Highways and Transportation Capital Programme 2023-24

Noted Executive 2 papers

Cabinet noted this item on Tuesday 28 March 2023. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That ( i ) the Redbridge funded Capital and relevant Revenue programmes as set out in 4.11 Table 1 of the report and with details in Appendix A (section 1 - internal) totalling £6.249m, be noted. (ii) Acknowledge that external bid for LIP (Local Implementation Plans) schemes from TfL to address the Mayor’s Transport Strategy objectives has been submitted to Cabinet under a separate report on 9 th February 2023 and the bid is set out in 4.11 Table 2 for reference totalling £2.658m, be noted. (iii)Acknowledge the external bids and work already underway in 4.11 Table 3 for grants won by the Council which totals as a minimum £2.900m, be noted. (iv) the annual work programme for Highway Resurfacing, Vision Zero (Accident Remediation), Flood Alleviation, School Streets and with inclusion of cycling and pedestrian improvements subject to funds being made available from the Council’s Capital programme and External funding detailed in Appendix A of this report, be approved. (v) Delegate authority to the Operational Director for Highways, Parking & Transportation, in consultation with the Cabinet Member for Environment and Civic Pride, to approve works changes within each funded programme, be agreed. (vi) Delegate authority to the Operational Director for Highways, Parking & Transportation in consultation with the Cabinet Member for Civic Pride to submit bids for new or additional external funding for highways works and, where such bids are successful, and to enter into the required documentation to enable the Council to receive such funding, be agreed. (vii) to delegate authority to the Operational Director for Highways, Parking & Transportation in consultation with the Cabinet Member for Civic Pride to bid to Transport for London for major schemes, asset renewals, cycle links, cycle training, air quality, freight, cycle and bus infrastructure, EV infrastructure and officer training, and approve the related expenditure in 2023-24, be agreed. (viii) £1.500m spend within the capital programme for Transport and Traffic Management as identified in Table 1 (para 4.11), be approved. (ix) to delegate approval of any minor works changes within each funded programme, any change in the priority of schemes and development of future bids to the Operational Director Highways, Parking and Transportation in consultation with the Cabinet Member for Environment and Civic Pride, be approved. (x) Delegate authority to the Corporate Director of Resources in consultation with the Deputy Leader/Cabinet Member for Resources, Leisure and Culture any budget amendments due to additional grant being award and received to any expenditure taking place as per recommendations 2.6, 2.7 and 2.10, be agreed
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report informs Cabinet of the Major Highways Works programme 2023-24. The funds being allocated from the Council’s budgets and external sources on the Council’s Highways Capital Programme and detailed further in Appendix A of this report.

1.2The report also provides the strategic aims and principles guiding the use of the funds and prioritisation summarised in Appendix A of this report.

Recommendations

The Cabinet is recommended to:-

2.1Note the Redbridge funded Capital and relevant Revenue programmes as set out in 4.11 Table 1 of the report and with details in Appendix A (section 1 - internal) totalling £6.249m.

2.2Acknowledge that external bid for LIP (Local Implementation Plans) schemes from TfL to address the Mayor’s Transport Strategy objectives has been submitted to Cabinet under a separate report on 9th February 2023 and the bid is set out in 4.11 Table 2 for reference totalling £2.658m.

2.3Acknowledge the external bids and work already underway in 4.11 Table 3 for grants won by the Council which totals as a minimum £2.900m.

2.4Approve the annual work programme for Highway Resurfacing, Vision Zero (Accident Remediation), Flood Alleviation, School Streets and with inclusion of cycling and pedestrian improvements subject to funds being made available from the Council’s Capital programme and External funding detailed in Appendix A of this report. 2.5 Delegate authority to the Operational Director for Highways, Parking & Transportation, in consultation with the Cabinet Member for Environment and Civic Pride, to approve works changes within each funded programme.

2.6Delegate authority to the Operational Director for Highways, Parking & Transportation in consultation with the Cabinet Member for Civic Pride to submit bids for new or additional external funding for highways works and, where such bids are successful, and to enter into the required documentation to enable the Council to receive such funding.

2.7Agree to delegate authority to the Operational Director for Highways, Parking & Transportation in consultation with the Cabinet Member for Civic Pride to bid to Transport for London for major schemes, asset renewals, cycle links, cycle training, air quality, freight, cycle and bus infrastructure, EV infrastructure and officer training, and approve the related expenditure in 2023-24.

2.8Approve £1.500m spend within the capital programme for Transport and Traffic Management as identified in Table 1 (para 4.11).

2.9Agree to delegate approval of any minor works changes within each funded programme, any change in the priority of schemes and development of future bids to the Operational Director Highways, Parking and Transportation in consultation with the Cabinet Member for Environment and Civic Pride.

2.10Delegate authority to the Corporate Director of Resources in consultation with the Deputy Leader/Cabinet Member for Resources, Leisure and Culture any budget amendments due to additional grant being award and received to any expenditure taking place as per recommendations 2.6, 2.7 and 2.10,

Reasons for recommendations

3.1The Highways capital programme focuses on a number of key issues particularly around safety in an attempt to meet Council strategies and the Mayor’s Transport Strategy.

3.2The programme also incorporates works that will meet the borough’s statutory functions such as asset renewals of its carriageways and footways and its flood alleviation work.

3.3The external funds listed in the report match the Council’s priorities and focus such as road safety schemes, school streets, cycle training, and installing new cycle routes within the borough to improve active and sustainable travel.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10.1 Appendix A: Capital Programme MasterAppendix 673 KB Download
PDF
Highways and Transportation Capital Programme 2023-24Report 443 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
KR
Councillor Kam RaiVice-Chair, present
MA
Councillor Mark A. SantosMember, present
SA
Councillor Sheila A. BainMember, present
JP
Councillor John Peter HowardMember, present
HM
Councillor Helen Mary CoombMember, present
JB
Councillor Jo BlackmanMember, present
KM
Councillor Khayer M. R. ChowdhuryMember, present
JA
Councillor Jas AthwalChair, present
HO
Helen O'TooleOfficer, expected
VS
Councillor Vanisha SolankiMember, present
JE
Julian EllerbyOfficer, expected

On this subject at Redbridge

Search all
  1. Highways and Transportation Capital Programme 2023-24This decision
  2. Highways and Transportation Capital Programme 2024-25Noted
  3. Highways and Transportation Scrutiny Task and Finish Group Outcome ReportAgreed
  4. Review of Fees and Charges for Highways and Transportation, including Parking (CAB/16/111218)Approved
  5. 2017/2018 Highways and Transportation Major Works Programme and Variations to the 2016/17 Programme (CAB/10/040417)Approved
  6. 2017/2018 Highways and Transportation Major Works Programme and Variations to the 2016/17 ProgrammeAgreed

More from Redbridge Cabinet

All decisions
MeetingDecisionOutcome
17 Jun 2026 Minutes of the Previous Meeting Held on 23 April 2026 - To FollowAgreed. Agreed Open
17 Jun 2026 Forward PlanThat the items shown in the for 1 June 2026 to 31 October 2026 be agreed. Agreed Open
17 Jun 2026 Budgetary Control Report Outturn for 2025/26That ( i ) the outturn against budget of £269.751m in relation to the 2025/26 General Fund Service Directorate Revenu... Noted Open
17 Jun 2026 Regionalisation of Fostering Recruitment, Assessment and SupportThat ( i ) LB Redbridge’s continued involvement in Local Community Fostering, as one of the four Local Authorities wi... Approved Open
17 Jun 2026 Preparation and Programme for a new Local PlanThat ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies