DECISIONS that: i) An experimental traffic regulation order (ETRO) is undertaken for a 22 hour (9am to 7am), two-car, taxi rank located at the southern end of the southbound bus lane on London Road, close to the junction with Laburnum Grove; ii) An information report be taken to Licensing Committee outlining the outcome of this decision; and iii) A report be brought back to the Cabinet Member of Traffic and Transportation with the results of the trial before the end of the ETRO period.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The purpose of this report is to seek approval for the trial of a 22-hour taxi rank in London Road, North End under an experimental traffic regulation order (ETRO) operating between 9am and 7am.
Recommendations
It is recommended that:
2.1An experimental traffic regulation order (ETRO) is undertaken for a 22 hour (9am to 7am), two-car, taxi rank located at the southern end of the southbound bus lane on London Road, close to the junction with Laburnum Grove.
2.2An information report be taken to Licensing Committee outlining the outcome of this decision.
2.3A report be brought back to the Cabinet Member of Traffic and Transportation with the results of the trial before the end of the ETRO period.
Background
3.1A review of Hackney Carriage stands was presented at the Licensing Committee on 25th September 2020 and included a proposal for a 24-hour taxi rank on London Road at the end of the bus lane on London Road close to the junction with Laburnum Grove
1 www.portsmouth.gov.uk 3.2 Following this proposal from the taxi trade, work has been underway to
examine the technical viability of a taxi rank in this location through: site observations technical designs safety reviews by transport officers and an independent Road Safety Audit engagement with bus operators, taxi trade representatives, and elected members.
3.3During engagement with bus operators, the importance of passing the junction with Derby Road before pulling out from the bus lane was highlighted, particularly during peak periods when traffic levels are higher including for this right-turn movement. Concerns were raised that if buses were required to join the carriageway before the junction with Derby Road this would lead to them joining queuing traffic and negatively impact bus reliability.
3.4Following engagement and site observations it was recommended that buses should maintain use of the existing bus lane in its entirety during the 7am to 9am period when demand and congestion is at its highest.
3.5To understand any potential conflict between different highway users, swept path analyses were undertaken whereby traffic movements are assessed and displayed. This also allowed understanding of the number of cars which could be accommodated safely in the proposed taxi rank to allow the buses to pass the Derby Road junction. The swept path analysis showed that the rank could only accommodate two cars, as presented at Licensing committee on 16th December 2021.
3.6Further safety considerations were raised regarding the proposal which are set out below.
3.7London Rd is the highest casualty route in Portsmouth and also the highest cyclist casualty route in the city. A cycle route and junction improvements were installed to address this and improve the safety of cyclists on this route.
There have been three personal injury collisions at this junction in the three year period 1 Feb 2018 to 31 Jan 2021; Car turning right from Laburnum Grove onto London Road collided with pedestrian crossing road Taxi turning left onto Laburnum Grove from London Road collided with a pedal cyclist travelling southbound on the nearside Car turning left into London Road from Derby Road collided with pedestrian crossing Derby Road
2 www.portsmouth.gov.uk 3.8 Buses exiting the bus lane past ranking vehicles would need wide turning movements and could cause northbound traffic to re-align their path, in turn risking safety of cycle lane users and also potentially pedestrians crossing Derby Road.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Tertiary Roads Inspection and RepairDecision The Cabinet Member: 1. Approved that the plans and timings of inspections of the tertiary road network are s...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.