That (i) the £6.358m forecast overspend position to the 2018/19 General Fund revenue budget and impact of Mitigation Plans set out by People and Place Directorates in Appendix B (i) and (ii) be noted; (ii) the balanced forecast position of £234.639m in relation to the 2018/19 DSG be noted; (iii) the Housing Revenue Account forecast an underspend of £1.720m at year end be noted; (iv) the virements as set out in table 3 in paragraph 11.1, 11.2 and 11.3 be noted; (v) the forecast outturn position reported on the capital programme in section 17 of the report be noted; (vi) it be noted that there is additional capital grant funding of £0.241m in respect of Disabled Facilities Grants for 2018/19 as set out in paragraph 17.2; (vii) approval be given to the following slippage £34.907m of the capital programme (£26.638m for General Fund and £8.269 for Housing General Fund) as set out in table 5 and paragraph 17 and £0.009 net Additional Funding; (viii) the progress and delivery of the approved savings programme (RAG - Red £9.846m, Amber £5.951m and Green £19.179m with substitution of unachievable savings and/or mitigation plans produced by Cabinet Members and Corporate Directors and presented at this Cabinet meeting be noted (to ensure savings delivery for all red saving items, substitutions are expected to be identified); (ix) it be noted that management continues to implement selective moratorium on spend, restricting non-essential spend for the remainder of the 2018/19 financial year as outlined in paragraph 19.3.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1This report sets out the Authority’s financial performance to 31 December and the forecast outturn for 2018/19
Recommendations
The Cabinet is recommended to:
2.1Note the £6.358m forecast overspend position to the 2018/19 General Fund revenue budget and impact of Mitigation Plans set out by People and Place Directorates in Appendix B (i) and (ii).
2.2Note the balanced forecast position of £234.639m in relation to the 2018/19 DSG.
2.3Note the Housing Revenue Account forecast an underspend of £1.720m at year end.
2.4Note the virements as set out in table 3 in paragraph 11.1, 11.2 and 11.3.
2.5Note the forecast outturn position reported on the capital programme in section 17 of the report.
2.6Note there is additional capital grant funding of £0.241m in respect of Disabled Facilities Grants for 2018/19 as set out in paragraph 17.2.
2.7Approve the following slippage £34.907m of the capital programme (£26.638m for General Fund and £8.269 for Housing General Fund) as set out in table 5 and paragraph 17 and £0.009 net Additional Funding.
2.8Note the progress and delivery of the approved savings programme (RAG - Red £9.846m, Amber £5.951m and Green £19.179m with substitution of unachievable savings and/or mitigation plans produced by Cabinet Members and Corporate Directors and presented at this Cabinet meeting. To ensure savings delivery for all red saving items, substitutions are expected to be identified.
2.9Note that management continues to implement selective moratorium on spend, restricting non-essential spend for the remainder of the 2018/19 financial year as outlined in paragraph 19.3 THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT
MAY BE CALLED IN
Cabinet Member Contact Point Name: Cllr Kam Rai Position: Deputy Leader/Cabinet Member for Finance and Resources Telephone: 020 8708 2020 Email: [email protected]
Contact Point Report Author: Deborah Hindson Position: Operational Director Finance (Deputy s151 Officer) Telephone: 0208 708 3013 Email: [email protected] 3. Background and Proposals
3.1Budgetary control reports are presented to Cabinet so that the Council’s revenue and capital programme can be monitored. It is essential that frequent monitoring takes place in order to ensure that the Council’s financial resources are properly controlled.
3.2In accordance with Financial Regulation 12.7, an Action Plan will be presented to Cabinet where the lower of an overspend of £0.200m or 5% of budget cannot be prevented from occurring through normal management action.
3.3This report highlights the main risks and issues that are being addressed by Corporate Directors to maintain expenditure within the approved revenue budget and capital programme. It also provides a summary of progress in delivering savings brought forward from 2017/18 and those due to be delivered in 2018/19. Where these actions require the virement of budgets, they are reported for noting in accordance with financial regulations.
4. Summary Position
4.1The table below shows the forecast budget variations as at 31 December 2018.
Table 1: Summary
Quarter 2 Forecast RAG Movement in Budget Spend status variation Variation from prior Over / (Under) month £m (Month 7) £m General Fund Revenue 6.358 Red (3.086) Housing Revenue Account (1.720) Green (0.120) Dedicated Schools Grant - Green - Capital Programme - Green -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.