Cabinet, Thursday 10 February 2022

Budgetary Control Report for Quarter 3

Noted Executive 6 papers

Cabinet noted this item on Thursday 10 February 2022. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

That ( i ) the forecast overspend position of £15.602m in relation to the 2021/22 General Fund Service Directorate Revenue Budget, be noted; ii. the forecast overspend position of £1.248m in relation to the overall 2021/22 General Fund budget, be noted; iii. that Dedicated Schools Grant (DSG) is forecasting an in-year underspend of £0.479m at Quarter 3, be noted. iv. that Housing Revenue Account is forecasting a deficit of £0.689m. This is an increase of £0.503m since Quarter 2, be noted. v. that services forecasting overspends as set out in Section 11 and Section 17 will require Mitigation Plans presented to the next Cabinet meeting, be noted. vi. The services which were currently forecasting an overspend and therefore required to produce an Action Mitigation Plan to address their residual forecast overspend to present to the next Cabinet meeting as per financial standing order 129 are: - Civic Pride - Civic Pride (Capital) - Housing - Customer Help, Digital & Complaints - Adult Social Care - Children & Families - Education & Inclusion - Communications - Director of Strategy vii. the approved virements processed as set out in Appendix A and Section 12 of this report, be noted. viii. the progress and delivery of the approved savings programme (RAG - Red £5.079m, Amber £0.359m, Green £1.721m and Blue £10.527m). To ensure savings delivery for all red saving items, substitutions are expected to be identified and implemented, be noted; ix. the forecast outturn position of £101.862m for the capital programme in section 17 of the report, be noted. x. capital slippage of £71.466m into future years as identified in Table 25, be noted • £53.131m slippage in the General Fund • £18.335m slippage in the HRA xi. capital acceleration of £0.723m from future years as identified in Table 26, be noted · £0.034m for Redbridge Low Emission Neighbourhoods · £0.113m for Wanstead High School · £0.479m for Wanstead Swimming Pool · £0.290m for Chadwell Primary School · £0.077m for Lifecycle and Refresh xii. the addition of £0.645m of capital grant funding to projects as identified in Table 27, be noted · £0.055m Forestry Commission England grant for Replacement Tree Planting on the Highway · £0.111m Basic Needs Grant for Gearies School · £0.105m Basic Needs Grant for Uphall Primary School · £0.150m Local Digital Fund: Round 5 grant for Housing IT Modernisation · Programme xiii. the reduction of £0.250m for Ilford Station Southern Entrance, as identified in Table 28, be noted xiv. the approved capital virements as detailed in paragraphs 17.11 to 17.15 with a total movement out of Corporate of £3.629m, be noted.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.131 December 2021 and the forecast outturn for 2021/22.

1.2Full details are set out in the report and additional information is provided in the following appendices:

• Appendix A Detailed Revenue Outturn • Appendix B 2021/22 Savings Tracker • Appendix C 2021/22 Capital Programme • Appendix D 2021/22 Performance Framework • Appendix E - H 2021/22 Mitigation Plans

Recommendations

The Cabinet is recommended to:

2.1Note the forecast overspend position of £15.602m in relation to the 2021/22 General Fund Service Directorate Revenue Budget;

2.2Note the forecast overspend position of £1.248m in relation to the overall 2021/22 General Fund budget;

2.3Note that Dedicated Schools Grant (DSG) is forecasting an in-year underspend of £0.479m at Quarter 3.

2.4Note that Housing Revenue Account is forecasting a deficit of £0.689m. This is an increase of £0.503m since Quarter 2.

2.5Note that services forecasting overspends as set out in Section 11 and Section 17 will require Mitigation Plans presented to the next Cabinet meeting.

2.6The services which are currently forecasting an overspend and therefore required to produce an Action Mitigation Plan to address their residual forecast overspend to present to the next Cabinet meeting as per financial standing order 129 are:

- Civic Pride - Civic Pride (Capital) - Housing - Customer Help, Digital & Complaints - Adult Social Care - Children & Families - Education & Inclusion - Communications - Director of Strategy

2.7Note the approved virements processed as set out in Appendix A and Section 12 of this report. 2.8. Note the progress and delivery of the approved savings programme (RAG - Red £5.079m, Amber £0.359m, Green £1.721m and Blue £10.527m). To ensure savings delivery for all red saving items, substitutions are expected to be identified and implemented;

2.9Note the forecast outturn position of £101.862m for the capital programme in section 17 of the report.

2.10Note capital slippage of £71.466m into future years as identified in Table 25

• £53.131m slippage in the General Fund

• £18.335m slippage in the HRA

2.11Note capital acceleration of £0.723m from future years as identified in Table 26

2.11.1 £0.034m for Redbridge Low Emission Neighbourhoods 2.11.2 £0.113m for Wanstead High School 2.11.3 £0.479m for Wanstead Swimming Pool 2.11.4 £0.290m for Chadwell Primary School 2.11.5 £0.077m for Lifecycle and Refresh

2.12Note the addition of £0.645m of capital grant funding to projects as identified in Table 27

2.12.1 £0.055m Forestry Commission England grant for Replacement Tree Planting on the Highway 2.12.2 £0.111m Basic Needs Grant for Gearies School 2.12.3 £0.105m Basic Needs Grant for Uphall Primary School 2.12.4 £0.150m Local Digital Fund: Round 5 grant for Housing IT Modernisation Programme

2.13Note the reduction of £0.250m for Ilford Station Southern Entrance, as identified in Table 28

2.14Note the approved capital virements as detailed in paragraphs 17.11 to 17.15 with a total movement out of Corporate of £3.629m.

THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT

MAY BE CALLED IN

Cabinet Member Contact Point Name: Cllr Kam Rai Position: Deputy Leader/Cabinet Member for Finance, Leisure and Culture Telephone: 020 8708 2020 Email: [email protected]

Contact Point Report Author: Ian Ambrose Position: Operational Director of Finance (Deputy s151 Officer) Telephone: 0208 708 6410 Email: [email protected] 3. Background and Proposals

3.1B and capital programme can be monitored. It is essential that frequent monitoring

controlled.

3.2In accordance with Financial Standing Orders 129, an Action Plan will be presented to Cabinet where the lower of an overspend of £0.200m or 5% of budget cannot be prevented from occurring through normal management action. Section 6 sets this out in more detail.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
9.1 Appendix A: Revenue Forecast Quarter 3 (002)Appendix 28 KB Download
PDF
9.2 Appendix Bi: Savings Tracker 2021-22 Q3 (002)Appendix 79 KB Download
PDF
9.3 Appendix Bii: Savings Tracker 2021-22 Q3 (002)Appendix 54 KB Download
PDF
9.4 Appendix Biii: Movements since Q2 (002)Appendix 37 KB Download
PDF
9.5 Appendix C: Capital Forecast Quarter 3 (002)Appendix 340 KB Download
PDF
Budgetary Control Report for Quarter 3Report 461 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
JA
Councillor Jas AthwalChair, present
KR
Councillor Kam RaiVice-Chair, apologies
EN
Councillor Elaine NormanMember, apologies
MA
Councillor Mark A. SantosMember, present
SA
Councillor Sheila A. BainMember, present
JP
Councillor John Peter HowardMember, present
HM
Councillor Helen Mary CoombMember, present
JB
Councillor Jo BlackmanMember, present
VS
Councillor Vanisha S. B. SolankiMember, present
KM
Councillor Khayer M. R. ChowdhuryMember, present

On this subject at Redbridge

Search all
  1. Budgetary Control Report for Quarter 3This decision
  2. Budgetary Control ReportNoted
  3. Budgetary Control Report Outturn for 2025/26Noted
  4. Budgetary Control Outturn 2025/26Noted
  5. Budgetary Control Report for Quarter 3 2025-26Noted
  6. Budgetary Control report for 2024/25Noted

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies