Capital Outturn 2025/26

Approved Committee 1 paper

AI summaryHealth and Housing Committee approved slipping £815,630 of 2025/26 capital budget into 2026/27. Nine of eleven capital schemes were not completed in-year and will carry forward remaining budgets.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNine of eleven capital schemes not completed
Money£815,630Slippage into 2026/27
What happens nextBudgets carry into 2026/27Ongoing works across 9 schemes
Who it affectsCapital schemes for Health and HousingHousing, grants, disabled facilities, market

What was decided

The Committee approved slippage of £815,630 of capital budget from the 2025/26 financial year to 2026/27, as set out in paragraph 3.6 of the report.

The decision covered slippage requests on nine of the eleven capital schemes in the Committee's 2025/26 programme.

Why

Actual expenditure on the Committee's capital programme was £2,223,674, which is 77.4% of the revised estimate budget of £2,871,540. Report 3.2, 2.6

Nine of eleven schemes were not completed in-year, and capital resources are already in place to fund the £815,630 carried forward.

What happens next

The remaining budgets on the nine incomplete schemes, totalling £815,630, are carried forward into 2026/27 for completion or further work.

Specific target dates include Autumn 2026 for Cemetery Lodge, May 2026 for 52 Downham Road, Summer 2026 for Waterloo House, and ongoing delivery through 2026/27 for Disabled Facilities Grants, First Time Buyer Grants and Landlord Tenant Grants. Report P79, P110, P178, P98, P133, P145

The money

  • £815,630 Total slippage from 2025/26 to 2026/27 Report P28
  • £1,443,000 Total original budget component for 2025/26 schemes Report P17, P47
  • £1,717,390 Original estimate 2025/26 Report P17, P47
  • £755,680 Slippage from 2024/25 moved into 2025/26 Report 2.2, P17, P47
  • £139,384 Additional approval for Disabled Facilities Grants, funded by grant Report 2.3, P17, P47
  • £4,055,454 Total approved budget for 11 schemes in 2025/26 Report 2.5, P17, P47
  • £2,871,540 Revised estimate budget for 2025/26 Report 2.6, P17, P47
  • £1,099,620 Budget moved to 2026/27 at revised estimate stage Report 2.6, P17, P47
  • £2,223,674 Actual capital expenditure in 2025/26 Report P17, P47

Options considered

  • Chosen: Approve slippage of £815,630 into 2026/27. Recommended by Director of Resources; nine of eleven schemes not completed in-year and capital resources already in place.

Implications

  • Financial: Overall capital expenditure was contained within the revised estimate, so fewer capital financing resources than budgeted were required in-year.
  • Financial: Capital resources are already in place to fund the £815,630 requested slippage to 2026/27.
  • Risk: Sound financial planning for known capital commitments is described as safeguarding the Council's reputation.
  • Equalities: Equality and diversity issues are examined as part of the capital bid appraisal process.

Who and where

  • Recipients of Disabled Facilities Grants, with the scheme rolling forward Report P39, P97, P98
  • First time buyers awaiting grant funding Report P42, P132
  • Landlords and tenants using Landlord Tenant Grants Report P43, P144
  • Future tenants of refurbished affordable housing at Cemetery Lodge, 52 Downham Road, and Waterloo House Report P78, P109, P46
  • Households using the Temporary Housing Scheme Report P45, P166
  • Users of Clitheroe Market, with further improvement options still being considered Report P41, P120

Timeline

  • February 2025: Original capital programme approved by Special Policy and Finance Committee Report 2.1
  • March 2025: Original capital programme approved by Full Council Report 2.1
  • June 2025: This Committee approved £755,680 of slippage from 2024/25 into 2025/26 Report 2.2
  • January 2026: Committee agreed reallocation of budget between affordable housing schemes Report 2.4
  • February 2026: Special Policy and Finance Committee approved revised estimate of £2,871,540 Report 2.6
  • 25 May 2026: Report dated Report P32
  • 4 June 2026: Committee meeting approving slippage Report P2

Plain English for the jargon

  • Slippage: Unspent capital budget carried forward from one financial year into the next.
  • Revised Estimate: Updated budget for the year, agreed part-way through, reflecting expected changes.
  • Disabled Facilities Grants (DFG): Grants to help adapt homes for disabled occupants, funded by government grant.
  • S106 monies: Funds paid by developers under Section 106 planning agreements, used for affordable housing and related purposes.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68

Resolved

RESOLVED THAT COMMITTEE: Approve the slippage of £815,630 as set out at paragraph 3.6 of the report.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Health and Housing

DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO HEALTH AND HOUSING COMMITTEE

meeting date: 4 JUNE 2026 title: CAPITAL OUTTURN 2025/26 submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: JEAN WADDINGTON

1 PURPOSE

1.1The purpose of this report is to review the final outturn of the 2025/26 capital programme for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2025/26 financial year to the 2026/27 financial year.

1.2Relevance to the Council’s ambitions and priorities: • Community Objectives – none identified. • Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need. • Other Considerations – none identified.

2 2025/26 CAPITAL PROGRAMME BACKGROUND

2.1There were 5 capital schemes for this Committee’s original estimate budget, totalling £3,160,390. These were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2025 and March 2025 respectively. This included 4 new budgets for 2025/26 and budget for 3 schemes that had been moved from the 2024/25 capital programme.

2.2In addition, at the end of the 2024/25 financial year a total budget of £755,680 covering 6 schemes was unspent and was moved into the 2025/26 capital programme budget, after approval by this Committee in June 2025. This unspent budget that was moved is known as slippage.

2.3Additional budget of £139,384 was approved for the Disabled Facilities Grants Scheme. This was funded by grant monies and therefore had no impact on the Council’s resources.

2.4Budget was reallocated between affordable housing capital schemes, ending one scheme and creating 3 new schemes, which was agreed by this Committee in January 2026.

2.5As a result of the above elements, the total approved budget for this Committee’s 2025/26 capital programme of 11 schemes was £4,055,454.

2.6Later in the year the 2025/26 capital programme budget was revised to £2,871,540 in respect of 11 schemes and was then approved by the Special Policy and Finance Committee in February 2026. This followed a review of progress on all schemes in the capital programme and included moving budget of £1,099,620 on 5 schemes into the 2026/27 financial year. The revised estimate budget is shown at Annex 1.

2.7During the financial year this Committee has received reports monitoring the progress of schemes within the capital programme.

7-26hh 1 of 16 3 CAPITAL OUTTURN 2025/26

3.1Annex 1 shows this Committee’s capital programme outturn position by scheme, including budget approvals, actual expenditure in-year and requested slippage into 2026/27. The table below summarises the final outturn position.

Budget Total Original Slippage Additional Revised Budget Actual Requested Moved Approved Estimate from Approvals Estimate Moved to Expenditure Slippage From Budget 2025/26 2024/25 2025/26 2025/26 2026/27 2025/26 into 26/27 2024/25 2025/26

1,443,000 1,717,390 755,680 139,384 4,055,454 2,871,540 1,099,620 2,223,674 815,680

3.2Actual expenditure on this Committee’s capital programme was £2,222,183 which is 77.4% of the revised estimate budget. 3.3 Of the 11 schemes in the revised capital programme 2 were completed in-year. 3.4 The remaining 9 schemes were not completed in-year, resulting in requested slippage from the 2025/26 financial year in to the 2026/27 financial year. 3.5 Annex 2 shows details for each scheme of: • the outcomes achieved for schemes that have been completed; and • where schemes have yet to be completed, requests for Committee approval for slippage into the 2026/27 financial year. 3.6 Shown below is a summary of the slippage requests for this Committee: Slippage Cost Scheme Requested Centre £ CLAFH Cemetery Lodge Affordable Housing Scheme 61,680

CLCED Clitheroe Cemetery Drainage Scheme 0

DISCP Disabled Facilities Grants 191,120

EQSOS Assisted Purchase Scheme 15,180

FCMIM Further Clitheroe Market Improvements -3,730

FTBGR First Time Buyer Grants 82,520

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn 2025/26Report 349 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 23 attended
SB
SImon BrunetOfficer, expected
EE
Erika Eden-PorterOfficer, expected
ST
Sarah ThrelfallOfficer, expected
MH
Councillor Mark HindleChairman, present
JA
Councillor John AthertonCommittee Member, present
A(
Councillor Anthony (Tony) AustinCommittee Member, present
DB
Councillor Derek BrocklehurstCommittee Member, present
LE
Councillor Louise EdgeVice-Chair, apologies
R(
Councillor Rosemary (Rosie) ElmsCommittee Member, present
SF
Councillor Steve FarmerCommittee Member, present
DO
Councillor Donna O'RourkeCommittee Member, present
CM
Councillor Charles McFallCommittee Member, present

All 23 on the meeting page

On this subject at Ribble Valley

Search all
  1. Capital Outturn 2025/26This decision
  2. Capital Outturn 2025/26Approved
  3. Capital Outturn 2025/26Approved
  4. Capital Outturn 2024/25Approved
  5. Capital Outturn 2024/25Approved
  6. Capital Outturn 2024/25Approved

More from Ribble Valley Health and Housing

All decisions
MeetingDecisionOutcome
3 Sep 2026 Dog Control Public Spaces Protection Order 2026RESOLVED THAT COMMITTEE: 1. Having regard to the provisions of Section 60 of the Anti-Social Behaviour, Crime and Pol... Approved Open
3 Sep 2026 Public Health Act Funerals PolicyRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Public Health Act Funerals Policy/Procedure. 2. Permit the H... Approved Open
3 Sep 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 2 of Part 1 of Schedule 12A of t... Decided Open
4 Jun 2026 Civil Penalties Under the Renters' Rights Act 2025 and Other Housing LegislationRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Civil Penalties Under the Renters Rights Act 2025 and Other ... Approved Open
4 Jun 2026 Appointment to Working GroupsRESOLVED THAT COMMITTEE: Approve the continuance of the Strategic Housing working group, the Health and Wellbeing Par... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies