Rotherham Metropolitan Borough Council

Procurement Strategy Action Plan

Noted Scrutiny 1 paper

The Former Performance and Scrutiny Overview Committee noted this item on Friday 17 December 2010. Below is the council's own wording, with the papers it was decided on.

Item97

Resolved

Resolved :- That the current position in respect of the action plan be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to The Former Performance and Scrutiny Overview Committee, 11 pages

Summary

The purpose of the Procurement Strategy is to set out how the Council intends to procure its goods, works and services in order to support the Authority’s overall aims and objectives over the life span of the Strategy. It outlines the Council’s current position and clearly points to areas where we need to improve with a supporting action plan to deliver those areas. The action plan is managed by the Council’s Procurement Panel.

The Strategy is aligned with the Council’s Corporate Commissioning Framework which examines how the Council can strategically pull together all commissioning activity to ensure maximum gain from any efficiencies that may be generated.

Recommendations

That the current position in respect the action plan is noted. 7. Proposals and Details

The Strategy action plan is set out in 9 themes in line with the Procurement Strategy:

• Supporting the Local Economy • Engaging with the Voluntary and Community Sector • Equality and Diversity • Fairtrade and Trade Justice • Environmentally Friendly Procurement • Legal Procurement • e-Procurement • Achieving Value for Money • Building Capacity

Actions within the plan span the life of the Strategy and therefore many are not yet due to commence. Procurement Panel have requested a full review of the Procurement Strategy action plan in early 2011 to assess whether outstanding actions remain relevant and achievable given changes in resources.

Full details of all actions are attached at Appendix A, but in summary of the 39 actions contained within the plan: 22 are status green and complete; 13 are status amber with work ongoing or a due date later in the life of the plan; and 3 are status red.

7.1Supporting the Local Economy

Of the 3 actions within this theme, 2 are complete and 1 ongoing across the life of the strategy. The ongoing action is to deliver Meet the Buyer events in 2011 and 2012. Work is progressing on the 2011 event to be held on 10th March 2011 at Magna; this will be a joint event in conjunction with the Rotherham Enterprise Event.

7.2Engaging with the Voluntary and Community Sector

Of the 3 actions within this theme, 1 is complete and 2 have dates to be confirmed. These latter actions are currently rated red as work is ongoing to resolve resource issues around resourcing these actions. A meeting has been held to progress these actions which has resulted in interim guidance being circulated. How to fully deliver these actions will be considered as part of the wider review of the Strategy action plan.

7.3Equality and Diversity

Of the 7 actions within this theme, 3 are complete, 3 are amber with work either ongoing or due later in the life of the plan and1 action is listed as red.

The red action relates undertaking equality and diversity audits of key suppliers; to date this work has not been taken forwards due to lack of resource, but discussions are ongoing as to how to resolve issues and deliver the outcomes of the plan. Again, how to deliver this action will be considered as part of the wider review.

2 7.4 Fairtrade and Trade Justice

Of the 3 actions within this theme, 2 are complete and 1 is amber with work ongoing.

7.5Environmentally Friendly Procurement

Of the 11 actions within this theme, 6 are complete and 5 are amber with work either ongoing or due later in the life of the plan.

7.6Legal Procurement

Of the 3 actions within this theme 2 are complete and 1 is amber with work ongoing.

7.7e-Procurement

Of the 2 actions within this theme, 1 is complete and 1 is amber with work ongoing.

7.8Achieving Value for Money

Of the 6 actions within this theme, 5 are complete and 1 is amber with work ongoing across the life of the plan.

7.9Building Capacity

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement Strategy Action PlanReport 11 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Procurement Strategy Action PlanThis decision
  2. Procurement StrategyNoted
  3. Procurement Strategy Action Plan ReviewNoted
  4. Procurement Strategy - Red Status ActionsNoted
  5. Procurement Strategy Action PlanNoted
  6. Procurement Strategy Action Plan.Noted

More from Rotherham The Former Performance and Scrutiny Overview Committee

All decisions
MeetingDecisionOutcome
27 Apr 2011 Corporate Risk RegisterResolved :- That the updated summary, attached at Appendix A to the report, be noted. Noted Open
27 Apr 2011 Review of Overview and Scrutiny- That the information be noted. Noted Open
27 Apr 2011 Rewriting the Script : Preparing Overview and Scrutiny for the" New Localism"Resolved :- That the information be noted. Noted Open
27 Apr 2011 Councillor Jane AustenResolved :- That Councillor Austen be thanked for her services to the Council and scrutiny in particular and she be w... Decided Open
8 Apr 2011 Date of Next MeetingResolved :- That the next meeting scheduled for 29th April be rearranged to Wednesday, 27th April, 2011 commencing at... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies