RESOLVED THAT COMMITTEE: 1. Noted the final overspend figure of £358,650 to be funded from general fund balances. 2. Agreed that the Towneley Gardens and the Sabden Village Hall car park should be considered by the UKSPF Working Group as part of the consideration of the Council’s 2025/26 UKSPF and REPF allocation with recommendations reported back to Committee. 3. Agreed to fund the fencing needed at Longridge Pump Track from the 2025/26 UKSPF allocation.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
RIBBLE VALLEY BOROUGH COUNCIL REPORT TO POLICY AND FINANCE COMMITTEE meeting date: TUESDAY, 17 JUNE 2025 title: UK SHARED PROSPERITY FUND AND RURAL ENGLAND PROSPERITY FUND (2022-2025) submitted by: DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING principal author: NICOLA HOPKINS – DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING
1 PURPOSE
1.1To update Members in respect of the Council’s original UK Shared Prosperity Fund (UKSPF) and Rural England Prosperity Fund (REPF) and to seek approval for some projects to be considered as part of this years UKSPF and REPF allocations.
1.2Relevance to the Council’s ambitions and priorities:
• Community Ambitions-
•To sustain a strong and prosperous Ribble Valley •To help make people’s lives safer and healthier
• Corporate Objectives – •To work with our partners to ensure that the infrastructure in the Ribble Valley is improved •To promote stronger, more confident, and more active communities throughout the borough
2 BACKGROUND 2.1 As Committee are aware Ribble Valley received the following funding allocations: 2.1.1 UKSPF- £1,967,754 for the years 2022-2025 2.1.2 REPF- £433,680 for the years 2023-2025
2.2The funding needed to be spent by the end of March 2025. All of the schemes were overseen by both the UKSPF Working Group and Policy and Finance Committee with the Economic Development section managing the delivery of all the schemes. All of the funding was utilised and schemes delivered within the prescribed time scales. Full details of the schemes supported and delivered are attached at Appendix 1.
3 OVERSPEND 3.1 Committee agreed to support all the projects listed at Appendix 1 which exceeded both the UKSPF and REPF allocations. Committee has previously agreed to utilise £217,393 from general fund balances to fund the overspend associated with the UKSPF schemes and £229,863 from general fund balances to fund the overspend associated with the REPF schemes.
3.2Following the payment of all the invoices associated with all the schemes Committee will note that the overspend associated with UKSPF was £150,756 and the overspend associated with REPF was £207,894. As such the total amount of funding taken from general fund balances will be £358,650.
4 OUTSTANDING SCHEMES 4.1 Committee will note that the following schemes were not delivered by the end of March 2025. Towneley Gardens Event Space (allocation £100,000) 4.2 Only £10,725 of the original £100,000 UKSPF allocation was utilised to deliver this scheme to concept design stage. This followed a decision by Policy and Finance Committee in June 2024 where it was agreed to allocate £10,000 of UKPSF to the design of the Towneley Garden event space, this was due to the inability to secure a design and build contract for the work. As such in respect of this project work progressed and was completed (before the end March 2025) wholly on the design element of the scheme.
4.3Following the previous Committee meeting the Head of Engineering has now worked out the costings for the scheme.
4.4At the meeting of this Committee on 1st April it was agreed that the UKSPF Working Group would meet to consider other suitable capital projects and revenue schemes for the Council’s 2025/26 UKSPF allocation. As such it is suggested that the Towneley Gardens scheme is considered by the first meeting of the Working Group. Committee are advised however that the indicative costings for the concept scheme as designed exceeds the remaining UKSPF 2025/26 allocation. The recommendations from the Working Group will be reported back to this Committee.
4.5Committee will also note the Expression of Interest into the Ribble Valley Shared Prosperity and Jubilee Fund from Longridge Town Council reported elsewhere on this agenda.
Sabden Village Hall project (allocation £12,270) 4.6 This project was not delivered (nor was a grant agreement entered into) prior to the end of March 2025 and as such has not been funded by the Council’s original REPF allocation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.