Erection of 6 x 132m wind turbines and 80m anemometer mast at land at Penny Hill Lane, Ulley (RB2009/0824)

Deferred Planning

Planning Board deferred this item on Thursday 12 August 2010. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

- That consideration of application RB2009/0824 be deferred to enable issues identified to be properly addressed, as requested in a letter received this morning, which was circulated to all Members of the Planning Board that were present, from DLA Piper UK LLP. The letter indicated DLA Piper’s consultation with counsel and their potential grounds for a challenge relating to the treatment of European protected species and noise.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Erection of 6 x 132m wind turbines and 80m anemometer mast at land at Penny Hill Lane, Ulley (RB2009/0824)This decision
  2. Courtesy Consultation from Doncaster MBC - Erection of One Wind Turbine and associated infrastructure at Conisbrough Grange Farm, Common Lane, Ravenfield (RB2015/1023)Noted
  3. Courtesy Consultation from Doncaster MBC - Erection of One Wind Turbine to replace existing at land adjacent to Ridgewood Farm, Cockhill Field Lane, Braithwell, Doncaster (RB2015/1092)Noted
  4. Courtesy Consultation in respect of the erection of one wind turbine (34.4m high) and associated works at Glen Quarry Ruddle Mill Lane Hirst Lane Stainton for Urban Wind Ltd. (RB2014/0261)Decided
  5. Courtesy Consultation in respect of the erection of one wind turbine (79m high) and associated works with installation of transformer/substation enclosure, formation of crane hardstanding area and creation of new access on approx 0.51 ha ofDecided
  6. Courtesy Consultation - Erection of a 500k Single Wind Turbine at land at Moor Lane, Great Houghton, Barnsley (RB2013/1378)Decided

More from Rotherham Planning Board

All decisions
MeetingDecisionOutcome
29 Oct 2026 Minutes of the previous meeting held on 8th October 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 8 th October, 2026, be ... Approved Open
29 Oct 2026 Development Proposals- (1 ) That , on the development proposals now considered, the requisite notices be issued and be made available on t... Approved Open
29 Oct 2026 Report of the Service Director for Planning, Regeneration and Transport - Whitestone Solar Farm - Nationally Significant Infrastructure Project Update- That the update be received and the contents noted. Noted Open
8 Oct 2026 Minutes of the previous meeting held on 17th September, 2026- That the minutes of the previous meeting of the Planning Regulatory Board held on Thursday, 17 th September, 2026, ... Approved Open
8 Oct 2026 Development Proposals- (1) That, on the development proposals now considered, the requisite notices be issued and be made available on the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies