That (i) the annual work programme of 2025-26 for the Redbridge funded Capital programme (£8.350m), as well as the Capital and Revenue programme for Transport for London LIP (Local Implementation Plan) works (£6.021m), and the various Capital external grants (£12.348m) as per 4.12 Tables 1,2 and 3 totalling £26.719m for 2025-26, be approved (ii) that any slippage from the financial year 2024-25 will be added to the relevant budgetary area following approval by Cabinet as part of the Provisional Outturn report for 2024/25 and spent on the programmes included within Appendix A, be agreed. (iii) Delegate authority to the Operational Director Highways, Parking & Transportation, in consultation with the Cabinet Member for Environment and Sustainability, to approve works changes within each programme, be agreed. (iv) Delegate authority to the Operational Director for Highways, Parking & Transportation, in consultation with the Cabinet Member for Environment and Sustainability, to submit new bids for new or additional external funding to relevant agencies, and where such bids are successful, enter into the relevant approval process to enable the Council to receive and spend such funding as per the conditions of the funding, be agreed. (v) the drawing down of funds marked as conditional in the report approved by Full Council on the 25 February 2025, which are Traffic Calming Measures £1.000m labelled as Traffic Calming and Road Safety Measures in 4.12 Table 1 below, and River Roding Environment Agency Contribution £0.500m also in 4.12 Table 1 for the use of the schemes outlined in Appendix A as per 2.1, be approved.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1This report informs Cabinet of the Major Highways Works programme 2025-26. The funds being allocated from the Council’s budgets and external sources on the Council’s Highways Capital Programme and detailed further in Appendix A of this report.
1.2The report also provides the strategic aims and principles guiding the use of the funds and prioritisation of the programmes within Appendix A of this report.
1.3The report also makes reference to external funds notably Transport for London (TfL) LIP funding. The figures provided are what has been bid for at the time of writing as formal approval has yet to be received for the entire bid.
Recommendations
The Cabinet is recommended to:-
2.1Note and approve the annual work programme of 2025-26 for the Redbridge funded Capital programme (£8.350m), as well as the Capital and Revenue programme for Transport for London LIP (Local Implementation Plan) works (£6.021m), and the various Capital external grants (£12.348m) as per 4.12 Tables 1,2 and 3 totalling £26.719m for 2025-26.
2.2Agree and note that any slippage from the financial year 2024-25 will be added to the relevant budgetary area following approval by Cabinet as part of the Provisional Outturn report for 2024/25 and spent on the programmes included within Appendix A.
2.3Delegate authority to the Operational Director Highways, Parking & Transportation, in consultation with the Cabinet Member for Environment and Sustainability, to approve works changes within each programme.
2.4Delegate authority to the Operational Director for Highways, Parking & Transportation, in consultation with the Cabinet Member for Environment and Sustainability, to submit new bids for new or additional external funding to relevant agencies, and where such bids are successful, enter into the relevant approval process to enable the Council to receive and spend such funding as per the conditions of the funding.
2.5Approve the drawing down of funds marked as conditional in the report approved by Full Council on the 25 February 2025, which are Traffic Calming Measures £1.000m labelled as Traffic Calming and Road Safety Measures in 4.12 Table 1 below, and River Roding Environment Agency Contribution £0.500m also in 4.12 Table 1 for the use of the schemes outlined in Appendix A as per 2.1.
Reasons for recommendations
3.1The Highways capital programme focuses on a number of key issues particularly around improving road safety to meet Council plans, strategies and the Mayor’s Transport Strategy.
3.2The programme also incorporates works that will meet the borough’s statutory functions such as asset renewals of its carriageways and footways, its road safety improvement programme, and its flood alleviation work.
3.3The external funds listed in the report match the Council’s priorities and focus such as road safety schemes, school streets, increasing electric vehicle charge points, cycle training, and installing new cycle routes within the borough to improve active and sustainable travel.
3.4All works submitted have been prioritised using various prioritisation matrices and value engineering methodologies to ensure value for money for the investment made.
THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN
Cabinet Member Contact Point Name: Cllr Jo Blackman Position: Cabinet Member for Environment and Sustainability Email: [email protected]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.