CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Ribble Valley Borough Council
Health and Housing, Thursday 15 January 2026 at 6.30pm

Revised Revenue Budget 2025/26

Agreed Committee 1 paper

AI summaryRibble Valley's Health and Housing Committee agreed the revised revenue budget for 2025/26, lowering net spending by £184,730 after earmarked reserves, driven mainly by S106 developer contributions set aside for capital use.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedHealth and Housing Committee revenue estimate approved
Money£184,730 decrease after reservesNet spend down from £1,671,820 to £175,760
What happens nextNone specifiedNo further steps set out in report
Who it affectsHealth and Housing Committee cost centresIncludes housing, environmental health, cemetery, market

What was decided

The committee agreed the revenue revised estimate for 2025/26, which reduces net expenditure by £1,496,060 before earmarked reserves, and by £184,730 after them. Report 4.2, 6.1

Why

The original estimate was set in March 2025, and revising it now allows the council to forecast the likely outturn and inform the next year's original budget. Report 2.3

The pay award for 2025/26 settled at 3.2%, lower than the 4% originally allowed, with prices and income allowed at 2.5%. Report 3.3

Most of the headline change comes from S106 developer contributions received into service revenue budgets and then transferred to the capital earmarked reserve, so they show as a large movement before reserves but have a net nil effect overall. Report 4.2, 6.2, P53

What happens next

The revised figures will feed into preparation of the original estimate for the coming financial year. Report 2.3

The money

  • 1,671,820 Original net estimate 2025/26 Report P33
  • 175,760 Revised net estimate 2025/26 Report P33
  • 1,496,060 Decrease in net expenditure before earmarked reserves Report 4.2, 6.1
  • 184,730 Decrease in net expenditure after earmarked reserves Report 4.2, 6.1
  • 1,304,050 S106 monies transferred to capital earmarked reserve (Affordable Housing) Report P35, P53
  • -53,110 Reduction in support services recharge to Environmental Health Report P45
  • -76,492 Increase in Homelessness Prevention Grant income Report P50
  • -46,190 Estimated increase in income on Improvement Grants cost centre Report P51

Options considered

  • Chosen: Agree the revenue revised estimate for 2025/26. Reflects latest monitoring, settled pay award, and S106 treatment for capital programme Report 3.3, 6.2

Implications

  • Risk: Sound financial planning through the budget monitoring process is said to safeguard the council's reputation. Report P58
  • Equalities: Equality and diversity issues are considered in the provision of all council services. Report P59
  • Other: No technical, environmental, legal, or political implications were identified. Report P58

Who and where

  • Ribble Valley Borough Council's Health and Housing Committee services, including Clitheroe Cemetery, Environmental Health, Housing Benefits, Homelessness Strategy, Improvement Grants, Joiners Arms and Affordable Housing. Report P16, P22, P24, P25, P26, P27, P33
  • Tenants and applicants for housing, homelessness prevention and Disabled Facilities Grants. Report P25, P26, P50
  • Council staff, with changes in officer time allocations and a temporary Homelessness Prevention Officer post recognised. Report P45, P50

Timeline

  • March 2025: Original revenue estimate for 2025/26 set
  • End of November 2025: Actual spending position used to inform revised estimate Report 3.6, P62
  • 15 January 2026: Health and Housing Committee agrees revised revenue budget 2025/26 Report P3

Plain English for the jargon

  • S106 monies: Payments from developers under section 106 planning obligations, used here to fund the capital programme via the capital earmarked reserve.
  • Earmarked reserves: Council funds set aside for a specific purpose, such as capital works or housing-related grants.
  • DFG: Disabled Facilities Grants, capital grants to help adapt homes for disabled occupants.
  • DWP: Department for Work and Pensions, which oversees housing benefit administration and returns.
  • Renters Rights Act: New legislation referenced as a source of grant income for Environmental Health Services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item567

Resolved

RESOLVED THAT COMMITTEE: Agree the revenue revised estimate for 2025/26.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Health and Housing

DECISION

RIBBLE VALLEY BOROUGH COUNCIL REPORT TO HEALTH AND HOUSING COMMITTEE

meeting date: meeting date: 15 JANUARY 2026 title: REVISED REVENUE BUDGET 2025/26 title: submitted submitted by:by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: principal author: JEAN WADDINGTON

1 PURPOSE

1.1To agree a revised revenue budget for 2025/26 for this committee.

2 BACKGROUND 2.1 The original estimate for this current financial year was set in March 2025.

2.2As members will be aware, there can be numerous variations to the budget that come to our attention as the year progresses, particularly through the budget monitoring process.

2.3At this time of year we revise the estimates for the current financial year in order to predict the likely outturn. In essence the Revised Estimate is the council's latest forecast for the outturn on the current financial year's budget. This also assists us in preparing the original estimate for the coming financial year.

3 REVISING THE ORIGINAL ESTIMATE 3.1 Since the budget was originally set we now have the benefit of information from the outturn position for 2024/25 and the variances that were experienced in that financial year. Furthermore, as we have been monitoring our budgets during the year we can also use this information to inform the revised budget process. 3.2 When setting our budgets for the current year we decided to allow 4% for pay, and 2.5% for prices and income increases.

