Revised Capital Programme 2025/26

Approved Committee 1 paper

AI summaryHealth and Housing Committee approves a revised 2025/26 capital programme of £2,811,540, cutting £1,209,620 and moving £1,179,620 into 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved2025/26 estimate set at £2,811,540
Money£2,811,540Down £1,209,620 from approved £4,021,160
What happens next£1,179,620 moved to 2026/27Budget carried forward on six schemes
Who it affectsHealth and Housing capital schemesRevised programme covers 9 schemes in 2025/26

What was decided

The committee approved the 2025/26 revised capital estimate of £2,811,540 as set out in Annex 1 of the report. Report 6.1

The revised programme is a £1,209,620 reduction from the previously approved capital budget of £4,021,160. Report P11

Why

Officers reviewed each scheme with budget holders and revised the programme to reflect progress on schemes and estimated full year spending.

The reduction reflects £1,200,000 moved between affordable housing schemes, £1,179,620 transferred to 2026/27, and £30,000 less S106 funding. Report P7, P8, P9, P10

Slippage of £755,680 from six incomplete 2024/25 schemes and £105,090 of extra funding for Disabled Facilities Grants had already been added to the programme. Report P20

What happens next

Budgets totalling £1,179,620 on six schemes will be carried into the 2026/27 financial year. Report P18

Annex 1 sets out the full capital programme by scheme, including budget and spending to date, and Annex 2 links each scheme to a Corporate Plan goal. Report P24, P33

Other reports to the same meeting may propose further changes to the capital schemes, which this report does not take account of.

The money

  • £2,811,540 Proposed revised 2025/26 capital programme estimate for the committee Report P11, 6.1
  • £4,021,160 Total previously approved 2025/26 capital budget Report P6, P20
  • £1,209,620 Reduction in the 2025/26 capital programme
  • £1,179,620 Budget transferred from 2025/26 to 2026/27 Report P9, P18
  • £755,680 Slippage carried from 2024/25 to 2025/26 Report P20
  • £105,090 Additional approved budget for Disabled Facilities Grants Report P20
  • £887,690 Spend or commitments at end of November 2025, equal to 31.6% of revised programme Report 3.7, P20
  • £30,000 Budget reduction due to less S106 funding being available Report P10

Implications

  • Financial: Approval reduces the level of financing resources needed in 2025/26 by £1,209,620, with £1,179,620 transferred to 2026/27 to fund carried forward schemes.
  • Risk: Officers describe the change as supporting sound financial planning for known capital commitments and protecting the council's reputation.
  • Equalities: Equality and diversity issues are considered as part of the capital bid process.

Who and where

  • Budget holders for the nine capital schemes remaining in the 2025/26 programme
  • Disabled Facilities Grants applicants, with £264,630 of budget moved to 2026/27 leaving £911,830 for 2025/26 Report P14
  • Clitheroe Cemetery Drainage Scheme, with £20,120 carried forward to fund preliminary works on the proposed cemetery extension Report P13
  • Clitheroe Market Improvement project, with £497,430 carried forward to allow members to consider options for improving the market Report P15
  • Landlord and tenant grant applicants, with £127,440 carried forward due to lower than expected take up in 2025/26 Report P16
  • Future tenants of the Affordable Housing Flat Scheme, with £270,000 carried forward for refurbishment before use as affordable rental units Report P17

Timeline

  • 5 June 2025: Slippage of £755,680 from 2024/25 approved by the committee
  • End of November 2025: £887,690 had been spent or committed, 31.6% of the revised programme Report 3.7, P20
  • December 2025: Report signed by the Senior Accountant and Director of Resources Report P23
  • 15 January 2026: Committee approved the revised 2025/26 capital estimate of £2,811,540 Report P2
  • 2026/27: Six schemes with £1,179,620 of budget to be carried forward Report P18

Plain English for the jargon

  • Capital programme: The council's planned spending on long term assets and major projects.
  • Slippage: Budget from a previous year that was not spent and is carried into a later year.
  • S106 funding: Money paid by developers under Section 106 of the Town and Country Planning Act to fund local infrastructure.
  • Virement: Moving budget between different budget headings within the same overall budget.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item569

Resolved

RESOLVED THAT COMMITTEE: Approve the 2025/26 revised estimate of £2,811,540 for this Committee’s capital programme, as set out in Annex 1 of the report.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Health and Housing

DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO HEALTH AND HOUSING COMMITTEE

meeting date: 15 JANUARY 2026 title: REVISED CAPITAL PROGRAMME 2025/26 submitted by: DIRECTOR OF RESOURCES principal author: JEAN WADDINGTON

