RESOLVED that Full Council: i. NOTED the content of the report; ii. Considered and ENDORSED the revised principles advanced by the cross-party steering group set out in Appendix A as a strategic brief to bring forward a scheme for development on Tipner West and Horsea Island East; iii. NOTED the single overarching project objective in Appendix B that provides a high-level vision of what the Council is seeking to achieve; iv. NOTED the masterplan options sifting process and regulatory engagement that is underway to create a shortlist of viable development options; v. NOTED the thumbnail options in Appendix C, which are to be worked up and sifted leading to a preferred masterplan option for the area known as Tipner West and Horsea Island East to be subsequently developed; and vi. NOTED the proposed programme for progressing the project in Appendix D.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1The report seeks approval of a revised set of principles to use as a strategic brief to bring forward a scheme for development on Tipner West and Horsea Island East. It includes an overarching project objective which will be used as part of the planning consent process to set out what the council aims to achieve.
1.2The report provides members with information on the sifting process to shortlist future development options for Tipner West and Horsea Island East and summarises thumbnail options to be developed further.
Recommendations
2.1Cabinet recommends to Full Council:
a) To note the content of this report. b) Consider and endorse the revised principles advanced by the cross-party steering group set out in Appendix A as a strategic brief to bring forward a scheme for development on Tipner West and Horsea Island East. c) Note the single overarching project objective in Appendix B that provides a high- level vision of what the Council is seeking to achieve. d) Note the masterplan options sifting process and regulatory engagement that is underway to create a shortlist of viable development options. e) Note the thumbnail options in Appendix C, which are to be worked up and sifted leading to a preferred masterplan option for the area known as Tipner West and Horsea Island East to be subsequently developed. f) Notes the proposed programme for progressing the project in Appendix D
www.portsmouth.gov.uk 3. Reasons for Recommendations
3.1Members of all parties have agreed to work together to meet the commitments of the City Deal1, between government, local businesses and leaders from Southampton, Portsmouth and Hampshire councils and the Solent Local Enterprise Partnership, as signed on 12 November 2013.
3.2The programme plan is set out in Appendix D. The current programme plan suggests a Spring 2024 public consultation on a masterplan. Following this, a recommendation to approve the masterplan to form the basis of the planning and consent process, and the forthcoming submission of the Transport and Works Act Order (TWAO) will be put forward to Full Council in July 2024. The programme plan anticipates that we would make the planning application shortly after this full council decision.
3.3Members have previously agreed to mitigate the impact of further delays to determining a scheme to promote at Tipner West and Horsea Island East noting that delay results in additional and abortive costs to the Council due to an increase in external consultancy fees and expired site surveys needing to be re-done. It is anticipated that programme will incur a minimum of £158k in additional costs for every month that it's delayed.
3.4In line with previous advice to members, when the existing principles were adopted in October 2022, the report set out the significant implications for the Council's finances, if councillors are unable to agree the amended principles as proposed. Should this position arise and ultimately the project reach a point where it cannot progress then it is likely that the terms of the City Deal will not be met and the Council could face the significant financial burden of having to pay back the City Deal funds. This would be repayable in a single year (i.e. the point at which it becomes clear that a scheme that does not meet the terms and conditions of the agreement will not be met). Should this be the case the £23.5m of project expenditure to date would need to be funded from savings yet unidentified in the Council's budget which would have a significant impact on the future delivery of Council Services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.