That (i) the LLP arrangement to deliver growth, be noted (ii) to the addition of £0.790m to the Capital Programme for the Fibre Infrastructure project, funding by SIP, be agreed. (iii) the use of SIP funds up to a total of £0.790m of capital funding to improve fibre broadband to Council owned buildings to provide a strategic connection from Hainault Country Park via Fairlop to Barkingside, be agreed. (iv) Delegate authority to the Operational Director, Regeneration Property & Planning in consultation with the Leader and Cabinet Member for Growth and Leisure to agree any additional routing or variations to be contained within the £0.790m grant maximum, be agreed (v) Delegate authority to the Operational Director, Regeneration Property & Planning in consultation with the Leader and Cabinet Member for Growth and Leisure, be agreed, to enter into: · any grant contract, drawdown or delivery agreement for LLP as required to access SIP funding, subject to approval by the City of London Corporation · any land or highways consents required to establish the strategic route · procurement of contractor to deliver fibre infrastructure and fibre provider subject to state aid compliance · Agreement of the operating model as set out in 4.7. · (vi) the intention to bid for round 2 as part of the Local London SIP Partnership, be noted.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1Cabinet agreed on 12 December 2017 to participate in the London Business Rates Pilot Pool (LBRPP) for 2018/19. The pooling arrangement enabled the retention of a greater percentage of Business Rates paid by firms in London to be shared between the GLA and the boroughs making up the pool, of which 15% was allocated to the Strategic Investment Pot (SIP). The SIP is administered by the London Local Enterprise Partnership (LEAP) and is allocated through a competitive bidding process.
1.2The London Borough of Redbridge is a member of the Local London Partnership (LLP) along with seven other London Boroughs; Barking and Dagenham, Bexley, Enfield, Greenwich, Havering, Newham and Waltham Forest. LLP works in partnership to deliver growth and identify opportunities at sub regional level to tackle challenges around housing, skills and employment and transport. Part of LLPs growth strategy focusses on ensuring the boroughs have access to a world class digital infrastructure by developing their own fibre connectivity strategies. LLP submitted a bid to secure SIP monies which would support the delivery of superfast and ultrafast fixed broadband services to public buildings alongside offering borough wide coverage of high speed, high capacity wireless services.
1.3LEAP awarded £46.830m through the SIP with £7.700m awarded to the LLP for the Local London Investment in Fibre project. Each Borough has been allocated £0.790m. This paper seeks approval to apply the funds towards works in Hainault where planned investment in upgrading the Borough’s CCTV system will be augmented with additional capacity to support the roll out of much needed fibre connections on Hainault Business Park; the Borough’s largest commercial/industrial area.
Recommendations
The Cabinet is recommended to:
2.1note the LLP arrangement to deliver growth
2.2agree to the addition of £0.790m to the Capital Programme for the Fibre Infrastructure project, funding by SIP 2.3 authorise the use of SIP funds up to a total of £0.790m of capital funding to improve fibre broadband to Council owned buildings to provide a strategic connection from Hainault Country Park via Fairlop to Barkingside.
2.4Delegate authority to the Operational Director, Regeneration Property & Planning in consultation with the Leader and Cabinet Member for Growth and Leisure to agree any additional routing or variations to be contained within the £0.790m grant maximum.
2.5Delegate authority to the Operational Director, Regeneration Property & Planning in consultation with the Leader and Cabinet Member for Growth and Leisure to enter into:
2.5.1 any grant contract, drawdown or delivery agreement for LLP as required to access SIP funding, subject to approval by the City of London Corporation 2.5.2 any land or highways consents required to establish the strategic route 2.5.3 procurement of contractor to deliver fibre infrastructure and fibre provider subject to state aid compliance 2.5.4 Agreement of the operating model as set out in 4.7.
2.6Note the intention to bid for round 2 as part of the Local London SIP Partnership.
THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN
Cabinet Member Contact Point Name: Cllr Jas Athwal Position: Leader and CabinetMemberforGrowthandLeisure Telephone: 020 8708 9083 Email: [email protected]
Contact Point Report Author: Sharon Strutt Position: Head of Regeneration Telephone: 020 8708 2143 Email: [email protected] 3. Background, Proposals and Reasons for the Decision
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.