AI summaryPortsmouth Cabinet backs Master Developer route for City Centre North regeneration, with £2.63m spend authority delegated to officers and a further report due summer 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet delegated authority to appoint a partner
Money£2.63mSpending authority delegated for next phase
What happens nextSummer 2026Further Cabinet report on DMSA and business case
Who it affectsCity Centre NorthLong-term Portsmouth regeneration scheme
What was decided
Cabinet noted positive developer interest in Portsmouth and City Centre North after the Preliminary Market Engagement process concluded. Report 2.1
Cabinet agreed to move to the next phase, seeking a Master Developer to deliver the city centre vision, based on the consultant's recommendations. Report 2.2
Authority delegated to the Assistant Director of Property & Investment and Assistant Director of Procurement, in consultation with the Leader, to procure a Master Developer, prepare a Development Management Services Agreement, commission site surveys and spend up to £2.63m. Report 2.3, P5, P7
Why
The Master Developer approach allows delivery of the full masterplan as a strategic, multi-phase scheme with coherent infrastructure, transport and placemaking outcomes. Report 4.1
The procurement will lead into a Development Management Services Agreement and a developer-led business case, with approval milestones before any Development Agreement is signed. Report 4.2, P16, P17
Continuing progress protects existing planning consent and prior survey work from lapsing, and uses remaining headroom in the approved capital programme. Report 4.4, 7.10
What happens next
Officers will run a procurement to select a Master Developer partner and prepare a Development Management Services Agreement for Cabinet approval. Report 2.3, P5
A further Cabinet report seeking authority to enter the DMSA and prepare a detailed business case is expected in summer 2026. Report 2.4
The Strategic Outline Business Case for the City Centre Road project will be submitted to the Department for Transport via the Major Road Network Fund. Report 2.5
The money
£2.63m Spending authority delegated for next phase activities (in exempt Appendix C) Report P7
c.£2.3m Estimated expenditure Jan '26 to Mar '27 on procurement route, due diligence, internal and project costs Report 4.3
£20.85m Total approved City Centre North Regeneration scheme in the capital programme Report 4.4
£18.22m Expenditure incurred to 31/12/25 across all CCN workstreams Report 7.1, P34, P35
£2.24m Internal council service charges since 2021 Report P34
Options considered
Chosen: Appoint a Master Developer for holistic, multi-phase delivery of the city centre masterplan. Allows strategic multi-phase scheme with coherent infrastructure, transport and placemaking outcomes, per the Mace consultant report. Report 2.2, 4.1
Implications
Financial: Remaining £2.63m of approved capital funds the next phase; further capital bid planned for 2027/28 to 2029/30, and additional external funding is likely needed to close forecast funding gaps. Report 4.4, 7.2, 7.5, 7.7, 7.9
Legal: Legal Services and external counsel Beven Brittan will support procurement and DMSA negotiations; statutory powers rely on the Town and Country Planning Act 1990, Levelling-Up and Regeneration Act 2023, Local Government Act 1972 s.122 and the Localism Act 2011, with CPO risk under TCPA s.226. Report 6.1, 6.2, 6.3, P27, 6.4, 6.7
Risk: Risks include judicial review of planning decisions, CPO compensation claims, planning permission lapsing and surveys becoming time expired, and residual funding gaps requiring council funds in competition with other priorities. Report 6.6, 7.9, 7.10
Other: Integrated impact assessment not required at this stage as recommendations do not directly affect service or policy delivery; future changes will be assessed separately. Report 5.1, P22
Who and where
Portsmouth residents and city centre users Report 3.1, 4.5
Future occupants of the 900+ homes planned in the early phase of the masterplan Report 3.3
Developers and consultants engaged in the project, including Mace, Montague Evans, Vail Williams and Beven Brittan Report 3.2, 6.7
Council staff in Property & Investment, Procurement, Legal and Finance Report 2.3, 6.1, 7.1
Timeline
05 October 2021: Earlier Cabinet report on city centre regeneration Report 3.1
08 March 2022: Earlier Cabinet report on city centre regeneration Report 3.1
2023: Planning consent approved for the CCN masterplan (Application Reference 22/01243/CS3) Report 3.2
February 2025: Full Council approved capital programme including £2.63m remaining CCN funding Report 7.2
May 2025: Preliminary Market Engagement (PME) period began Report 3.2
September and October 2025: Market interviews and peer reviews during PME Report 3.2
31/12/25: Expenditure incurred to date totalled £18.22m Report 7.1, P34
Jan '26 to Mar '27: Indicative period for the c.£2.3m of next-phase spend, depending on chosen procurement route Report 4.3
Summer 2026: Further Cabinet report expected seeking authority to enter the DMSA and prepare a detailed business case Report 2.4
2027/28 to 2029/30: Window for the council's next capital bids process, where a further CCN capital bid is planned Report 4.4, 7.2
Plain English for the jargon
CCN: City Centre North, the long-running regeneration scheme in Portsmouth city centre
PME: Preliminary Market Engagement, the market sounding and peer review exercise that ran from May 2025
Master Developer: A single development partner appointed to deliver the holistic city centre masterplan across phases
DMSA: Development Management Services Agreement, the contract to be entered into with the Master Developer before a full Development Agreement