3.3The pay award for 2025/26 has now been settled at 3.2% which was slightly lower than the 4% allowed for.

3.4There have been detailed discussions with budget holders and heads of service on past service provision and future plans both playing an important part in the budget setting process.

3.5Committee decisions during the year have also been incorporated into the budget setting process where appropriate.

3.6The revised estimates for this committee are set out in the following section. There are also details of the current actual position as at the end of November against the profiled Original Estimate and alongside the proposed Revised Estimate at Annex 1.

4 PROPOSED REVISED REVENUE BUDGET 2025/26

4.1A comparison between the Original and Revised budgets for each cost centre is shown below, together with the associated movements in earmarked reserves. DCN 01 Net (Multiple Items) Expenditure

3-26hh Page 1 of 9 Original Movement in Movement in Revised Cost Centre and Movement in Movement in Estimate Support Capital Estimate Description Expenditure Income 2025/26 Services Charges 2025/26 AFHOU: Affordable Rent 21,140 9,030 -1,302,460 -320 -7,670 -1,280,280 Properties APLAC: 16 Alma Place 3,120 500 -60 -620 210 3,150 Clitheroe AWARM: Affordable 0 63,150 -50,320 12,830 Warmth

CLAIR: Clean Air 4,960 -60 4,900

CLAND: Contaminated 12,310 -4,200 8,110 Land CLCEM: Clitheroe 79,300 -4,320 -11,500 -5,030 58,450 Cemetery CLDCY: Closed 4,630 1,060 840 6,530 Churchyards

CLMKT: Clitheroe Market -39,250 16,750 -8,980 -350 -7,230 -39,060

CMGHH: Community 9,700 -4,930 4,770 Groups - Health & Housing

COMNL: Common Land 5,450 -1,750 3,700

CTBEN: Localised Council 271,210 80 -22,130 249,160 Tax Support Administration DOGWD: Dog Warden & 176,760 -2,900 1,740 -820 -3,520 171,260 Pest Control ENVHT: Environmental 533,440 -2,100 -920 -51,470 478,950 Health Services

HFORU: Homes for Ukraine 41,790 12,040 3,350 57,180

HGBEN: Housing Benefits 261,280 -217,240 174,620 -1,330 217,330 Administration HOMEE: Home Energy 11,580 -40 610 12,150 Conservation HOMES: Homelessness 56,220 28,740 -68,130 -15,610 1,220 Strategy HSASS: Housing 7,970 -950 7,020 Associations

HSTRA: Housing Strategy 45,860 -2,860 2,180 45,180

3-26hh Page 2 of 9 Original Movement in Movement in Revised Cost Centre and Movement in Movement in Estimate Support Capital Estimate Description Expenditure Income 2025/26 Services Charges 2025/26 IMPGR: Improvement 91,430 -45,380 30,640 76,690 Grants

JARMS: Joiners Arms 48,630 5,790 12,660 1,660 190 68,930

SHARE: Shared Ownership -450 870 420 Rents

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Revenue Budget 2025/26Report 265 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 22 attended
MH
Councillor Mark HindleChairman, present
JA
Councillor John AthertonCommittee Member, apologies
SA
Councillor Stephen AtkinsonCommittee Member, apologies
A(
Councillor Anthony (Tony) AustinCommittee Member, present
DB
Councillor Derek BrocklehurstCommittee Member, present
LE
Councillor Louise EdgeVice-Chair, present
R(
Councillor Rosemary (Rosie) ElmsCommittee Member, present
SF
Councillor Steve FarmerCommittee Member, present
DO
Councillor Donna O'RourkeCommittee Member, present
CM
Councillor Charles McFallCommittee Member, present
MP
Councillor Malcolm PeplowCommittee Member, present
RR
Councillor Rachael RayCommittee Member, present

All 22 on the meeting page

On this subject at Ribble Valley

Search all
  1. Revised Revenue Budget 2025/26This decision
  2. Revised Revenue Budget 2025/26Agreed
  3. Revised Revenue Budget 2025/26Agreed
  4. Revised Revenue Budget 2025/26Agreed
  5. Revised Revenue Budget 2025/26Agreed
  6. Revised Revenue Budget 2024/25Agreed

More from Ribble Valley Health and Housing

All decisions
MeetingDecisionOutcome
3 Sep 2026 Dog Control Public Spaces Protection Order 2026RESOLVED THAT COMMITTEE: 1. Having regard to the provisions of Section 60 of the Anti-Social Behaviour, Crime and Pol... Approved Open
3 Sep 2026 Public Health Act Funerals PolicyRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Public Health Act Funerals Policy/Procedure. 2. Permit the H... Approved Open
3 Sep 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 2 of Part 1 of Schedule 12A of t... Decided Open
4 Jun 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approve the slippage of £815,630 as set out at paragraph 3.6 of the report. Approved Open