Resolved
Resolved :- (1) That the revised corporate risk register summary be noted. (2) That the current assessment of the Council’s top four corporate risks be confirmed. (3) That any further risks identified and be added to the risk register.
Cabinet (Pre-Intervention noted this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- (1) That the revised corporate risk register summary be noted. (2) That the current assessment of the Council’s top four corporate risks be confirmed. (3) That any further risks identified and be added to the risk register.
Attached to this report is the new look corporate risk register summary. The summary shows the risks associated with the Council’s most significant priorities and projects, and actions being taken to mitigate these risks.
Following comments from Cabinet, the risk register has been streamlined to emphasize the Council’s most significant risks and key actions and developments relating to these risks.
Not surprisingly, the Council’s key current risks relate to the financial pressures faced by the Council. Management actions are being taken to mitigate these and other risks in the register.
Cabinet is asked to:
• note the revised corporate risk register summary attached at Appendix A
• confirm the current assessment of the Council’s top four corporate risks
• indicate any further risks that it feels should be added to the risk register 7 Proposals and Details
7.1Format
This report contains the latest position on the Corporate Risk Register. The format of the report and corporate risk register summary, attached at Appendix A, has been changed to reflect comments made by Cabinet.
The covering report highlights the top four inherent risks. The corporate risk register summary reflects the current risk assessments for each corporate priority or project in the corporate risk register.
There are 3 overall categories of risk (RED, AMBER, GREEN) representing varying degrees of exposure. Each category contains a range of risk scores, so there are varying degrees of risk within each category. Appendix A shows the risk category and score for each priority or project included in the register before and after risk mitigation actions.
7.2Top four inherent risks The new risk register summary now shows risks in descending inherent risk order, to emphasize the most significant risks faced by the Authority. The top four inherent risks are:
• Managing Government budget reductions - unable to maintain key services due to budgetary limits. Cabinet and Strategic Leadership Team are meeting on a regular basis to consider the options available and, ultimately, Cabinet will make decisions that ensure the Council can provide priority services within available resources.
• Unable to deliver effective Children’s Services within budget. Ongoing action is being taken by management to provide services within the budget available. Cabinet is being kept informed of the relevant financial challenges as part of the budget monitoring and budget setting processes and makes decisions accordingly.
• Funding of the Digital Region Project to provide comprehensive broadband facilities across South Yorkshire The company (Digital Region Ltd), four South Yorkshire Councils and Government Department for Business, Innovation and Skills are continuing to work on plans to ensure the ongoing viability of the project.
• Sustaining improvement in Children’s Services post DFE intervention Relevant monitoring and scrutiny of progress is being conducted by Members and management, and action plans varied according to any emerging issues. Good progress is being made and reflected in positive outcomes and inspection feedback. The summary at Appendix A provides more details of the actions being taken to mitigate these and other risks recorded in the corporate risk register. 8. Finance
The risks contained in the register require ongoing management action. In some cases additional resources may be necessary to implement the relevant actions or mitigate risks. Any additional costs associated with the risks should be reported to the Strategic Leadership Team and Members for consideration on a case by case basis.
9. Risks and Uncertainties
It is important to review corporate risks on an ongoing basis, to ensure risks relating to the Council’s key projects and priorities are effectively monitored and managed by the Strategic Leadership Team and Members.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk RegisterReport | 8 pages | DownloadRead as text |
Follow Cabinet (Pre-Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2004 | IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... | Approved | Open |
| 2 Jun 2004 | Questions from Members of the Public.It was agreed to provide a detailed answer in writing. | Agreed | Open |
| 2 Jun 2004 | Awards- That Members and staff involved be congratulated on these achievements. | Decided | Open |
| 2 Jun 2004 | John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . | Decided | Open |
| 2 Jun 2004 | Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.