Approved the revised Overarching Project Objective as set out in this report, appendix A. 2. Confirmed the 7 principles as set out in this report, appendix B. 3. Noted the update from the project team in relation to actions taken and planned. 4. Referred the report to Full Council to note.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1This report updates members on the progress with the regeneration plans for Tipner West and seeks specific approvals to enable the Tipner West development team to continue working up a masterplan for submission later this year.
Recommendations
It is recommended that the Cabinet;
2.1Approve the revised Overarching Project Objective as set out in this report, appendix A.
2.2Confirm the 7 principles as set out in this report, appendix B.
2.3Note the update from the project team in relation to actions taken and planned.
2.4Refer the report to Full Council to note.
Background
3.1The regeneration of Tipner West has been a longstanding ambition of the City Council to provide a flagship gateway and make most efficient use of brownfield land within the city’s tight administrative boundaries. The site has been recognised as a pivotal site to support the growth of the marine cluster within the Solent. This was recognised in the Southampton and Portsmouth City Deal signed in 2013.
1 www.portsmouth.gov.uk - Official -
3.2Development options for the site have indicated that there could be an adverse impact on internationally designated sites such as the Portsmouth Harbour SPA. In order to enable delivery of any plan or project that might have such an impact, the proposals must go through a rigorous process of ensuring that there are no alternative solutions to meet the objective that the project is aimed to achieve (known as the Overarching Objective), that the project needs to be undertaken for imperative reasons of overriding public interest and that any impact to the international site can be compensated for.
3.3In order to inform the final selection of a proposed scheme, the Tipner West development team are reviewing the manner in which the proposed allocation at Tipner could be delivered. This process will ensure that the regulatory requirements for a project that might have an impact on internationally designated sites have been fully interrogated to ensure that a robust application can be made for consenting a deliverable solution for Tipner West.
3.4Further to the update provided to Cabinet and Council in December 2023, the Tipner West development team have progressed the following work packages concurrent between the two previously identified land use options for delivering the proposed allocation for Tipner West;
Package Scope Update • Flood and coastal modelling methodologies issued to regulators (Environment Agency, Natural England, Marine Management Organisation and Coastal Ground Levels Partners) on 1 February. • Updating the flood and coastal models to complete baseline model • Remediation strategy technical note issued to internal Remediation team. Identifies further ground investigation works to Strategy be undertaken as part of next steps. SUDS and Foul • Technical note being prepared. drainage strategy 1 • Condition surveys for four listed structures on site completed and costed to bring structures back into a ‘good condition’. Note this is not a condition that enables them to be occupied for marine employment uses. • Outline design proposals for ‘shell and core fit-out’ Listed Building prepared for conversion of buildings into appropriate Scope of Works new uses within marine employment area. • Design for the levels and retaining walls around listed structures with regulator for agreement. • External discussions with heritage team to be progressed – Heritage Statement to be issued for further discussion.
2 www.portsmouth.gov.uk - Official -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.