CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Redbridge
Cabinet, Thursday 20 July 2023

Digital Programme: Shaping our Future

Approved Executive 1 paper

Cabinet approved this item on Thursday 20 July 2023. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

That ( i ) the drawdown of the capital funds allocated against the digital programme . The total draw down is £1.671m. This total is made up of already confirmed work and monies to be applied to business cases as they are finalised. It is managed as i.i . The drawdown of £1.065m conditionally held capital is to progress the Adult Social Care and Children’s & Families business cases; i.ii . The drawdown of the remaining £0.606m capital is to progress the planned workstreams for Communities, Resources and Regeneration and Culture. These funds will be approved through the completion of business cases that are approved and confirmed by Corporate Strategy Group. (ii)Delegate to the Chief Executive, in consultation with the Portfolio Holder for Resources and Transformation, approval of the Communities, Resources and Regeneration & Culture Business Cases, and the subsequent incurring of capital expenditure, be agreed; (iii)that the programme is under the governance of the Corporate Strategy Group and the Shaping our Future Board. Monthly Highlight Reports are submitted for scrutiny and monitoring each board via the Council's programme management office, be noted. (iv) the ambition of the Digital Programme Shaping our Future is to deliver a new and improved customer experience and long-term efficiencies across the organisation. This is about budgetary savings as well as self-serve models of delivery, be noted. (v) the continued work and progression on the Councils Digital Infrastructure and Digital Inclusion workstreams, be noted.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report provides a summary update on the Digital Programme and requests approval to continue funding of the Council’s Digital Programme as previously agreed at last year’s Cabinet Meeting 7/03/2022.

1.2Cabinet on 8 March 2022 approved the 2nd Phase of the Digital Programme, subject to business cases for each respective workstream being developed and agreed with each directorate and Finance, with efficiencies identified forming part of the 2023/24 Medium Term Financial Strategy. a skeleton digital team was retained to minimise overheads and finalise Digital Phase 1 projects. Phase 1 is complete and formally closed, acceptance of the programme and its benefits agreed by a panel of Corporate Directors chaired by the Chief Executive.

1.3This report seeks to outline the forward plan of work that will utilise £1.671m of the conditional capital programme for 2023/24 to drive forward the development of a new Customer Front Door Digital Front Door programme which will span the ongoing Adult Social Care, Children and Families, Housing and Communities Directorate programmes, as well as new work spanning all operations to establish a Customer Front door model, which is one of 8 major new Shaping our Future (SoF) programmes.

Recommendations

The Cabinet Member/Cabinet is recommended to:-

2.1Approve the drawdown of the capital funds allocated against the digital programme . The total draw down is £1.671m. This total is made up of already confirmed work and monies to be applied to business cases as they are finalised. It is managed as

2.1.1 The drawdown of £1.065m conditionally held capital is to progress the Adult Social Care and Children’s & Families business cases; 2.1.2 The drawdown of the remaining £0.606m capital is to progress the planned workstreams for Communities, Resources and Regeneration and Culture. These funds will be approved through the completion of business cases that are approved and confirmed by Corporate Strategy Group.

2.2Delegate to the Chief Executive, in consultation with the Portfolio Holder for Resources and Transformation, approval of the Communities, Resources and Regeneration & Culture Business Cases, and the subsequent incurring of capital expenditure;

2.3Note that the programme is under the governance of the Corporate Strategy Group and the Shaping our Future Board. Monthly Highlight Reports are submitted for scrutiny and monitoring each board via the Council's programme management office.

2.4Note the ambition of the Digital Programme Shaping our Future is to deliver a new and improved customer experience and long-term efficiencies across the organisation. This is about budgetary savings as well as self-serve models of delivery .

2.5Note the continued work and progression on the Councils Digital Infrastructure and Digital Inclusion workstreams.

Reasons for recommendations

3.1The resources required to facilitate the digital programmes will be applied to specific programmes. However, each programme may also provide efficiencies and learnings to future digital programmes. The draw down enables the current agreed work to progress at pace and also to facilitate future business cases.

3.2The recommendations recognise the need for robust governance and accountability as well as the potential of benefits across multiple areas of the organisation. Through the recommended draw down and associated governance the organisation will be able to achieved its digital ambitions and importantly deliver savings and better services

3.3The Digital strategy focuses on outcomes for residents, employees, and service users. It sets out clear principles for the Council to work to. These principles are:

 Make online services an excellent, consistent customer experience so that our customers choose it as their channel of choice.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Digital Programme: Shaping our FutureReport 478 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
KR
Councillor Kam RaiVice-Chair, present
MA
Councillor Mark A. SantosMember, apologies
HM
Councillor Helen Mary CoombMember, present
JB
Councillor Jo BlackmanMember, present
KM
Councillor Khayer M. R. ChowdhuryMember, present
JA
Councillor Jas AthwalMember, present
VS
Councillor Vanisha SolankiMember, present
LJ
Councillor Lloyd Jacob DuddridgeMember, apologies
NB
Councillor Namreen B. ChaudhryMember, present
SE
Councillor Sahdia E WarraichMember, present

On this subject at Redbridge

Search all
  1. Digital Programme: Shaping our FutureThis decision
  2. Digital Programme Conditional FundingApproved
  3. Digital Programme Phase 2 SummaryNoted
  4. Digital Programme Phase 1 summary and Capital InvestmentApproved
  5. Digital Programme and Capital InvestmentNoted

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies