Resolved
That we (i) approve expenditure from the DfES grant funding for this project to cover the professional fee element of the project, the current provision for which is £3,669,065; (ii) delegate authority to the Director of Children’s Services, in consultation with the Director of Environment and Regeneration and the Cabinet Member for Children’s Services to agree to the final amount to be spent on fees which will need to be contained within the overall grant funding of £38.6 million; and (iii) note the measures in place to ensure financial control of the project. Actions: Frank O'Neill Ext. 83117 Phil Nunn Ext. 83620
Word for word from the decision Redbridge published for this meeting.