SOBC: Strategic Outline Business Case, in this case for the City Centre Road project submitted to the Department for Transport
CCR: City Centre Road, the transport infrastructure project linked to the wider regeneration programme
MRN Fund: Major Road Network Fund, the Department for Transport funding route for the SOBC
CPO: Compulsory Purchase Order, a council power to acquire land, here under Town and Country Planning Act 1990 section 226
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
Noted the positive interest from developers in both Portsmouth as a city and City Centre North (CCN) as a regeneration project, following the conclusion of the recent Preliminary Market Engagement (PME) process. 2. Noted the delivery options and commence the next phase of the project, as per the recommendations outlined in the attached Mace report (Executive Summary Appendix A, and Full report in the confidential exempt Appendix B). This is to seek an agreement with a Master Developer to deliver the vision for the City Centre. 3. Delegated authority to the Assistant Director of Property & Investment and Assistant Director of Procurement, in consultation with the Leader, to: 3.1 Following determination of the preferred option , procure a Master Developer partner. 3.2 Prepare a Development Management Services Agreement (DMSA) to be entered into with the Master Developer Partner. 3.3 Commission key site surveys to support the DMSA Business case. 3.4 Incur expenditure as required to progress these activities and other associated activities related to the scheme up to the estimated value of £2.63m (exempt Appendix C). 4. Noted that a further report seeking authority to enter into the DMSA with the Master Developer, enabling the preparation of a detailed business case will be brought to Cabinet in summer 2026. 5. Supported the submission of the Strategic Outline Business Case (SOBC) for the City Centre Road project to the Department of Transport via the Major Road Network Fund (noting this is currently under review by DfT).
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To update members on the City Centre North Regeneration scheme, including City Centre Roads and seek authority to progress all work packages required to select a suitable development partner.
Recommendations
2.1Note the positive interest from developers in both Portsmouth as a city and City Centre North (CCN) as a regeneration project, following the conclusion of the recent Preliminary Market Engagement (PME) process.
2.2Note the delivery options and commence the next phase of the project, as per the recommendations outlined in the attached Mace report (Executive Summary Appendix A, and Full report in the confidential exempt Appendix B). This is to seek an agreement with a Master Developer to deliver the vision for the City Centre.
2.3To delegate authority to the Assistant Director of Property & Investment and Assistant Director of Procurement, in consultation with the Leader, to:
2.3.1. Following determination of the preferred option, procure a Master Developer partner. 2.3.2. Prepare a Development Management Services Agreement (DMSA) to be entered into with the Master Developer Partner. 2.3.3. Commission key site surveys to support the DMSA Business case.
1 www.portsmouth.gov.uk - Official -
2.3.4. Incur expenditure as required to progress these activities and other associated activities related to the scheme up to the estimated value of £2.63m (exempt Appendix C).
2.4Note that a further report seeking authority to enter into the DMSA with the Master Developer, enabling the preparation of a detailed business case will be brought to Cabinet in summer 2026.
2.5Support the submission of the Strategic Outline Business Case (SOBC) for the City Centre Road project to the Department of Transport via the Major Road Network Fund (noting this is currently under review by DfT).
Background
3.1The regeneration of the city centre has been a long-held ambition of the city council, outlined by previous Cabinet reports of 05 October 2021 and 08 March 2022.
3.2Following the approval to grant planning consent for the CCN masterplan in 2023 (Application Reference 22/01243/CS3), the council has been developing options for delivery, culminating in a period of Preliminary Market Engagement (PME) running from May 2025. This PME included market interviews and peer reviews throughout September and October 2025. This activity has been led by a team of technical experts from Mace, Montague Evans and Vail Williams.
3.3The concluding report (exempt Appendix B) elaborates on the changing economic and regulatory climate and recommends a possible way forward for delivery of 900+ homes and green infrastructure as an early phase with later phases delivering the total ambition laid out in the Masterplan, which remains the Council's vision for the City Centre.
3.4Attached at Appendix A is the Executive Summary of our expert consultant's report, which outlines the next steps for the scheme. As per the recommendations at paragraph 2, this includes entering into a period of further consideration of procurement routes, to solidify a procurement strategy.
Reasons for recommendations
4.1The approach of appointing a Master Developer allows the opportunity to deliver the holistic masterplan. It would allow for a strategic, multi-phase scheme that enables short, medium and longer-term development. It would also provide a coherent approach to infrastructure and transport connectivity as well as facilitate the placemaking and regeneration ambitions of the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.