CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
Cabinet (Pre-Intervention, Wednesday 2 June 2004

Bus Rapid Transit North - Submission of Major Scheme Best and Final Funding Bid

Approved Executive 2 papers

Cabinet (Pre-Intervention approved this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

- That the submission by the SYPTE on behalf of the project partners of a ‘best and final funding bid’ (BAFFB) to the Department of Transport be approved for the implementation of the BRT North scheme, with the bid to seek £19.406m from the Department of Transport towards the total scheme cost of £36m. (The Mayor agreed to the exemption from call-in on 7th September, 2011 in order to enable the bid to be received by the Department for Transport by 12 Noon on 9th September, 2011, as failure to submit the bid would mean that the Department for Transport would not consider the scheme further)
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Cabinet (Pre-Intervention, 6 pages

Summary

The report outlines the current position relating to the Bus Rapid Transit ‘North’ Major Scheme, which is currently in the Department for Transport’s (DfT) ‘development pool’ of schemes that are required to submit a ‘best and final funding bid’ by the 9 September 2011. It outlines developments since late October 2010, following the Comprehensive Spending Review, the revised costs and associated quantified risks contained within the estimate and highlights those elements of the scheme for which Rotherham Metropolitan Borough Council will have responsibility.

Recommendations

i) Members approve the submission by the SYPTE on behalf of the project partners of a ‘best and final funding bid’ (BAFFB) to the DfT for the implementation of the BRT North scheme, with the bid to seek £19.406m from the DfT towards the total scheme cost of £36m.

ii) The agreement of the Mayor be sought to exempt this from the provisions of the call in procedure on the grounds that it is urgent. The BAFFB and documentation for the scheme must be received by the DfT by 12 noon on 9 September 2011, failure to submit the bid would mean that the DfT would not consider the scheme further. 7. Proposals and Details

Background On 1 March 2010 Cabinet Member for Economic Development, Planning and Transportation approved the submission of Major Scheme Business Cases (MSBC) to the Department for Transport (DfT) seeking funding for two Bus Rapid Transit schemes. (Minute Number G124 refers). The two BRT schemes were:

BRT North – which would operate a limited stop service from Rotherham to Sheffield via Templeborough, Meadowhall (under the Tinsley Viaduct on a new Fixed Link), Carbrook, Attercliffe and loop around the City Centre – serving end to end trips but also new development in the Lower Don Valley.

BRT South – which would operate a limited stop service from Rotherham to Sheffield via Canklow, Brinsworth, Waverley (stopping at the proposed Waverley Interchange and Park & Ride), on the A630 Parkway to loop around the City Centre – serving end to end trips but also key development sites in Waverley.

The BRT projects are jointly promoted by South Yorkshire Passenger Transport Executive (SYPTE), RMBC and Sheffield City Council (SCC). Within the Project team the PTE take a lead on the overall project management of the scheme, and the bus service matters, with both RMBC and SCC leading on those elements of the schemes within their respective districts referred to as ‘Work Packages’. The Project Board comprises of senior officers from each of the Districts and is chaired by the Director General of SYPTE.

In March 2010 the Major Schemes Business Case (MSBC) for BRT North was submitted to DfT. In June 2010, as part of the Comprehensive Spending Review, the process for “major” spending was suspended for review. The MSBC for the BRT South scheme was not submitted to the DfT before the major scheme process was suspended and the DfT would not accept any further submissions and would only consider the MSBC for BRT North.

In October 2010, the new process was revealed. The BRT North project was in the “pre-qualification pool”. In December 2010, an Expression of Interest (EOI) form was submitted to DfT for BRT North to be considered for inclusion in the ‘Development Pool’.

In February 2011, the DfT announced this had been successful and the project was in the “Development Pool” of projects. This pool was at that time oversubscribed by about 1:1.5. Since then the Project team have been working to improve the project, ready for submission of the ‘best and final funding bid’ (BAFFB) to DfT by 9th September 2011.

The benefits of BRT North

The primary objectives of the BRT North scheme is:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bus Rapid Transit North: Submission of Major Scheme Best and Final Funding BidReport 6 pages DownloadRead as text
PDF
Rapid Bus Transit AttachmentReport 1 pages Download

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Bus Rapid Transit North - Submission of Major Scheme Best and Final Funding BidThis decision
  2. Bus Rapid Transit - Major Scheme Business Cases (Northern and Southern Routes)Approved
  3. Sheffield to Rotherham Bus Rapid Transit SchemeNoted
  4. Sheffield to Rotherham Bus Rapid Transit SchemeNoted
  5. Bus Rapid Transit Northern Route - Full Approval and Collaboration and Funding AgreementApproved

More from Rotherham Cabinet (Pre-Intervention

All decisions
MeetingDecisionOutcome
2 Jun 2004 IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... Approved Open
2 Jun 2004 Questions from Members of the Public.It was agreed to provide a detailed answer in writing. Agreed Open
2 Jun 2004 Awards- That Members and staff involved be congratulated on these achievements. Decided Open
2 Jun 2004 John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . Decided Open
2 Jun 2004 Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies