CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Portsmouth City Council
Cabinet, Tuesday 10 February 2026 at 2.00pm

Spinnaker Tower - New Operator Procurement

Decided Executive 1 paper

AI summaryPortsmouth Cabinet approves procurement of a new Spinnaker Tower operator ahead of the current lease ending on 10 October 2026, with the current deal worth £154,000 a year to the council.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFinalise requirements, market and procure a new operator, sign contracts
Money£154,000 per year current lease incomeAt risk if no new operator secured
What happens nextPlanned Procurement Notice on 11 Feb 2026Formal tender starts 02 Mar 2026, award by 31 Jul 2026
Who it affectsSpinnaker Tower visitors and operator staffTower likely to close during refurbishment works

What was decided

Cabinet delegated authority to the Assistant Director of Property and Investment, the Assistant Director of Procurement and the City Solicitor, in consultation with the Leader, to finalise operator requirements, run the marketing and procurement exercise, and sign all required contract documents. Report 2.1, P4, P5, P6

Why

The current lease with Heritage Projects (Portsmouth) Limited, part of the Continuum Attractions group, expires on 10 October 2026, and the council wants a long-term partner to operate, invest in and enhance the attraction. Report 3.1, 1.2

Visitor numbers have been reduced since the Covid pandemic, and a new operator gives the chance to reset the operation, supported by a specialist leisure marketing agency and legal advice on Procurement Act 2023 compliance. Report 3.3, 3.4, 3.5, 4.4

Six suitably experienced operators took part in preliminary market engagement, with broad support for a partnership approach, longer term contracts and transfer of revenue and operating risk. Report 4.1, 4.2, 4.3

What happens next

Procurement will use a Competitive Flexible Procedure including dialogue, negotiation and staged bids, aiming for a concession contract and co-terminus occupational lease of 15 to 25 years. Report 4.4, 4.6, P22, 4.8

Draft programme: Planned Procurement Notice 11 Feb 2026, formal tender from 02 Mar 2026, Best and Final Offers by 19 Jun 2026, full approvals 13 Jul 2026, standstill to 31 Jul 2026, and service commencement on 11 Oct 2026. Report 4.9, P29

An Integrated Impact Assessment is not required at this stage but will be completed in later phases, and the council must also secure the best consideration reasonably obtainable under Section 123 of the Local Government Act 1972. Report 5.1, 4.5

The money

  • £154,000 per annum Current income to PCC from the existing Spinnaker Tower lease Report 7.1

Options considered

  • Chosen: Procure a new operator with a concession contract and co-terminus occupational lease of 15 to 25 years. Secures best value under PA23, transfers operating risk, leverages operator investment Report 4.4, 4.6, P22
  • Rejected: Continue with the existing operator arrangement. Lease ends 10 October 2026 and reset is needed after reduced post-Covid visitor numbers Report 3.1, 3.3

Implications

  • Financial: Loss of the £154,000 per year income stream if a new operator is not secured; a successful procurement would mitigate this risk. Report 7.1
  • Legal: Process must comply with the Procurement Act 2023 for a covered above-threshold concession and with Section 123 of the Local Government Act 1972 on best consideration. Report 4.4, 4.5, 6.1, P33, P34
  • Staffing: Tender evaluation will include staff retention, conditions and development, and the new operator is expected to retain existing staff. Report 4.7, P25, P22
  • Climate: Requirements include environmental considerations, carbon reduction and sustainability, and tender evaluation will cover environmental impact and sustainability. Report P22, P25
  • Risk: The tower will probably need to close to the public while dilapidations, refurbishment and maintenance works are carried out; exact closure timing is unknown. Report 3.6

Who and where

  • Visitors to the Spinnaker Tower and Portsmouth residents using local resident discount Report 3.2, P22
  • Current operator Heritage Projects (Portsmouth) Limited and its staff Report 3.1, P22
  • Prospective operators in the UK visitor attraction market Report 4.1, 4.2
  • Gunwharf Quays Limited (Interface Agreement counterparty) Report P22

Timeline

  • 13th November 2025: Preliminary Market Engagement Notice published on Find a Tender service Report 4.1
  • 11 February 2026: Issue Planned Procurement Notice following Cabinet approval Report P29, 4.9
  • 02 March 2026: Formal procurement starts with Tender Notice and first stage documentation Report P29, 4.9
  • 24 April 2026: First stage tender submissions due Report P29, 4.9
  • 19 June 2026: Best and Final Offers submitted Report P29, 4.9
  • 13 July 2026: Full approvals Report P29, 4.9
  • 14 July 2026 to 31 July 2026: Standstill period, award notice and conclusion of award Report P29, 4.9
  • 03 August 2026 to 10 October 2026: Mobilisation and lead-in period Report P29, 4.9
  • 10 October 2026: Current lease with Heritage Projects (Portsmouth) Limited expires Report 3.1
  • 11 October 2026: New operator service commencement Report P29, 4.9

