Resolved
- That the current position in respect of the action plan be noted.
The Former Performance and Scrutiny Overview Committee noted this item on Friday 8 October 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the current position in respect of the action plan be noted.
The purpose of the Procurement Strategy is to set out how the Council intends to procure its goods, works and services in order to support the Authority’s overall aims and objectives over the life span of the Strategy. It outlines the Council’s current position and clearly points to areas where we need to improve with a supporting action plan to deliver those areas. The action will be managed by the Council’s Procurement Panel.
The Strategy is aligned with the Council’s Corporate Commissioning Framework which examines how the Council can strategically pull together all commissioning activity to ensure maximum gain from any efficiencies that may be generated.
That the current position in respect the action plan is noted. 7. Proposals and Details
The Strategy action plan is set out in 9 themes in line with the Procurement Strategy:
• Supporting the Local Economy • Engaging with the Voluntary and Community Sector • Equality and Diversity • Fairtrade and Trade Justice • Environmentally Friendly Procurement • Legal Procurement • e-Procurement • Achieving Value for Money • Building Capacity
Actions within the plan span the life of the Strategy and therefore many are not yet due to commence.
Full details of all actions are attached at Appendix A.
7.1Supporting the Local Economy
Of the 3 actions within this theme, 2 are complete and 1 ongoing across the life of the strategy.
7.2Engaging with the Voluntary and Community Sector
Of the 3 actions within this theme, 1 is complete and 2 have dates to be confirmed. These latter actions are currently rated red as work is ongoing to resolve resource issues and there is potential that Voluntary Action Rotherham may be able to deliver against these actions on behalf of RMBC.
7.3Equality and Diversity
Of the 7 actions within this theme, 3 are complete, 3 are amber with work either ongoing or due later in the life of the plan and1 action is listed as red.
The red action relates to publishing examples of good practice on the procurement pages of the website, however none have been received.
1 completed action relates to investigating how SCMS can be used to provide E&D data on suppliers. Whilst investigations are complete, SCMS is unable to provide this information in a suitable report.
7.4Fairtrade and Trade Justice
Of the 3 actions within this theme, 2 are complete and 1 is amber with work ongoing.
7.5Environmentally Friendly Procurement
Of the 11 actions within this theme, 6 are complete and 5 are amber with work either ongoing or due later in the life of the plan.
2 In respect of the Sustainable Procurement and Commissioning Code of Practice, work is ongoing to update the draft following consultation and the revised update will be presented to October’s Procurement Panel.
7.6Legal Procurement
Of the 3 actions within this theme 2 are complete and 1 is amber with work ongoing.
7.7e-Procurement
Of the 2 actions within this theme, 1 is complete and 1 is amber with work ongoing.
7.8Achieving Value for Money
Of the 6 actions within this theme, 5 are complete and 1 is amber with work ongoing across the life of the plan.
7.9Building Capacity
The single action within this theme has a completion date for later in the life of the plan however it should noted that this action is dependant on actions 2.02 and 2.03 which are currently rated red.
8. Finance
All costs for implementing the Corporate Procurement Strategy are currently being absorbed within existing budgets though some unbudgeted costs may arise and funding sources may need to be identified.
9. Risks and Uncertainties
If the actions in the above plan are not met the refreshed Corporate Procurement Strategy may not be fully implemented and embedded across the Council which could impact on the Council’s ability to evidence value for money.
10. Policy and Performance Agenda Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Procurement Strategy Action PlanReport | 10 pages | DownloadRead as text |
Follow The Former Performance and Scrutiny Overview Committee at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Apr 2011 | Corporate Risk RegisterResolved :- That the updated summary, attached at Appendix A to the report, be noted. | Noted | Open |
| 27 Apr 2011 | Review of Overview and Scrutiny- That the information be noted. | Noted | Open |
| 27 Apr 2011 | Rewriting the Script : Preparing Overview and Scrutiny for the" New Localism"Resolved :- That the information be noted. | Noted | Open |
| 27 Apr 2011 | Councillor Jane AustenResolved :- That Councillor Austen be thanked for her services to the Council and scrutiny in particular and she be w... | Decided | Open |
| 8 Apr 2011 | Date of Next MeetingResolved :- That the next meeting scheduled for 29th April be rearranged to Wednesday, 27th April, 2011 commencing at... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.