That ( i ) the £42.706m forecast overspend position to the 2020/21 General Fund revenue budget, be noted ; (ii) the balanced forecast position of £248.928m in relation to the 2020/21 DSG; , be noted; (iii) the forecast overspend position of £1.000m in relation to the Housing Revenue Account due to COVID-19, be noted; (iv) the mitigation plans relating to the forecast outturn position as a Month 2 2020/21 as reported to July Cabinet and the requirement for further mitigation plans to be presented to November Cabinet in relation to the current forecast overspends as per section 6 and Appendix E( i ) - (xii), be noted; (v) the progress and delivery of the approved savings programme (RAG - Red £15.992m, Amber £5.271m, Green £0.954m and Blue £4.966m). Note the progress and delivery of the approved savings programme (RAG - Red £15.992m, Amber £5.271m, Green £0.954m and Blue £4.966m). To ensure savings delivery for all red saving items, substitutions are expected to be identified, be noted (vi) the forecast outturn position reported on the capital programme in section 12 of the report, be noted ; (vii) the addition of £0.976m capital funding comprised of £0.898m TFL Grant Funding and £0.078m DfT Grant Funding in 2020/21 as identified in paragraph 12.2, be approved ; (viii) the reduction of £2.430m capital funding in 2020/21, following the reduction of TFL Grant allocation, as identified in paragraph 12.2, be approved ; (ix) the forecast COVID-19 impact and associated grant funded as set out in section 14, be noted; and (x) the performance update as set out in section 15 and Appendix D, be noted
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1This report sets out the Authority’s financial performance to 30 June 2020 and the forecast outturn for 2020/21.
Recommendations
The Cabinet is recommended to:
2.1Note the £42.706m forecast overspend position to the 2020/21 General Fund revenue budget;
2.2Note the balanced forecast position of £248.928m in relation to the 2020/21 DSG;
2.3Note the forecast overspend position of £1.000m in relation to the Housing Revenue Account due to COVID-19;
2.4Note the mitigation plans relating to the forecast outturn position as a Month 2 2020/21 as reported to July Cabinet and the requirement for further mitigation plans to be presented to November Cabinet in relation to the current forecast overspends as per section 6 and Appendix E(i) - (xii);
2.5Note the progress and delivery of the approved savings programme (RAG - Red £15.992m, Amber £5.271m, Green £0.954m and Blue £4.966m). Note the progress and delivery of the approved savings programme (RAG - Red £15.992m, Amber £5.271m, Green £0.954m and Blue £4.966m). To ensure savings delivery for all red saving items, substitutions are expected to be identified;
2.6Note the forecast outturn position reported on the capital programme in section 12 of the report;
2.7Approve the addition of £0.976m capital funding comprised of £0.898m TFL Grant Funding and £0.078m DfT Grant Funding in 2020/21 as identified in paragraph 12.2.
2.8Approve the reduction of £2.430m capital funding in 2020/21, following the reduction of TFL Grant allocation, as identified in paragraph 12.2.
2.9Note the forecast COVID-19 impact and associated grant funded as set out in section 14.
2.10Note the performance update as set out in section 15 and Appendix D. THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT
MAY BE CALLED IN
Cabinet Member Contact Point Name: Cllr Kam Rai Position: Deputy Leader/Cabinet Member for Finance and Resources Telephone: 020 8708 2020 Email: [email protected]
Contact Point Report Author: Ian Ambrose Position: Operational Director of Finance (Deputy s151 Officer) Telephone: 0208 708 6410 Email: [email protected] 3. Background and Proposals
3.1Budgetary control reports are presented to Cabinet so that the Council’s revenue and capital programme can be monitored. It is essential that frequent monitoring takes place in order to ensure that the Council’s financial resources are properly controlled.
3.2In accordance with Financial Standing Orders 129, an Action Plan will be presented to Cabinet where the lower of an overspend of £0.200m or 5% of budget cannot be prevented from occurring through normal management action. Section 6 sets this out in more detail.
3.3This report highlights the main risks and issues that are being addressed by Corporate Directors to maintain expenditure within the approved Revenue Budget and Capital Programme. It also provides a summary of progress in delivering savings brought forward from 2019/20 and those due to be delivered in 2020/21. Where these actions require the virement of budgets, they are reported for noting in accordance with financial regulations.
3.4Clearly the Council’s response to the COVID-19 pandemic continues to overlay considerable complexity and uncertainty to forecasting, given that the financial impact ranges from additional expenditure requirements, increases in demand from vulnerable clients, consequential losses of income and the inability for services to work normally. The forecasting is in this area is also affected by the unknown length of the emergency or indeed the extent and depth of any consequential recession.
4. Summary Position
4.1Table 1 below shows the General Fund revenue summary forecast outturn position before and after recommended virements. Detailed revenue budgets are set out in Appendix A.
Table 1: Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.