Report Report P6
£250,000 Estimated external professional costs the Council is liable for under the DMSA; master developer does not charge for its services Report 4.7
£ 18.67 Total expenditure on the scheme to 31/05/26, met from the approved Council Capital Programme Report 7.1, P38
£ 4.08 Master planning (RIBA Stages 1 and 2) to inform the planning application Report P38
£ 11.01 Land acquisition including legal fees, covering Delancey assets and other property within the redline boundary Report P38
£ 2.46 Internal fees from council services since 2021 Report P38
£ 0.42 Local planning fees under the planning performance agreement with the LPA Report P38
£2.18m Remaining approved City Centre North Regeneration scheme funding within the capital programme, from which this DMSA can be funded Report 7.2
Options considered
Chosen: Direct award under the Pagabo Framework to Morgan Sindall LLP, delivered through Muse/ECF, as master developer. Expedient, compliant procurement route to an industry-leading master developer, allowing Heads of Terms for a future Development Agreement to be negotiated in parallel Report 3.2, 4.1, 4.3, 4.4, 6.5
Implications
Legal: The Council has power to enter the DMSA under section 1 of the Localism Act 2011 and section 111 of the Local Government Act 1972; the delegation does not extend to any future Development Agreement, which will need separate governance. Report 6.1, 6.3, 6.4
Risk: Procurement law risks include keeping the DMSA within the Pagabo Framework's services scope and ensuring any future Development Agreement also sits within the framework. Report 6.6, P32, 6.7
Financial: Director of Finance warns of likely significant residual funding gaps in early and longer-term delivery phases, with further capital likely needed; a capital bid is planned for the 2027/28 to 2029/30 process, and Homes England is the most likely external funder. Report 7.2, 7.5, 7.6, 7.7, 7.8
Staffing: Future Unitary Authority transition through Local Government Reorganisation is flagged as likely to make any further council funding more difficult to secure. Report 7.9
Risk: There is a risk of abortive cost if progress stalls and planning permission or surveys lapse, so the Council wants to keep moving. Report 7.10
Other: An integrated impact assessment is not required as the recommendations do not directly affect service or policy delivery. Report 5.1, P23
Who and where
Neighbouring landowners around the City Centre North site, who will be engaged under the DMSA Report 4.5, P19
The Portsmouth community, through community mapping, needs assessment and social impact work under the DMSA Report 4.5, P19
Homes England and other potential external funders, including the future Combined Authority Report 4.2, 7.7
The Assistant Director of Property and Investment, Assistant Director of Procurement, Section 151 Officer and City Solicitor, who receive delegated authority Report 2.2, P5
Timeline
05 October 2021: Previous Cabinet paper on the City Centre regeneration Report 3.1
08 March 2022: Previous Cabinet paper on the City Centre regeneration Report 3.1
10 February 2026: Previous Cabinet paper that approved the procurement strategy and £729,000 estimate, supported by the Mace report (confidential Appendix B) Report 3.1, 3.4, 7.5, P44
24th February 2026: Full Council approved the Capital Programme containing the City Centre North Regeneration scheme funding Report 7.2
31/05/26: Expenditure on the scheme to date totalled £ 18.67m Report 7.1, P38
2026-07-21: Cabinet decision to delegate authority to enter the DMSA and spend up to £729,000
early 2027: Further Cabinet report expected on the DMSA outcome, the final business case and draft Heads of Terms Report 4.8
2027/28 to 2029/30: Capital bids process period during which any further capital funding for the scheme is to be sought Report 7.2
Plain English for the jargon
DMSA: Development Management Services Agreement: a services agreement for development management and advisory support, not a commitment to any future development
CCN: City Centre North Regeneration, the Portsmouth scheme covered by this report
Pagabo Framework: A procurement framework used to make a direct award of the master developer contract
Master Developer: Lead development partner taking a long-term, holistic view of phasing, placemaking and design across the masterplan area
HoT: Heads of Terms: the outline terms for a future Development Agreement to be negotiated during the DMSA
RIBA Stages 1 and 2: Early Royal Institute of British Architects work stages covering preparation and concept design (masterplanning)
CPO: Compulsory Purchase Order, referenced as a form of support used to date
LPA: Local Planning Authority
PPA: Planning Performance Agreement with the Local Planning Authority
S151 Officer: The Council's chief finance officer, designated under section 151 of the Local Government Act 1972
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
Noted progress made since the last Cabinet Report of February 2026, to include the following: Successful determination of a preferred procurement option. Preparation of a DMSA, in conjunction with the preferred partner. Successful commissioning of various site surveys to feed into the DMSA. 2. Delegated authority to the Assistant Director of Property & Investment, Assistant Director of Procurement, Section 151 Officer and City Solicitor to: 2.1 Conclude and enter into the proposed DMSA with Morgan Sindall LLP. 2.2 Incur expenditure as required to progress working through the DMSA activities and other associated activities related to the scheme up to the estimated £729,000 identified in the February Cabinet Report.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To seek approval from Cabinet for the Council to enter into a Development Management Services Agreement (DMSA) with Morgan Sindall LLP (delivered through Muse/ECF) for the City Centre North Regeneration (CCN) project.