1 PURPOSE 1.1 To approve the 2025/26 revised estimate for this Committee’s capital programme. 1.2 Relevance to the Council’s ambitions and priorities:  Community Objectives – none identified.  Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs.  Other Considerations – none identified. 2 CAPITAL PROGRAMME 2025/26 BACKGROUND 2.1 There were 5 capital schemes that were originally approved for this committee totalling £3,160,390 (including budget and schemes moved from 2024/25). These were approved by the Policy and Finance Committee and Full Council at their meetings in February 2025 and March 2025 respectively. 2.2 At the 2024/25 year-end, it was identified that there were 6 schemes that had not been completed. The balance of budget for these schemes was £755,680, and the transfer of this budget to the 2025/26 financial year is known as slippage and was approved by this committee at the meeting held on 5 June 2025. 2.3 Furthermore, there has been additional, fully funded, budget approved for an existing scheme, Disabled Facilities Grants, totalling £105,090, and capital virements between existing and new affordable housing schemes with no financial impact. 2.4 As a result of the above, the total approved budget for this Committee’s capital programme of 10 schemes is £4,021,160. This is provided in detail at Annex 1. 3 REVISING THE 2025/26 CAPITAL PROGRAMME 3.1 We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect progress on the schemes and estimated full year expenditure. Following this review, the proposed revised 2025/26 capital programme for this committee would reduce by £1,209,620 to £2,811,540 and consist of 9 schemes. 3.2 Committee members are asked to note that reports will be submitted to this meeting regarding some of the capital schemes for Health and Housing Committee. This report takes no account of any changes that these reports propose.

2-26hh 1 of 5 3.3 The reduction of £1,209,620 in the revised capital programme can be accounted for as follows:

Element £

Current Total Approved Budget 4,021,160

Budget moved FROM AHLON and EQSOS -1,200,000

Budget moved TO CLAFH and WLHFS 1,200,000

Less Budget Moved to 2026/27 -1,179,620

Less Budget reduction due to less S106 funding being available -30,000

Resulting Proposed Revised Estimate 2,811,540

3.4Detailed below is a summary of the position on the schemes that are recommended for moving to the 2026/27 financial year. Budget Being Latest Position Resulting in Transfer of Scheme to Scheme Moved to 2026/27 2026/27 £

CLCED: Clitheroe The work on the initial Cemetery Scheme is now Cemetery completed, with this budget being moved to 2026/27 to 20,120 Drainage fund any preliminary works, such as drainage surveys, Scheme on the proposed extension to the cemetery.

A large number of projects have been completed, but activity, and therefore spend, is limited by capacity, and it DISCP: Disabled is highly unlikely that all of the available funds will be spent in the 2025/26 financial year. 264,630 Facilities Grants It is proposed that £264,630 of the budget is moved at this stage to 2026/27 leaving £911,830 in 2025/26.

FCMIM: Further This budget is being moved forward to allow members to Clitheroe Market 497,430 consider various options for improving the market. Improvements

LANGR: Take up on these grants has been lower than expected Landlord/Tenant in 2025/26. The budget is being moved forward in 127,440 Grants anticipation of future higher levels of interest.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Capital Programme 2025/26Report 100 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 22 attended
MH
Councillor Mark HindleChairman, present
JA
Councillor John AthertonCommittee Member, apologies
SA
Councillor Stephen AtkinsonCommittee Member, apologies
A(
Councillor Anthony (Tony) AustinCommittee Member, present
DB
Councillor Derek BrocklehurstCommittee Member, present
LE
Councillor Louise EdgeVice-Chair, present
R(
Councillor Rosemary (Rosie) ElmsCommittee Member, present
SF
Councillor Steve FarmerCommittee Member, present
DO
Councillor Donna O'RourkeCommittee Member, present
CM
Councillor Charles McFallCommittee Member, present
MP
Councillor Malcolm PeplowCommittee Member, present
RR
Councillor Rachael RayCommittee Member, present

All 22 on the meeting page

On this subject at Ribble Valley

Search all
  1. Revised Capital Programme 2025/26This decision
  2. Overall Revised Capital Programme 2025/26Approved
  3. Revised Capital Programme 2025/26Approved
  4. Revised Capital Programme 2025/26Approved
  5. Overall Revised Capital Programme 2024/25Approved
  6. Revised Capital Programme 2024/25 and Future Capital Programme Review and New BidsApproved

More from Ribble Valley Health and Housing

All decisions
MeetingDecisionOutcome
3 Sep 2026 Dog Control Public Spaces Protection Order 2026RESOLVED THAT COMMITTEE: 1. Having regard to the provisions of Section 60 of the Anti-Social Behaviour, Crime and Pol... Approved Open
3 Sep 2026 Public Health Act Funerals PolicyRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Public Health Act Funerals Policy/Procedure. 2. Permit the H... Approved Open
3 Sep 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 2 of Part 1 of Schedule 12A of t... Decided Open
4 Jun 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approve the slippage of £815,630 as set out at paragraph 3.6 of the report. Approved Open
4 Jun 2026 Civil Penalties Under the Renters' Rights Act 2025 and Other Housing LegislationRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Civil Penalties Under the Renters Rights Act 2025 and Other ... Approved Open