Courtesy Consultation in respect of the erection of one wind turbine (79m high) and associated works with installation of transformer/substation enclosure, formation of crane hardstanding area and creation of new access on approx 0.51 ha of
DecidedPlanning1 paper
Planning Board decided this item on Thursday 20 February 2014. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That Doncaster Metropolitan Borough Council be thanked for giving this Council the opportunity to comment on this planning application. (2) That Doncaster Metropolitan Borough Council be advised:- (a) of this Council’s concerns about the limited publicity provided in respect of this application; (b) of the extent of objection, amongst local residents in the area near to the application site, because of the impact of the proposed development upon the local environment in this part of Hellaby and Maltby; and (c) that, whilst this Council has no objections to the proposed development, subject to the relevant comments from the Transportation Unit, Environmental Health and Public Rights of Way Officers being taken into consideration as part of the determination of the application, a full assessment of the cumulative impact of the proposed turbine and of the one proposed off Hellaby Lane should also be taken into account in the determination of the application.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Rotherham MBC has been consulted on the above planning application submitted to Doncaster Council. This is a ‘courtesy’ consultation as required due to the close proximity of Rotherham Borough to the application site which is across the boundary in Doncaster. RMBC are invited to provide DMBC with comments on the application and the impact of the proposal on Rotherham. Members may recall that a previous courtesy consultation (our ref. RB2013/0166) was received from Doncaster relating to a proposed wind turbine, of similar specifications, on Fieldhouses Farm land, approximately 550 metres to the west of the site proposed by this application. The proposal was presented to members on 25 April 2013.
Members Resolved:- (1) That Doncaster Metropolitan Borough Council be thanked for giving the Council the opportunity to comment on the planning application. (2) That Doncaster Metropolitan Borough Council be advised that this Council had no objections to the proposed development, subject to adequate publicity and that the relevant comments from the Transportation Unit and Environmental Health be included.
At the time of writing this report Doncaster Council have advised that the application is still undetermined, however they have stated that the current proposal is a separate application and not a replacement for the previous application.
Site Description & Location
The site of application is an area of arable farm land to the east of the M18 Motorway, and is located to the east of Fordoles Head Lane inside the Doncaster Borough Council’s boundary. To the west of the motorway is further arable farm land within Rotherham. To the south and south east of the site are residential properties on the northern edge of Maltby
The nearest sensitive properties within the Rotherham Borough are: • The dwellings situated on the northern side of Braeburn Close, Empire Drive and Egremont Rise in Maltby which are approximately 570 metres away.
Proposal
The application is for the erection of a single three blade wind turbine 51m to the hub and 79m to the blade tip, with a blade length of 28m, which is indicated to be located to the east of Fordoles Head Lane, approximately 775m to the east of the M18 motorway and 448m to the south of Moor Lane. The blades are made from glass reinforced plastic which are expected to be coloured pale grey. The turbine foundations are indicated to measure approximately 12 metres in diameter.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Courtesy Consultation in respect of the erection of one wind turbine (79m high) and associated works with installation of transformer/substation enclosure, formation of crane hardstanding area and creation of new access on approx 0.51 ha of land at Fordoles Farm House, Marsh Hill, Micklebring for FoReport
82Courtesy Consultation in respect of the erection of one wind turbine (79m high) and associated works with installation of transformer/substation enclosure, formation of crane hardstanding area and creation of new access on approx 0.51 ha ofThis decision
Courtesy Consultation in respect of the erection of one wind turbine (79m high) and associated works with installation of transformer/substation enclosure, formation of crane hardstanding area and creation of new access on approx 0.51 ha ofThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.