Recommendations
2.1Note progress made since the last Cabinet Report of February 2026, to include the following:
• Successful determination of a preferred procurement option. • Preparation of a DMSA, in conjunction with the preferred partner. • Successful commissioning of various site surveys to feed into the DMSA.
2.2To delegate authority to the Assistant Director of Property & Investment, Assistant Director of Procurement, Section 151 Officer and City Solicitor to:
2.2.1 Conclude and enter into the proposed DMSA with Morgan Sindall LLP.
2.2.2 Incur expenditure as required to progress working through the DMSA activities and other associated activities related to the scheme up to the estimated £729,000 identified in the February Cabinet Report.
1 www.portsmouth.gov.uk - Official -
Background
3.1The regeneration of the City Centre continues to be a key deliverable for the Council and is a long-held ambition. Previous Cabinet papers in 05 October 2021, 08 March 2022 and 10 February 2026 provide further details.
3.2Following Cabinet approval in February, further work has been undertaken to solidify the procurement strategy for the Master Developer alongside Mace, Montagu Evans and Vail Williams consultancy team. This has concluded in the recommendation to use the Pagabo Framework to direct award to Morgan Sindall, delivered through Muse/ECF (referred to as Muse/ECF in the rest of the report)
3.3A copy of the full Procurement Options Assessment report, which considered all the options open to the scheme, as well as further market evidence and wider procurement contract can be found at exempt Appendix A.
3.4The February Cabinet decision delegated authority to the Assistant Director of Property & Investment and the Assistant Director of Procurement, in consultation with the Leader to procure a Master Developer and prepare the DMSA.
3.5However, it also noted that authority to enter into the DMSA from Cabinet would be requested and this report seeks to do that.
Reasons for recommendations
4.1The activities outlined in 3.3 above have now been completed and this report seeks approval to enter into the DMSA with a Master Developer via a Direct Award using the Pagabo framework.
4.2In partnering with a Master Developer, the Council benefit from a robust, market facing business case. It will also provide a further link and early engagement with Homes England and other funding bodies. There will be a coherent strategy for planning and infrastructure delivery. Additionally, by working with one Master Developer there will be holistic, long-term view of phasing, placemaking and design across the masterplan area, informed by robust viability considerations.
4.3The benefit of using the Direct Award procedure allows for expediency of procurement and therefore delivery. It ensures a compliant and lawful approach to procuring an industry leading Master Developer, who brings a track record of delivering comparable multi-phase, placemaking projects. It allows for the appointment to be made on programme.
4.4The methodology gives the opportunity to negotiate the Heads of Terms (HoT's) for a future Development Agreement, so that the project can move seamlessly into delivery following successful completion of the work under the DMSA.
2 www.portsmouth.gov.uk - Official -
4.5The delivery business case that will be produced by Muse/ECF under the DMSA will consider (amongst others), the:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.