Resolved :- (1) That the submission by the SYPTE on behalf of the project partners of a Full Approval application to the DfT for the implementation of the BRT North scheme, with the bid to seek £19.406m from the DfT towards the total scheme cost of £36m be approved. (2) That the Collaboration and Funding Agreement Bus Rapid Transit between Rotherham and Sheffield Northern Route be signed. (The Mayor agreed to exempt this item from call-in on the grounds that it was urgent due to the deadline for submission being 2 nd August, 2013)
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
i) Members approve the submission by the SYPTE on behalf of the project partners of a Full Approval application to the DfT for the implementation of the BRT North scheme, with the bid to seek £19.406m from the DfT towards the total scheme cost of £36m.
ii) The Collaboration and Funding Agreement Bus Rapid Transit between Rotherham and Sheffield Northern Route be signed.
iii)The agreement of the Mayor be sought to exempt this from the provisions of the call in procedure on the grounds that it is urgent. SYPTE have set a deadline of 2 August 2013 for submission of the Full Approval application.
Page 1 7. Proposals and Details A best and final funding bid for BRT North was submitted by SYPTE to the Department for Transport (DfT) on behalf of the scheme partners in September 2011. This was endorsed by Cabinet on 7 September 2011, Minute Number C58 refers. BRT North would operate as a limited stop service from Rotherham to Sheffield via Templeborough, Meadowhall (under the Tinsley Viaduct on a new Link Road), Carbrook, Attercliffe and loop around the City Centre and is planned to serve centre to centre trips but also new developments in the Lower Don Valley.
In December 2011 the DfT announced that this funding bid was successful and since then significant progress has been made on the BRT North scheme. The key milestones achieved since then have been: • Sheffield City Council (SCC) successfully completed the Compulsory Purchase Order process to obtain the land required for BRT North in Sheffield • SCC has tendered and is currently assessing Tenders for the construction of Tinsley Link which forms a substantial part of the BRT North project. • SCC has secured £3,000,000 from the Growing Places Fund to cover Section 106 (S106) contributions until these have been paid.
SYPTE currently intend to make the application for full scheme approval to the DfT on 2 August 2013.
Collaboration and Funding Agreement In order to define the legal and financial responsibilities of SYPTE, RMBC and SCC in delivering this major transport scheme a Collaboration and Funding Agreement has been produced. This establishes the Partners’ respective obligations with regard to the project and compliance with requirements of the funding bodies.
The Partnership agreement has been reviewed by both Legal and Financial Services and they have no adverse comments.
8. Finance The latest cost estimate for the BRT North project is approximately £36 million and the table below shows how this would be funded.
Source Amount European Regional Development Fund (ERDF) £11,296,386 Department for Transport £19,406,000 Section 106 Contributions £3,000,000 Local Transport Plan £2,000,000 Total Cost £35,707,386
The latest cost estimate for the element of the project within Rotherham (Work Package 26) is £715,582 comprising of £504,267 works costs, £137,000 allowance for risk and £74,315 for inflation. Work Package 26 consists of two
Page 2 new bus and cycle lanes, a Toucan crossing, widening the A6021 Sheffield Road approach to Ickles roundabout to two lanes and minor changes to road markings at Ickles and Templeborough roundabouts. Drawing number 126/17/TT235, showing these works, is attached as Appendix A.
The table below shows the predicted spend profile for Work Package 26.
2013-2014 2014-2015 2015-2016 Design £14,700 Supervision £50,000 Works £504,627
Note that Design and Supervision costs are funded from SYPTE’s Local Transport Plan allocation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.