That ( i ) to release £1.600m of conditional capital budget from the “Rolling Schools Expansion” scheme to provide budget for the major works at Chadwell Primary School’s Key Stage 1 building, be agreed. (ii) Delegate authority to the Corporate Director of Regeneration and Culture and Operational Director for Capital Delivery, Planning, Property and Regeneration, in consultation with the Lead Member for Children’s Services, to finalise terms and appoint a contractor selected through the procurement process and based on the specialist advisor’s reviews of the tenders submitted, be agreed.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1A new Key Stage 1 building to accommodate rising pupil numbers at Chadwell Primary was completed in 2013. Within a matter of months of completion, the school reported issues with dampness which continued until the Council and school agreed that pupils would need to vacate the building to all for specialist assessments to establish the causes and best option to address the problem.
1.2Between September 2021 and October 2022, the Council commissioned a series of studies and specialist surveys.
1.3Following those extensive and comprehensive specialist surveys, the Council was advised at the end of October 2022 that the building could be repaired. In mid-March 2023, the specialist assessors completed their review of tenders submitted by three contractors, based on the technical specification. This has identified the budget requirement for the major repairs which will be needed.
1.4The report is now urgent because the timescale for work means that we need the period from April to the end of August to complete the repairs. This will allow us to return the children to the main building from September 2023 and allow the Council to complete the technical arrangements for removing the current temporary accommodation on the school site during the school summer holiday period.
Recommendations
The Cabinet is recommended to: -
2.1Agree to release £1.600m of conditional capital budget from the “Rolling Schools Expansion” scheme to provide budget for the major works at Chadwell Primary School’s Key Stage 1 building
2.2Delegate authority to the Corporate Director of Regeneration and Culture and Operational Director for Capital Delivery, Planning, Property and Regeneration, in consultation with the Lead Member for Children’s Services, to finalise terms and appoint a contractor selected through the procurement process and based on the specialist advisor’s reviews of the tenders submitted. 3. Reasons for Recommendations
3.1Carrying out the repairs will ensure that the Key Stage 1 building will be suitable for the pupils and staff to access and in addressing the underlying causes of the problems with the building, it will ensure that the school no longer need to arrange for frequent repairs to the building which has been the case previously.
3.2Once the repairs are complete, pupils will be able to vacate the temporary classrooms on site at the end of the Summer Term 2023 and it will then allow the Council to make arrangements for the temporary classrooms to be removed from the school site during the school summer break.
THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY NOT BE CALLED IN
Cabinet Member Contact Point Name: Cllr Mark Santos Position: Cabinet Member for Children and Young People Telephone: 020 8708 Email: [email protected]
Contact Point Report Author: Colin Stewart Position: Director of Education and Inclusion Telephone: 0208 708 3378 Email: [email protected] 4. Background and Proposals
3.1A new Key Stage 1 building to accommodate rising pupil numbers at Chadwell Primary was completed in 2013. Within a matter of months of completion, the school reported issues with dampness. Despite frequent further works by the initial contractors who completed the scheme in 2013, the problems with dampness in the building have continued.
3.2By the end of the academic year 2020-21, specialists advised that more substantial investigations were needed into the root cause of the problems with dampness and consequently, the school had to move all the Key Stage 1 pupils into other parts of the school, with some moving into temporary classrooms which were placed on the school site during the summer of 2021.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.