That ( i ) modifications to the existing funding and management agreement with Vision RCL to, be approved: · extend the term of the agreement by 12 months until 31 March 2027; and · incorporate an option to extend the term of the agreement (at the Council’s sole discretion) by a further 12 months until 31 March 2028 for a value of £11.12m per annum (based on 2025/26 costs) and subject to indexation, in accordance with CSO 105.7; (ii) that beyond the modifications proposed at 2.1 above, no further modifications to the existing contract terms are recommended, be agreed; (iii) Give delegated authority to the Executive Director Place, Communities and Enterprise to agree the final terms of the modifications to the funding and management agreement, be agreed; and (iv) that officers will report back to Cabinet with the outcomes of FMG Consulting’s detailed options appraisal and full business case for the future delivery of leisure and culture services for consideration and approval of next steps no later than early 2026, be noted. Recommendation 2.5 is set out in exempt Appendix A to this report. Councillor Coomb declared an interest in the Proposal for the Delivery of Leisure and Culture Services post March 2026 report and left the room.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1The report provides a proposal for the delivery of leisure and culture services beyond the existing agreement with Vision RCL which expires on 31 March 2026.
1.2Council officers and FMG Consulting (FMG) are currently evaluating the range of options available to the Council to deliver these services in the longer term.
1.3To enable this detailed work to be completed this report recommends an extension of the agreement with Vision RCL of 12 months until 31 March 2027 (with the option of a further 12 month extension if required) in order to maintain service delivery whilst providing sufficient time for the completion of a detailed options appraisal and full business case by FMG and the mobilisation of new arrangements for the services thereafter, in readiness for contract expiry.
1.4A further report will be brought back to Cabinet with the outcomes of FMG’s detailed analysis and recommendations for the future service delivery model and proposed next steps. This is anticipated later in 2025.
Recommendations
Cabinet is recommended to:-
2.1Approve modifications to the existing funding and management agreement with Vision RCL to:
i. extend the term of the agreement by 12 months until 31 March 2027; and ii. incorporate an option to extend the term of the agreement (at the Council’s sole discretion) by a further 12 months until 31 March 2028
for a value of £11.12m per annum (based on 2025/26 costs) and subject to indexation, in accordance with CSO 105.7; 2.2 Agree that beyond the modifications proposed at 2.1 above, no further modifications to the existing contract terms are recommended;
2.3Give delegated authority to the Executive Director Place, Communities and Enterprise to agree the final terms of the modifications to the funding and management agreement; and
2.4Note that officers will report back to Cabinet with the outcomes of FMG Consulting’s detailed options appraisal and full business case for the future delivery of leisure and culture services for consideration and approval of next steps no later than early 2026.
Recommendation 2.5 is set out in exempt Appendix A to this report.
Reasons for recommendations
3.1The existing funding and management agreement with Vision RCL is due to expire on 31 March 2026 and the Council will be required to make a decision as to the future delivery of the services currently delivered by Vision RCL after this date.
3.2It is intended that officers will report to Cabinet no later than early 2026, informed by FMG’s options analysis and business case, with recommendations for future delivery of the services. Whilst it is not possible to pre-empt the recommendations that will result from FMG’s report, options may include insourcing the services, re-procuring the services, or to split the services (or any combination of these). It is acknowledged that there is unlikely to be time before 31 March 2026 for the Cabinet’s decision on the future of the services to be implemented.
3.3At this stage, officers anticipate that a one-year extension to 31 March 2027 will provide adequate time for a Cabinet decision to be implemented. However, officers also recognise that there are a range of different recommendations that may be made as a consequence of FMG’s options analysis and that additional time beyond 31 March 2027 may be required to implement those recommendations while ensuring ongoing service delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.