Plain English for the jargon

  • PA23: Procurement Act 2023, the UK procurement law that applies to this letting
  • Concession contract: A contract where the operator takes revenue and operating risk in return for running the service
  • Competitive Flexible Procedure: A procurement process under PA23 allowing dialogue, negotiation and staged bidding
  • Preliminary Market Engagement (PME): Early sounding of the market before a formal tender, used here via a PME Notice on Find a Tender
  • Section 123 LGA 1972: Local Government Act requirement to secure the best consideration reasonably obtainable for a council disposal
  • BAFO: Best and Final Offer, the final stage of negotiated tendering
  • Dilapidations: Repairs and reinstatement works required from an outgoing tenant at lease end
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Delegated authority to the Assistant Director of Property & Investment, the Assistant Director of Procurement and the City Solicitor in consultation with the Leader to: 1.1 Finalise the future operator requirements (section 4.6), 1.2 Undertake marketing and procurement of a new Tower operator, 1.3 Complete and execute all required contract documentation to enable 1.1 and 1.2 above.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1To provide information and to seek authority to commence the procurement process for securing an operator for the Spinnaker Tower post the current lease expiry in October 2026.

1.2The Council will be seeking a long-term partner to operate, invest and enhance the attraction that is the Spinnaker Tower to support the Council's ambitions.

Recommendations

2.1Delegated authority to the Assistant Director of Property & Investment, the Assistant Director of Procurement, and the City Solicitor in consultation with the Leader to:

2.1.1. Finalise the future operator requirements (section 4.4 below),

2.1.2. Undertake marketing and procurement of a new Tower operator,

2.1.3. Complete and execute all required contract documentation to enable 2.1.1. and 2.1.2. above.

Background

3.1The Spinnaker Tower has been leased to Heritage Projects (Portsmouth) Limited (part of the Continuum Attractions group) since opening in 2005 and the current lease expires on 10 October 2026. 1 www.portsmouth.gov.uk - Official -

3.2The Spinnaker Tower continues to be an important visitor attraction and landmark on the Portsmouth skyline, it continues to be the Councils ambition to ensure that the Tower continues as a key visitor destination helping raise the profile of the City, delivering growth and supporting the City Vision 2040.

3.3Since opening in 2005 the Tower has seen visitor numbers of many hundreds of thousands per year, in recent years, and specifically since the Covid pandemic visitor numbers have continued at reduced levels. The end of lease in October 2026 allows the Council the opportunity to identify a new operator and reset and refresh the Tower operation.

3.4To support this activity, the Council has appointed a specialist leisure marketing agency, Colliers, to input into the strategic design and options for the project’s next steps.

3.5The Council has also appointed a specialist law firm, Clyde & Co., to provide property and procurement law advice to assess the potential routes to market under the Procurement Act 2023 (PA23) which applies to the Council as a Contracting Authority.

3.6Given the age, condition, unique nature of the tower, and normal practice at a lease end, it is highly likely that physical works, related to current tenant lease obligations (known as dilapidations), leasing refurbishment requirements, and general maintenance (current landlord obligations) will need to be undertaken. These works will include but will not be limited to significant investment / refurbishment of the internal lift and other items that directly impact on operation. It is anticipated that the tower will need to be closed to the public while these works are completed. The exact timing of any closure is currently unknown and subject to discussions as part of the operator procurement process.

Reasons for recommendations

4.1A PA23 compliant formal Preliminary Market Engagement exercise has been undertaken via the issue of a PME Notice (2025/S 000-073620) to the governments Find a Tender service platform on 13th November 2025. This process was supported by the marketing agents Colliers. Interested operators were invited to participate in 1-1 discussions to provide insight on:

• Market experience, capacity & interest • Options for development of the visitor offer, site uses & continuing position as a key landmark of the wider Solent region • Options for operating models, roles & responsibilities, legal structures & partnership working • Commercial options, investment, funding, return & risk

2 www.portsmouth.gov.uk - Official -

• Competitive bidding options, process & programme

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Spinnaker Tower: New Operator ProcurementReport 202 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SP
Councillor Steve PittChair, present
DS
Councillor Darren SandersVice-Chair, present
DA
Councillor Dave AshmoreCabinet Member, present
CA
Councillor Chris AttwellCabinet Member, present
KB
Councillor Kimberly BarrettCabinet Member, present
PC
Councillor Peter CandlishCabinet Member, present
ND
Councillor Nicholas DorringtonCabinet Member, present
LH
Councillor Lee HuntCabinet Member, apologies
HM
Councillor Hugh MasonCabinet Member, present
MW
Councillor Matthew WinningtonCabinet Member, present

On this subject at Portsmouth

Search all
  1. Spinnaker Tower - New Operator ProcurementThis decision
  2. Spinnaker Tower partnership agreementNoted
  3. Naming Rights proposals for the Spinnaker TowerApproved

More from Portsmouth Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... Noted Open
22 Sep 2026 Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... Approved Open
21 Jul 2026 Carbon Action PlansNoted the report which is for information and is not subject to call-in. Noted Open
21 Jul 2026 Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... Noted Open
21 Jul 2026 Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies