Budgetary Control Report for Quarter One 2018/19 (CAB/07/040918)

Noted Executive 6 papers

Cabinet noted this item on Tuesday 4 September 2018. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That the £0.283m forecast overspend position after recommended virements in relation to the 2018/19 General Fund revenue budget and impact of Mitigation Plans set out by People and Place directorates in Appendix B ( i ) and (ii) be noted; (ii) the balanced forecast position in relation to the 2018/19 DSG be noted; (iii) the Housing Revenue Account is forecasting an underspend of £1.042m at year end, this is due to lower interest costs relating to a lower borrowing requirement be noted; (iv) the inter-Directorate virements as set out in table 3 in paragraph 11.1 be noted; (v) the forecast outturn position reported on the capital programme in section 16 of the report be noted; and (vi) the progress and delivery of the approved savings programme (RAG - Red £8.116m, Amber £11.389m and Green £15.470) with substitution of unachievable savings and mitigation plans produced by Cabinet Members and Corporate Directors and presented at this Cabinet meeting. To ensure savings delivery for all red saving items, substitutions are expected to be identified be noted.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report sets out the Authority’s financial performance to 30 June 2018 and the forecast outturn for 2018/19.

Recommendations

The Cabinet is recommended to:

2.1Note the £0.283m forecast overspend position after recommended virements in relation to the 2018/19 General Fund revenue budget and impact of Mitigation Plans set out by People and Place directorates in Appendix B (i) and (ii).

2.2Note the balanced forecast position in relation to the 2018/19 DSG.

2.3Note the Housing Revenue Account is forecasting an underspend of £1.042m at year end, this is due to lower interest costs relating to a lower borrowing requirement.

2.4Note the inter-Directorate virements as set out in table 3 in paragraph 11.1.

2.5Note the forecast outturn position reported on the capital programme in section 16 of the report.

2.6Note the progress and delivery of the approved savings programme (RAG - Red £8.116m, Amber £11.389m and Green £15.470) with substitution of unachievable savings and mitigation plans produced by Cabinet Members and Corporate Directors and presented at this Cabinet meeting. To ensure savings delivery for all red saving items, substitutions are expected to be identified. THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT

MAY BE CALLED IN

Cabinet Member Contact Point Name: Cllr Kam Rai Position: Deputy Leader/Cabinet Member for Finance and Resources Telephone: 020 8708 2020 Email: [email protected]

Contact Point Report Author: Becky Hellard Position: Assistant Director Finance, Business Support and Enablement Telephone: 0208 708 3013 Email: [email protected] 3. Background and Proposals

3.1Budgetary control reports are presented to Cabinet so that the Council’s revenue and capital programme can be monitored. It is essential that frequent monitoring takes place in order to ensure that the Council’s financial resources are properly controlled.

3.2In accordance with Financial Regulation 12.7, an Action Plan will be presented to Cabinet where the lower of an overspend of £0.200m or 5% of budget cannot be prevented from occurring through normal management action.

3.3This report highlights the main risks and issues that are being addressed by Corporate Directors to maintain expenditure within the approved revenue budget and capital programme. It also provides a summary of progress in delivering savings brought forward from 2017/18 and those due to be delivered in 2018/19. Where these actions require the virement of budgets, they are reported for noting in accordance with financial regulations.

4. Summary Position

4.1The table below shows the forecast budget variations as at 30 June 2018.

Table 1: Summary

Month 3 Forecast RAG Movement in Budget Spend status variation Variation from prior Over / (Under) month (M2) £m £m General Fund Revenue 0.283 Red (9.977) Housing Revenue Account (1.042) Green (1.042) Dedicated Schools Grant - Green - Capital Programme - Green -

4.2Section 5 sets out the summary position for revenue budgets within the General Fund and in Section 16 for the Capital Programme. The overall position for the General Fund is a forecast overspend of £0.283m. This is a significant reduction from the month 2 position and assumes full delivery of significant mitigation actions proposed by both People and Place directorates are delivered in full by the end of the financial year.

4.3The Housing Revenue Account is forecasting an underspend of £1.042m for the year.

4.4The Dedicated Schools Grant is fully committed and projecting a balanced position.

5. Revenue

5.1A review of the 2018/19 budget has been undertaken to re-prioritise resources into key areas having consideration to projected demand, risks and pressures. This has resulted in the requirement to transfer resources between Directorates within the overall budget approved by Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
00: Appendix A Savings Tracker for BCR 3Appendix 126 KB Download
PDF
(i): People mitigation planAppendix B 173 KB Download
PDF
(ii): Place mitigation planAppendix B 113 KB Download
PDF
Capital for BCR 3Appendix C 122 KB Download
PDF
00: Directorate Revenue forecastsAppendix D 115 KB Download
PDF
Budgetary Control Report for Quarter One 2018/19 (CAB/07/040918)Report 331 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
JA
Councillor Jas AthwalChair, present
KR
Councillor Kam RaiVice-Chair, present
EN
Councillor Elaine NormanMember, present
MA
Councillor Mark A. SantosMember, present
SA
Councillor Sheila A. BainMember, present
JP
Councillor John Peter HowardMember, apologies
HM
Councillor Helen Mary CoombMember, apologies
FK
Councillor Farah Khanum HussainMember, present
RC
Councillor Robert C. LittlewoodMember, present

On this subject at Redbridge

Search all
  1. Budgetary Control Report for Quarter One 2018/19 (CAB/07/040918)This decision
  2. Budgetary Control ReportNoted
  3. Budgetary Control Report Outturn for 2025/26Noted
  4. Budgetary Control Outturn 2025/26Noted
  5. Budgetary Control Report for Quarter 3 2025-26Noted
  6. Budgetary Control report for 2024/25Noted

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies