That ( i ) the concept design for phase two of the public realm transformation works, be approved; (ii) delegate authority to the Operational Director of Regeneration, Property and Planning in consultation with the Cabinet Member for Civic Pride and the Cabinet Member for Growth and Leisure to approve the detailed designs for phase two of the public realm transformation works, be agreed; (iii) authorise the use of £4.857m of the approved [The] Spark and Renewing Ilford Public Realm Capital Budget to implement the scheme, be agreed. (iv) delegate authority to the Operational Director of Regeneration, Property and Planning in ... view the full minutes text for item 17.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1Since adopting an exciting new vision for Ilford, co-produced with local residents and businesses, the pace of change in Ilford has been building rapidly. The first 600 new homes in the town centre are almost complete, works are now underway to completely redevelop Ilford Station and add a third entrance, investment has bought much needed family friendly facilities and events into the Exchange shopping centre and the first phase of The Spark project opens imminently with Space Studios providing more than 40 studios for local artists in otherwise redundant parts of the Town Hall.
1.2Looking ahead there is much to be excited about with the Council well progressed on proposals to upgrade the local market and roll out a broad events programme, a further 1,500 new homes having been granted planning consent, the anticipated commencement of the second phase of The Spark featuring Mercato Metropolitano’s food market and the opening of the Elizabeth Line. Beyond that, the Council has made its intentions to lead the broader regeneration of the town centre clear with recent announcements in respect of planned theatre and leisure facilities as well as a new Town Hall.
1.3The High Street and the roads running off of it provide the central link between these initiatives and the Council has long acknowledged that improving the quality of the public realm will improve the image of Ilford and provide the infrastructure needed to promote a wide variety of events and activities in the town centre. Having completed the first phase of the public realm transformation project in December 2018, monitored its performance and sought feedback and views from a range of stakeholders the Council is now seeking to implement the second phase of the transformation works.
1.4When complete, the second phase will renew the stretch of public realm along the High Road, connecting the Crossrail Complementary Works (CCM) to the junction of Cranbrook Road, along to Clements Road and a spur into Oakfield Road; offering new paving, street furniture, lighting, water and play features and public art alongside new planting. Anticipated to start on site early next year, Phase 2 will be completed within 12 months. This report outlines the work done to design the second phase and seeks delegated authority to procure and implement the works under the previously agreed budgets. 2. Recommendations
Cabinet is recommended to:-
2.1approve the concept design for phase two of the public realm transformation works;
2.2delegate authority to the Operational Director of Regeneration, Property and Planning in consultation with the Cabinet Member for Civic Pride and the Cabinet Member for Growth and Leisure to approve the detailed designs for phase two of the public realm transformation works;
2.3authorise the use of £4.857m of the approved [The] Spark and Renewing Ilford Public Realm Capital Budget to implement the scheme; and
2.4delegate authority to the Operational Director of Regeneration, Property and Planning in consultation with the Cabinet Member for Growth and Leisure to procure and award such contracts as required to deliver phase two of the public realm transformation works.
THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN
Cabinet Member Contact Point Name: Cllr Jas Athwal Position: Leader and Cabinet Member for Growth and Leisure Telephone: 020 8708 9083 Email: [email protected]
Contact Point Report Author: Sharon Strutt Position: Head of Regeneration Telephone: 020 8708 2143 Email: [email protected] 3. Background and Proposals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.