CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Redbridge
Cabinet, Monday 15 January 2007

Procurement of Service Contracts for building plant and equipment.Collaborative Project with London Borough of Waltham Forest (CAB/21/150107)

Approved Executive 1 paper

Cabinet approved this item on Monday 15 January 2007. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

That we approve the collaborative approach with London Borough of Waltham Forest for the procurement of the servicing and maintenance of building plant and equipment. Actions: Roger Smith Ext. 83503
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The contracts for the servicing and maintenance of building plant and equipment are due for retendering with the contracts being in place by April 2008. As part of the research into achieving effective and efficient tenders, discussions have been taking place with Officers from the London Borough of Waltham Forest.

1.2A business case has been prepared to consider the potential advantages of an amalgamation of the tendering process and the use of the same contractors to deliver the service.

1.3Officers within the London Borough of Waltham Forest have the delegated authority to negotiate and agree a decision on this collaborative framework.

1.4The officer report is attached as Appendix A to this report.

Reasons for the recommendations

2.1It is necessary to gain approval to work in collaboration with the London Borough of Waltham Forest to procure the contracts for servicing and maintenance of building plant and equipment

Recommendations

The Cabinet is recommended to:

3.1Approve the collaborative approach with London Borough of Waltham Forest for the procurement of the servicing and maintenance of building plant and equipment.

THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE REQUISITIONED

Contact Point Name: Cllr Mrs Huggett Position: Cabinet Member for Resources and Communication Telephone: 020 8708 9678 E. Mail: Cllr [email protected] APPENDIX A

Officer report To: Cabinet Member for Resources and Communication

From: Chief Engineering and Building Services Officer Date: 15th January 2007

Background

1.1The contracts for servicing and maintenance of building plant and equipment are currently let on five-year contracts that expire in March 2008. There is an option to extend the contracts for a further three years by agreement of both parties. As part of the review undertaken within Engineering & Building Services (E & BS), it was considered the number of individual contracts could be reduced to achieve benefits on both quality of the service and cost effectiveness.

1.2Servicing and maintenance of plant and equipment is an essential element of maintaining the corporate property portfolio in a safe and reliable condition. The contracts are also offered to Redbridge schools within the School Maintenance and Development Service. Currently approximately 95% of schools buy into the service from their delegated budgets.

1.3Approaches were made to a number of other London Boroughs to determine the methods used to manage these contracts and the responses received indicated similar contracts were in place.

1.4The London Borough of Waltham Forest indicated they had similar contracts that expired by March 2008. Officers therefore had discussions to consider a joint procurement exercise.

1.5The total cost of Service Contracts to the Council is in the region of £1.200.000 per annum. Currently this value is spread across 21 separate contracts utilising 16 separate contractors. The values of individual contracts ranges from less than £10,000 to in excess of £200,000 per annum. Officers within Waltham Forest Council have indicated the total value of work within their property portfolio was in the region of £1,022,000 in 2005/06.

1.6With the proposal to reduce the number of individual contracts to 7, the combined spread of values are anticipated to be between £120,000 and £700,000 per annum. With these contract values, the contractors will have a greater ability to coordinate work to achieve a balance for their staff. This will lead to more efficient working practices and can be reflected in more competitive tender levels.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Service Contracts for building plant and equipment.Collaborative Project with London Borough of Waltham Forest (CAB/21/150107)Report 36 KB DownloadRead as text

At this meeting

Whole meeting
5Forward Plan and Work Programme (CAB/05/150107)Agreed 6Introduction of Identity Cards (CAB/06/150107)Agreed 7Budget Strategy - Revenue 2007/08 - 2009/10 (CAB/07/150107)Agreed 8Budget Strategy - Capital 2007/8 -2009/10 (CAB/08/150107)Noted 9Initial Budget Proposals 2007/08 - 2009/10 (CAB/09/150107)Agreed 10Asset Management Plan and Capital Strategy 2006/07 - 2008/09 (CAB/10/150107)Approved 11Building Schools for the Future - One School Pathfinder (CAB/11/150107)Agreed 12Transfer of Land adjacent to Oaks Park School, Perrymans Farm Road, Barkingside (CAB/12/150107)Agreed 13References to Cabinet: Levett Gardens (CAB/13/150107)Deferred 14Draft Olympic Transport Plan - Consultation (CAB/14/150107)Decided 152006/2007 Highways Capital Funding Arrangements (CAB/15/150107)Approved 16Aldborough Road South/Meads Lane Junction (CAB/18/150107)Noted 17Review of Housing Revenue Account Finances and Charges (CAB/17/150107)Noted 18Settled Homes Initiative Pilot (CAB/18/150107)Agreed 19Petition about Small Independent Shops on Wanstead High Street (CAB/19/150107)Decided 20Age Discrimination - Implications for the Council as an employer (CAB/20/150107)Agreed
21Procurement of Service Contracts for building plant and equipment.Collaborative Project with London Borough of Waltham Forest (CAB/21/150107)This decision
22Establishing a New Data Centre (CAB/22/150107)Noted 23Consultation on Social Care Eligibility (CAB/23/150107)Agreed 24Any other items which the Chairman decides for the reasons stated are urgent (CAB/24/150107)Noted 25Motion to exclude the public (CAB/25/150107)Agreed 26Report on the Negotiated Tender for the Construction of Phase 2 of an Administration and Teaching Extension at Cleveland Junior and Infants School (CAB/26/150107)Noted 27Single Status Review (CAB/27/150107)Agreed 28Report of Land Sales Advisory Panel and Matters Arising for Cabinet Consideration (CAB/28/150107)Agreed 29Affordable Housing Capital Programme (CAB/29/150107)Agreed 30Establishment of a local Non-Profit Distributing Organisation (CAB/30/150107)Agreed

Who was there

9 of 10 attended
AE
Councillor Alan Edward Weinberg MBEMember, present
LA
Councillor Linda A. HuggettMember, present
MA
Councillor Mark AaronMember, present
RI
Councillor Ronald I. BardenMember, present
VC
Councillor Vanessa ColeMember, present
PR
Councillor Peter R. GoodyMember, apologies
SM
Councillor Suzanne M. NolanMember, present
JP
Councillor James P. O'SheaMember, present
KP
Councillor Keith PrinceMember, present
CM
Councillorr Michael StarkMember, present

On this subject at Redbridge

Search all
  1. Procurement of Service Contracts for building plant and equipment.Collaborative Project with London Borough of Waltham Forest (CAB/21/150107)This decision
  2. Exempt: Procurement Design and Build Contractors HRA Phase 2 Services and WorksAgreed
  3. Procurement of an Integrated Community Equipment Service Framework (CAB/07/110619)Agreed
  4. Procurement of Development Management Services on behalf of the Council's Development Company (CAB/25/060318)Noted
  5. Procurement of an Integrated HIV Prevention and Support Service (CAB/11/060218)Approved
  6. The Design and Procurement of Domicilliary Home Care Provision for Children and Adults Services (CAB/12/060218)Agreed

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies