Establishing a New Data Centre (CAB/22/150107)

Noted Executive 1 paper

Cabinet noted this item on Monday 15 January 2007. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

That we:- (i) note the operational limitations of the Council’s existing data centres; (ii) note the analysis of options and agree the recommendation to establish a new data centre supporting the concept of a joint venture initiative, with a committed public sector partner; and (iii) approve the £210,000 capital expenditure from the ICT Strategy, earmarked for the provision of a data centre. Actions: Lee Edwards Ext. 84100
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1Members approved the current Information and Communications Technology (ICT) Strategy in July 2006, recognising the strategic importance of technology in contributing to the values of the Council. An area of immediate action recommended in the Strategy was the establishment of a new data centre to replace ageing facilities.

1.2In line with the Strategy, a considerable amount of resources have been applied to improve the technical infrastructure and service resilience of Council systems. These systems are housed in data centre environments, which are now approximately 20 years old and no longer fit for purpose.

1.3As technology advances the demand on the Council’s data centre environments continually increases. The current generation of computer equipment, although considerably more compact than its predecessors, is significantly heavier, produces more heat and needs more power to operate. Therefore any environment in which it is situated needs to have significant weight distribution, cooling and power supply capabilities.

1.4In consideration of these factors, specialists in the field of data centre environments were engaged to support the work being undertaken by Officers. The outcome of this review signalled the need to move away from the existing data centres to establish a new purpose built environment.

1.5In light of the inadequacies of the Council’s existing data centres, Officers undertook a comprehensive evaluation of all possible options open to the Council.

1.6The conclusion of the options analysis was to recommend the establishment of a data centre with one or more public sector partners. This shared services approach will provide an opportunity to establish these facilities at a reduced cost and meet the Government’s national agenda for the development of shared services.

1.7The officer report is attached as Appendix A to this report. 2. Reasons for the Recommendations

2.1It is necessary to continue to invest in technology in order to support the Council’s front line services and meet the challenges of improving efficiency. A new data centre environment is critical to the stability and resilience of Council systems and associated services. Improvements in the Council’s technology infrastructure offer the opportunity for enhanced levels of customer service and hence potential for increased customer satisfaction.

2.2The Government has recently signalled a strong focus on developing technology as a driver for business change and service modernisation for the delivery of better front line public services, with particular emphasis on shared services.

Recommendations

3.1The Cabinet is recommended to:

3.1.1 Note the operational limitations of the Council’s existing data centres.

3.1.2 Note the analysis of options and agree the recommendation to establish a new data centre supporting the concept of a joint venture initiative, with a committed public sector partner.

3.1.3 Approve the £210,000 capital expenditure from the ICT Strategy, earmarked for the provision of a data centre.

THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE REQUISITIONED

Contact Point: Name: Councillor Mrs Huggett Position: Cabinet Member for Resources and Communication Telephone: 020 8708 9638 Email: Cllr [email protected] APPENDIX A

Officer report To: Cabinet Member for Resources and Communication From: Chief Information & Business Systems Officer Date: 15th January 2007

Background

1.1Members approved the current Information and Communications Technology (ICT) Strategy in July 2006, recognising the strategic importance of technology in contributing to the values of the Council. An area of immediate action recommended in the Strategy was the establishment of a new data centre to replace ageing facilities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Establishing a New Data Centre (CAB/22/150107)Report 53 KB DownloadRead as text

At this meeting

Whole meeting
5Forward Plan and Work Programme (CAB/05/150107)Agreed 6Introduction of Identity Cards (CAB/06/150107)Agreed 7Budget Strategy - Revenue 2007/08 - 2009/10 (CAB/07/150107)Agreed 8Budget Strategy - Capital 2007/8 -2009/10 (CAB/08/150107)Noted 9Initial Budget Proposals 2007/08 - 2009/10 (CAB/09/150107)Agreed 10Asset Management Plan and Capital Strategy 2006/07 - 2008/09 (CAB/10/150107)Approved 11Building Schools for the Future - One School Pathfinder (CAB/11/150107)Agreed 12Transfer of Land adjacent to Oaks Park School, Perrymans Farm Road, Barkingside (CAB/12/150107)Agreed 13References to Cabinet: Levett Gardens (CAB/13/150107)Deferred 14Draft Olympic Transport Plan - Consultation (CAB/14/150107)Decided 152006/2007 Highways Capital Funding Arrangements (CAB/15/150107)Approved 16Aldborough Road South/Meads Lane Junction (CAB/18/150107)Noted 17Review of Housing Revenue Account Finances and Charges (CAB/17/150107)Noted 18Settled Homes Initiative Pilot (CAB/18/150107)Agreed 19Petition about Small Independent Shops on Wanstead High Street (CAB/19/150107)Decided 20Age Discrimination - Implications for the Council as an employer (CAB/20/150107)Agreed 21Procurement of Service Contracts for building plant and equipment.Collaborative Project with London Borough of Waltham Forest (CAB/21/150107)Approved
22Establishing a New Data Centre (CAB/22/150107)This decision
23Consultation on Social Care Eligibility (CAB/23/150107)Agreed 24Any other items which the Chairman decides for the reasons stated are urgent (CAB/24/150107)Noted 25Motion to exclude the public (CAB/25/150107)Agreed 26Report on the Negotiated Tender for the Construction of Phase 2 of an Administration and Teaching Extension at Cleveland Junior and Infants School (CAB/26/150107)Noted 27Single Status Review (CAB/27/150107)Agreed 28Report of Land Sales Advisory Panel and Matters Arising for Cabinet Consideration (CAB/28/150107)Agreed 29Affordable Housing Capital Programme (CAB/29/150107)Agreed 30Establishment of a local Non-Profit Distributing Organisation (CAB/30/150107)Agreed

Who was there

9 of 10 attended
AE
Councillor Alan Edward Weinberg MBEMember, present
LA
Councillor Linda A. HuggettMember, present
MA
Councillor Mark AaronMember, present
RI
Councillor Ronald I. BardenMember, present
VC
Councillor Vanessa ColeMember, present
PR
Councillor Peter R. GoodyMember, apologies
SM
Councillor Suzanne M. NolanMember, present
JP
Councillor James P. O'SheaMember, present
KP
Councillor Keith PrinceMember, present
CM
Councillorr Michael StarkMember, present

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies