CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rotherham Metropolitan Borough Council
Audit Committee, Friday 23 July 2004

Risk Management Action Plan

Decided Finance 3 papers

Audit Committee decided this item on Friday 23 July 2004. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Resolved :- ( i ) That arrangements be made for Cabinet and Corporate Management Team to receive reports on a quarterly basis on how risks are being managed, the reports to include analysis details. (ii) That portfolio holders report to Cabinet on the management of risks identified for their relevant Programme Area. (iii) That Cabinet receive details of the top ten risks for the Authority and the top ten risks for each Programme Area and how they were being managed. (iv) That appropriate training on Risk Management be arranged for members. (v) That Scrutiny Panels be involved with all aspects of Risk Management .. (vi) That having regard to the recommendations of the Audit Commission in respect of SWIFT, its performance be considered by the Social and Community Support Scrutiny Panel, the outcome and findings to be reported to this Audit Committee.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Audit Committee

audit 2003/2004

Performance audit follow-up (April 2004) Rotherham Metropolitan Borough Council

INSIDE THIS REPORT

PAGES 2 - 5

Summary Report • Introduction • Audit approach • Risk management: main conclusions • Waiting list for occupational therapy assessments: main conclusions • IT standards and security: main conclusions

PAGES 6 - 21

Appendices • Appendix 1 - Action plan progress - Risk management • Appendix 2 – Action plan progress – Waiting list for occupational therapy assessments • Appendix 3 - Action plan progress – IT standards and security

Reference: RO009-13-2004

Date: June 2004 audit 2003/2004 SUMMARY REPORT

Introduction As part of our work each year we follow up recommendations made in previous performance audit and management arrangements studies. This ensures that benefits gained from the recommendations are being achieved or, if not, that the matter can be drawn to the attention of the Council. As part of our audit risk assessment this year we have selected the following studies for follow-up: • risk management • waiting list for occupational therapy assessments • IT standards and security.

Audit approach We have assessed progress through discussions with officers and a review of Council documents. The follow-up of our work on Occupational Therapy has also involved discussion with managers within the PCT.

Risk management: main conclusions Progress against the agreed action plan arising from the study has been poor.

Good progress has been made by the Council in achieving compliance with Association of Local Authority Risk Managers (ALARM) standards and the Council has improved its risk management infrastructure in terms of systems and processes. These achievements have been recognised by a national ALARM award.

However implementation of corporate processes and systems is weak. After initial activity in 2002, little has been followed through in Programme Areas; positive corporate initiatives have not resulted in actions across the Council. Moreover there is significant evidence that the Council is not embedding risk management or achieving a risk management culture. Risk management is still the preserve of a relatively few number of officers within the centre of the Council or in key ‘risk’ areas such as health and safety; social services and highways.

Many of the agreed recommendations in the action plan have either only been progressed in a limited way or have not been completed. Key areas for improvement now are:

• addressing fundamental weaknesses with risk registers. Risk registers need to be brought up-to-date and robust monitoring and review arrangements need to be established as a priority • establishing a clear role for Members in risk management; ensuring that Members are informed and consulted on strategic risks • defining an action plan to complement the corporate risk management strategy. The strategy needs to be supported by clear timescales; statements on resourcing and responsibilities for delivery • focusing strategies and action plans less on process and more on embedding a risk management culture. Strategies for engaging programme areas more widely in risk management need to be developed.

The majority of our original recommendations were concerned with integrating risk management more fully into the work of the Council, rather than it being seen solely as the concern of corporate risk managers. Fundamentally this is still the issue facing the Council one year later.

Performance audit follow-up (April 2004) – Audit Rotherham Metropolitan Borough Council – Page 2 2003/2004 audit 2003/2004 SUMMARY REPORT

Appendix 1 (attached) provides an update on each of our recommendations agreed in the action plan of May 2003. Exhibit 1 summarises progress as at the end of March 2004.

EXHIBIT 1 RISK MANAGEMENT: SUMMARY OF PROGRESS AFTER 1 YEAR

Progress on agreed actions has been poor with only 4 of the 20 recommendations having been completed or good progress having been made.

Limited progress Some progress Good progress Complete

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RO009-13-2004Report 119 KB DownloadRead as text
PDF
Risk Management Action PlanReport 62 KB Download
PDF
corp gov matrix for audit: july 2004Report 56 KB Download

At this meeting

Whole meeting

Who was there

8 of 14 attended
JM
Councillor John Michael ClarkeMember, apologies
RS
Councillor Robin StonebridgeChairman, present
JD
Councillor John DoyleMember, present
DH
Councillor David HallMember, present
MH
Councillor Mahroof HussainMember, present
NL
Councillor Neil LicenseMember, apologies
AR
Councillor Ann RussellMember, present
RS
Councillor Richard S. RussellMember, apologies, sent representative
CS
Cath SaltisMember, expected
AS
Councillor Alex SangsterMember, present
IS
Councillor Iain St. JohnMember, present
GW
Councillor Glyn WhelbournMember, apologies

All 14 on the meeting page

On this subject at Rotherham

Search all
  1. Risk Management Action PlanThis decision
  2. Risk Management Annual Summary 2025-2026 and Corporate Strategic Risk Register UpdateDecided
  3. Risk Management Directorate Presentation - Finance and Customer ServicesNoted
  4. Risk Management Guide Refresh 2025Noted
  5. Risk Management Directorate Presentation - Regeneration and EnvironmentNoted
  6. Risk Management Directorate Presentation - Adult Care, Housing and Public HealthNoted

More from Rotherham Audit Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Exclusion of the Press and Public- That, under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for... Decided Open
24 Sep 2026 Minutes of the previous meeting held on 28th July, 2026- That the minutes of the previous meeting of the Audit Committee be approved as a correct record of proceedings. Approved Open
24 Sep 2026 External Audit Progress Report and Sector Update- That the progress and sector updates be noted. Noted Open
24 Sep 2026 Code of Corporate Governance- That the refreshed version of the be received and noted. Noted Open
24 Sep 2026 Anti-Money Laundering Policy Review- (1) That the revised Anti-Money Laundering Policy be received and noted. (2) That the actions being undertaken to r... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies