That (i) the progress of Phase 1 of the Digital Programme in the implementation of 27 projects that realise Digital Programme to achieve £2.609m in efficiencies of which £1.637m is a revenue saving over a three-year period, be noted. ii. the second phase of the Digital Programme which will draw on £1.180m of the conditional capital programme for 2022/23 to deliver the three further programmes commissioned by Children’s, Adults and Communities, be approved. iii. that prior to any expenditure, business cases for each respective workstream will be developed and agreed with each directorate and Finance, with efficiencies identified forming part of the 2023/24 Medium Term Financial Strategy, be noted. vi. that the culmination of the Phase 2 work will deliver radically new and improved customer experiences and with that, new efficiencies across those service areas to increase the digitisation of services utilised by residents necessitated by the Covid-19 pandemic and the Digital Economies Act 2017, be noted.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1This report provides a summary update on Phase 1 of the Digital Programme and requests formal approval to continue funding Phase 2 as previously agreed at last year’s Cabinet Meeting 20/04/2021.
1.2Phase 1 commenced in April 2021, has successfully delivered 26 of 27 projects originally commissioned with one project delayed until the second quarter of 2022. The programme has been a real success notably winning awards for cutting-edge development of Robotic Process Automation RPA within Redbridge council systems.
1.3This report seeks to outline the forward plan of work that will utilise £1.180m of the conditional capital programme for 2022/23 to drive forward the development of the Digital Front Door programme which will span the Adult Social Care, Children and Families and Communities Directorate. This continues the delivery of the MTFS projects and delivering 3 new programs of work commissioned by Adults, Children’s and Communities.
Recommendations
Cabinet is recommended to:-
2.1Note the progress of Phase 1 of the Digital Programme in the implementation of 27 projects that realise Digital Programme to achieve £2.609m in efficiencies of which £1.637m is a revenue saving over a three-year period.
2.2Approve the second phase of the Digital Programme which will draw on £1.180m of the conditional capital programme for 2022/23 to deliver the three further programmes commissioned by Children’s, Adults and Communities.
2.3Note that prior to any expenditure, business cases for each respective workstream will be developed and agreed with each directorate and Finance, with efficiencies identified forming part of the 2023/24 Medium Term Financial Strategy.
2.4Note that the culmination of the Phase 2 work will deliver radically new and improved customer experiences and with that, new efficiencies across those service areas to increase the digitisation of services utilised by residents necessitated by the Covid-19 pandemic and the Digital Economies Act 2017. THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN
Cabinet Member Contact Point Name: Cllr Helen Coomb Position: Cabinet Member for Transformation and Digital Telephone: 020 8708 9072 Email: [email protected]
Contact Point Report Author: Cassandra Gardiner & Emeran Saigol Position: Head of Digital Delivery / Operational Director Digital, Customer Experience and Community Safety Telephone: 0208 708 9072 / 02087085477 E.Mail: [email protected] / [email protected] 3. Background and Proposals 3.1 Legacy technology creates a series of issues and without stripping out the full suite will never be solved. Everything ages and will need to be replaced eventually. However, it does have to be managed. In the past, there was a tendency to just replace things and run digital transformation strategies. This approach can work, but often leads to a complex web of systems that need to be integrated – generally through replicated manual entry. Employees have to take information from one system and often manually enter it into another. Another approach has been the disaggregation of technology across the entire public sector. In the past, the Government tended to choose a few large systems integrators to run large IT projects and systems for a number of years. Arguably, this is what has created much of the monolithic and unwieldy legacy technology we now have. Redbridge currently hosts 359 IT applications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.