RESOLVED THAT COMMITTEE: Approve the virement for £4,360 between the Temporary Housing Scheme and the Clitheroe Affordable Housing Scheme, as requested by Health and Housing Committee. Approve that £135,000 be brought forward from the 2025/26 capital programme to the 2024/25 capital programme to enable the purchase of a replacement JCB Loadall, as requested by Community Committee.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO POLICY AND FINANCE COMMITTEE
meeting date: 10 SEPTEMBER 2024 title: OVERALL CAPITAL MONITORING 2024/25 submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: JEAN WADDINGTON
1. PURPOSE
1.1To report the progress on the Council’s approved 2024/25 capital programme for the period to the end of July 2024.
1.2Relevance to the Council’s ambitions and priorities: • Community Objectives - none identified. • Corporate Priorities - to continue to be a well-managed council, providing efficient services based on identified customer need. • Other considerations - none identified. 2. CAPITAL PROGRAMME 2024/25 BACKGROUND 2.1. The detail provided in this report relate to the capital programme for all committees, and includes the UK Shared Prosperity Fund and Rural England Prosperity Fund Schemes. 2.2. There were 35 capital schemes that were originally approved totalling £6,352,000 (including budget and schemes moved from 2023/24). These were approved by the Policy and Finance Committee and Full Council at their meetings in February 2024 and March 2024 respectively. 2.3. At the 2023/24 year-end, it was identified that there were 24 schemes that had not been completed. The balance of budget for these schemes was £1,074,300, and the transfer of this budget to the 2024/25 financial year is known as slippage. 2.4. There have also been twelve new schemes approved and additional/transfer of budget approved for four existing schemes. These additional approvals totalled £512,760. 2.5. As a result of the above, the total approved capital programme of 60 schemes is £7,939,060. This is provided in detail at Annex 1. 3. CAPITAL MONITORING 2024/25 3.1. The table below summarises the position on the capital programme. Totals for All Committees Scheme £ Count Original Estimate 2024/25 19 2,671,190 Schemes and Budget moved from 2023/24 16 3,680,810 Total Original Estimate as per Budget Book 35 6,352,000 Slippage from 2023/24 13 1,074,300 Additional Approvals in year 2024/25 12 512,760 Current Total Approved Budget 2024/25 60 7,939,060 Actual Spend and Commitments – April to July 1,181,022 Remaining Budget as at the end of July 2024 6,758,039
52-24pf 1 of 11 3.2. At the end of July 2024, £1,181,022 had been spent or committed. This is 14.9% of the full year approved capital programme of £7,939,060. 3.3. Shown at Annex 1 is a table showing a breakdown of the position as at the end of July 2024. 4. LATEST COMMENTS ON RED FLAGGED SCHEMES 4.1. The table below provides a summary of the latest comments from budget holders for the 8 schemes flagged as ‘Red’ - Unlikely to be completed within the financial year.
Cost Scheme Name Latest Comments Centre
Castle Keep Lime Repointing The necessary structural works on the Castle CASKP Works and Repairs Keep, as identified by a recently completed survey, will cost significantly more than the allocated budget. To allow for a bid to the Heritage Lottery Fund for the shortfall, CASKP will need to be considered together with IMWCG to comply with the Heritage Improvement Works to Castle and IMWCG Lottery Fund requirements. The budget Grounds holder recommends the remaining CASKP budget be moved into the 2025/26 financial year when the capital programme is reviewed at the Revised Estimate.
There are no appropriate economic ECDVI Economic Development Initiatives development opportunities in progress that are likely to be funded from this budget.
Introduction of Planning Portal No upgrades to the current system have Link to the Planning Application PLANN been needed or identified as being needed System and Planning System so far in 2024/25. Update
Legal advice received has not supported a model of assisting first time buyers with a deposit but suggested investigating a shared equity model. Members approved further EQSOS Assisted Purchase Scheme investigations of this model. Options are being considered for the commitment of commuted sum allocations in Chipping and Chatburn.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies