Noted the work to date and the on-going work required by the project team to address the remaining key matters (set out in section 4.8) in order to complete the development of the Tipner West and Horsea Island Masterplan. 2. Requested the Chief Executive and the Director of Finance & Resources in consultation with the Leader, to engage with Central Government to discuss the City Deal outputs and the opportunities for further funding to close the viability gap(s) as detailed in section 4.10 of this report. 3. Delegated authority to the Assistant Director of Regeneration to progress with matters that are common to both land use options (Appendix A) in the development of the Tipner West and Horsea Island Masterplan using £7.7m funds previously approved by the City Council on 11 October 2022. This will include but is not limited to the following activities: on-going site-assembly; any necessary updating and commissioning of technical research including on-site, intrusive ground investigations and survey work; and progressing public engagement and consultation. 4. Noted the intention for the project team to present to a future meeting of the Cabinet for approval to develop a full masterplan for Tipner West and Horsea Island following the conclusion of 2.2 and 2.3 above. 5. Noted the revised project programme as detailed in Appendix C. 6. Referred the report to Full Council to note.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report builds on the information provided to members in the October report of the same name and seeks approval for the Tipner West development team to address the remaining key matters required to progress working up a Masterplan for submission to the City Council's Planning department as detailed in this report.
Recommendations
It is recommended that Cabinet;
2.1Note the work to date and the on-going work required by the project team to address the remaining key matters (set out in section 4.8) in order to complete the development of the Tipner West and Horsea Island Masterplan.
2.2Request the Chief Executive and the Director of Finance & Resources in consultation with the Leader, to engage with Central Government to discuss the City Deal outputs and the opportunities for further funding to close the viability gap(s) as detailed in section 4.10 of this report.
2.3Delegate authority to the Assistant Director of Regeneration to progress with matters that are common to both land use options (Appendix A) in the development of the Tipner West and Horsea Island Masterplan using £7.7m funds previously approved by the City Council on 11 October 2022. This will include but is not limited to the following activities: on-going site-assembly; any necessary updating and commissioning of technical research including on-site, intrusive ground investigations and survey work; and progressing public engagement and consultation.
2.4Note the intention for the project team to present to a future meeting of the Cabinet for approval to develop a full masterplan for Tipner West and Horsea Island following the conclusion of 2.2 and 2.3 above.
1 www.portsmouth.gov.uk - Official -
2.5Note the revised project programme as detailed in Appendix C.
2.6Refer the report to Full council to note.
Reasons for recommendations
3.1Members of all parties have agreed to work together to meet the commitments of the City Deal1, between government, local businesses and leaders from Southampton, Portsmouth and Hampshire councils and the Solent Local Enterprise Partnership, as signed on 12 November 2013.
3.2The 3 October 2023 Cabinet report set out a project programme to present a land use concept plan to Cabinet in November 2023, with the intention of commencing public engagement on a draft masterplan from Spring 2024. A recommendation to approve the masterplan to form the basis of the planning and consent process, and the forthcoming submission of the Transport and Works Act Order (TWAO) was to be put forward to the Cabinet and Full Council in July 2024.
3.3Following the last report to Cabinet and Full Council the project team have continued to explore land use options engagement with the Regulatory Panel and planning officers at the LPA.
3.4Officers presented to the Cross-Party Steering group on the Monday 13 November 2023. The presentation focused on the difference, benefits and disbenefits of the shortlisted two options, and suggested, that it would be possible for a decision on a preferred land use plan to be made at a December meeting of the Cabinet. However, the development team have reflected on the discussions at the meeting, and continued to explore issues raised, and this has crystalised a clear need to answer a number of major questions before a preferred option emerges out of the process.
3.5Given 3.4 above, the project plan has been revised and this is detailed in appendix C to this report.
3.6Members have previously agreed to mitigate the impact of further delays to determining a scheme to promote at Tipner West and Horsea Island East, noting that programme delays could result in additional and potential abortive costs to the Council due to an increase in external consultancy fees and the need to update expired site surveys works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.