Budgetary Control Report for Quarter 3

Noted Executive 5 papers

Cabinet noted this item on Tuesday 11 February 2020. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That ( i ) the £7.268m forecast overspend position to the 2019/20 General Fund revenue budget, be noted. (ii) the balanced forecast position of £240.519m in relation to the 2019/20 DSG, be noted. (iii) the underspend of £0.157m in relation to the Housing Revenue Account against its gross budget of £28.854m at year end, be noted. (iv) the forecast outturn position reported on the capital programme in section 12 of the report, be noted. (v) the progress and delivery of the approved savings programme (RAG - Red £6.437m, Amber £1.110m, Green £4.028m and Blue £10.607m). To ensure savings delivery for all red saving items, substitutions are expected to be identified, be noted. (vi) the intra-directorate revenue virements as listed in paragraph 7.1, be noted (vii) the capital virements as identified in paragraphs 12.2-12.4, be noted. (viii) the addition of £2.061m capital funding for Special Provision Fund in 2019/20 as identified in paragraph 12.10 and an additional £0.450m from Transport for London for Highways capital projects as identified in paragraph 2.11, be approved. (ix) capital slippage of £51.873m into 2020/21 and the acceleration of £0.501m from 2020/21 as detailed in section 12, be approved. (x) slippage of £17.081m into 2020/21 in the HRA capital programme as identified in paragraph 12.8, be approved. (xi) the performance information as per section 14, be noted.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report sets out the Authority’s financial performance to 31 December 2019 and the forecast outturn for 2019/20.

Recommendations

The Cabinet is recommended to:

2.1Note the £7.268m forecast overspend position to the 2019/20 General Fund revenue budget.

2.2Note the balanced forecast position of £240.519m in relation to the 2019/20 DSG.

2.3Note the underspend of £0.157m in relation to the Housing Revenue Account against its gross budget of £28.854m at year end.

2.4Note the forecast outturn position reported on the capital programme in section 12 of the report.

2.5Note the progress and delivery of the approved savings programme (RAG - Red £6.437m, Amber £1.110m, Green £4.028m and Blue £10.607m). To ensure savings delivery for all red saving items, substitutions are expected to be identified.

2.6Note the intra-directorate revenue virements as listed in paragraph 7.1

2.7Note the capital virements as identified in paragraphs 12.2-12.4.

2.8Approve the addition of £2.061m capital funding for Special Provision Fund in 2019/20 as identified in paragraph 12.10 and an additional £0.450m from Transport for London for Highways capital projects as identified in paragraph 2.11.

2.9Approve capital slippage of £51.873m into 2020/21 and the acceleration of £0.501m from 2020/21 as detailed in section 12.

2.10Approve slippage of £17.081m into 2020/21 in the HRA capital programme as identified in paragraph 12.8.

2.11Note the performance information as per section 14. THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT

MAY BE CALLED IN

Cabinet Member Contact Point Name: Cllr Kam Rai Position: Deputy Leader/Cabinet Member for Finance and Resources Telephone: 020 8708 2020 Email: [email protected]

Contact Point Report Author: Ian Ambrose Position: Operational Director of Finance (Deputy s151 Officer) Telephone: 0208 708 6410 Email: [email protected] 3. Background and Proposals

3.1Budgetary control reports are presented to Cabinet so that the Council’s revenue and capital programme can be monitored. It is essential that frequent monitoring takes place in order to ensure that the Council’s financial resources are properly controlled.

3.2In accordance with Financial Standing Orders 129, an Action Plan will be presented to Cabinet where the lower of an overspend of £0.200m or 5% of budget cannot be prevented from occurring through normal management action. Section 6 sets out the planned mitigating actions to address this.

3.3This report highlights the main risks and issues that are being addressed by Corporate Directors to maintain expenditure within the approved Revenue Budget and Capital Programme. It also provides a summary of progress in delivering savings brought forward from 2018/19 and those due to be delivered in 2019/20. Where these actions require the virement of budgets, they are reported for noting in accordance with financial regulations.

4. Summary Position

4.1Table 1 below shows the General Fund revenue summary forecast outturn position before and after recommended virements. Detailed revenue budgets are set out in Appendix A.

Table 1: Summary

Budget as at Inter Revised Year-end Forecast Change Quarter 2 Virements Budget as at Forecast as variation since Department Quarter 3 at Quarter 3 against Quarter 2 budget £m £m £m £m £m £m People 94.461 - 94.461 106.583 12.122 2.465 Place 23.992 (0.051) 23.941 31.508 7.567 3.395 Resources 14.264 0.231 14.495 13.905 (0.590) (0.333) Strategy 5.339 0.051 5.390 5.759 0.369 (0.029) Total Service Directorate Budgets 138.056 0.231 138.287 157.755 19.468 5.498 Corporate Budgets 49.938 (0.231) 49.707 37.507 (12.200) (7.200) Net Budget requirement 187.994 - 187.994 195.262 7.268 (1.702)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
7.1 Appendix A: Revenue Forecast Quarter 3Appendix 116 KB Download
PDF
7.2 Appendix B: Savings Tracker Quarter 3Appendix 174 KB Download
PDF
7.3 Appendix C: Capital Programme Quarter 3Appendix 230 KB Download
PDF
7.4 Appendix D: Performance Framework Q3Appendix 368 KB Download
PDF
Budgetary Control Report for Quarter 3Report 605 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
JA
Councillor Jas AthwalChair, apologies
KR
Councillor Kam RaiVice-Chair, present
EN
Councillor Elaine NormanMember, present
MA
Councillor Mark A. SantosMember, present
SA
Councillor Sheila A. BainMember, present
JP
Councillor John Peter HowardMember, present
HM
Councillor Helen Mary CoombMember, present
FK
Councillor Farah Khanum HussainMember, present
RC
Councillor Robert C. LittlewoodMember, present

On this subject at Redbridge

Search all
  1. Budgetary Control Report for Quarter 3This decision
  2. Budgetary Control ReportNoted
  3. Budgetary Control Report Outturn for 2025/26Noted
  4. Budgetary Control Outturn 2025/26Noted
  5. Budgetary Control Report for Quarter 3 2025-26Noted
  6. Budgetary Control report for 2024/25Noted

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies